1) Using the 50-50 Rule, what is earned value for this project?
2) Using the 0-100 Rule, what is earned value for this project?
3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
5) What is the schedule performance index (SPI)?
6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
7) What is the cost performance index (CPI)?
8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.
Writer have done good job. Assignment was given much earlier than dateline. good structure and layout..
Looking for corporate assignment help? Then MyAssignmenthelp.com is your one-stop answer. We render custom-made assistance with corporate as well as with IT assignment. We are available 24*7 to offer operating system, database, MATLAB, web development and lots of other IT subject based assignment help. We work round the clock to ensure 100% students satisfaction with our delivered service and to make sure that students get assistance on urgent basis.
Just share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
thank you so much I get exactly what i need from first time the Dr. thank me that i make something unique and defrrant from the other students .thank you so much
Australia
Able to get my work done after few changes, which were done as per suggestion provided by us. Appreciate their positive approach for this
Australia
Amazing experience with you guys. I got 20/20. You are the best in the market i tried multiple sites but you guys gave best output.
Australia
good paper, thank you very much. i am looking forward to working with you. Recommended
Australia