6007ENG-Project Plan For Houses In Mumbai

tag 2 Downloads9 Pages / 2,245 Words tag Add in library Click this icon and make it bookmark in your library to refer it later. GOT IT
  • Course Code: 6007ENG
  • University: Griffith University
  • Country: Australia

Question:

Prepare a Project Plan Planning. Discuss most eventualities that could occur during the project. 

 

Answer

Project Background

General background

The project is based on construction work of minimum of 500 houses in Mumbai, India for the poor people. The construction work is used to manage modular construction for getting better result than the normal construction procedures. The main aim of the project plan is to fulfill needs of the poor people and satisfy by providing possible project outcomes. The duration of the construction work is 3 years. The construction work uses modular construction in which the house is constructed off-site by means of same materials and designing same codes plus standards for built facilities.   

Significance and justification of project

The construction work is included of modular techniques which allow the builders to keep positive cash flow without risk of the project client takes control of goods on the land. Modular construction is built to suit the existing architecture style furthermore trends. The houses are sustainable and supportive housing which are built for homeless and poor people so that they can get houses to stay.

Purpose of the Project

The purpose of the project plan is to outline the project scope, time, cost and quality for design and construction work of building. There are also significant risks associated with this project work which is mitigated on time for project success. The completion of this plan will allow the project team to finalize the detailed construction project schedule. In this project DFMA method is used, which stand for Design for Manufacture and Assembly, which is combination of two of the construction methods such as Design for Manufacture and Design for Assembly. Design for manufacture means design for ease of the manufacturing of the parts that can form the product. Design for assembly means design of the product for ease of assembly. This method is used for the construction of 500 houses in Mumbai as it provides guidance to the designing team to simplify the structure of product. It is also used as benchmarking tool for studying products of competitors and cost tool for assisting in the supplier negotiations. Following are the objectives of this project:

  • To design 500 houses in Mumbai, India for the poor people
  • To provide new sources for the revenue by attracting the local residents and members of the building
  • To use DFMA method and modular construction techniques in the construction work of houses
  • To estimate future requirements of the construction techniques
  • To meet with specific requirements of the construction work of the building work
  • To ensure for providing sustainable building work

Expected Project Outcomes

In the construction work of 500 building houses for poor people, the main design frameworks are included such as:

  • A detailed review of the construction policies and standards which are included document specific to the design of the houses.
  • There are checklists for the project design stages from planning phase to construction stage consists of drawings and blueprints to guide the team members.
  • There is also training manual required for the project based on the construction related work.
  • AutoCAD customization is used in the construction project plan specific to the internal project requirements for the client deliverables.

After the completion of the project work, it is expected that the project manager manages the project risks and issues and there is proper interaction among the project stakeholders. A risk management program is created which can mitigate identified risks to make an effectiveness of the current risk management approaches for the company. There is development of professional practice skills for the construction work. 

 

Methodology to be Adopted and Project Schedule

Methodology

In this research study, academic research is adopted to evaluate the risk management strategies to assist in the development and construction work. There is investigation of current construction standards of India which will focus to make sure that the program is related to exiting construction industry requirements. Risk management methods will conduct to determine the project risks, issues and programs which are available in the market. In this construction work, DfMA is a design approach which is focused on ease of the manufacture plus efficiency of the assembly. By simplification in design of the product, it is probable to assemble in addition to manufacture the work in minimum time and lower cost. The main principles related to DfMA are:

  • Minimization of the total number of the components like reduction of assembly cost and reduction of work-in-progress
  • Design of ease of the fabrication
  • Design of ease of assembly
  • Elimination and reduction of the designing adjustments into the product

Project schedule

WBS

Task Name

Duration

Start

Finish

0

Construction work of 500 houses in Mumbai

79 days

Tue 1/15/19

Fri 5/3/19

1

   Preliminary details

17 days

Tue 1/15/19

Wed 2/6/19

1.1

      Prepare the schedule for the project

2 days

Tue 1/15/19

Wed 1/16/19

1.2

      Contract the sub-contractors

2 days

Thu 1/17/19

Fri 1/18/19

1.3

      Material take off order

3 days

Mon 1/21/19

Wed 1/23/19

1.4

      Order the construction materials

5 days

Thu 1/24/19

Wed 1/30/19

1.5

      Review the materials

2 days

Thu 1/31/19

Fri 2/1/19

1.6

      Draw a blueprint of the construction work

3 days

Mon 2/4/19

Wed 2/6/19

2

   Start the project plan

24 days

Thu 2/7/19

Tue 3/12/19

2.1

      Site the preparation

3 days

Thu 2/7/19

Mon 2/11/19

2.2

      Set up the construction job

5 days

Tue 2/12/19

Mon 2/18/19

2.3

      Receive the building materials

4 days

Tue 2/19/19

Fri 2/22/19

2.3.1

         Sub floor plywood

4 days

Tue 2/19/19

Fri 2/22/19

2.4

      Demolition

10 days

Mon 2/25/19

Fri 3/8/19

2.4.1

         Interior dooring

5 days

Mon 2/25/19

Fri 3/1/19

2.4.2

         Exterior floor railing

2 days

Mon 3/4/19

Tue 3/5/19

2.4.3

         Tile the floor

1 day

Wed 3/6/19

Wed 3/6/19

2.4.4

         Kitchen cabinets

2 days

Thu 3/7/19

Fri 3/8/19

2.5

      Paneling

2 days

Mon 3/11/19

Tue 3/12/19

3

   Contracts the construction work

27 days

Wed 3/13/19

Thu 4/18/19

3.1

      Supply the construction agreement

2 days

Wed 3/13/19

Thu 3/14/19

3.2

      Supply the contract specifications

5 days

Fri 3/15/19

Thu 3/21/19

3.3

      Secure the project financing

3 days

Fri 3/22/19

Tue 3/26/19

3.4

      Document review and revision

5 days

Wed 3/27/19

Tue 4/2/19

3.5

      Review and finalize the plans

2 days

Wed 4/3/19

Thu 4/4/19

3.6

      Review and finalize the project specifications

4 days

Fri 4/5/19

Wed 4/10/19

3.7

      Review and finalize the site plan

2 days

Thu 4/11/19

Fri 4/12/19

3.8

      Approve the revised construction plan

3 days

Mon 4/15/19

Wed 4/17/19

3.9

      Approve the revised project specifications

1 day

Thu 4/18/19

Thu 4/18/19

4

   Design stage

6 days

Fri 4/19/19

Fri 4/26/19

4.1

      Design the building

2 days

Fri 4/19/19

Mon 4/22/19

4.2

      Construct the building as per project requirements

4 days

Tue 4/23/19

Fri 4/26/19

5

   Closure stage

5 days

Mon 4/29/19

Fri 5/3/19

5.1

      Final walk-through

2 days

Mon 4/29/19

Tue 4/30/19

5.2

      Final draft of the project work

3 days

Wed 5/1/19

Fri 5/3/19

Work breakdown structure

Figure 1: Work breakdown structure

(Source: Created by author using Ms Project)

Gantt chart

Figure 2: Gantt chart

(Source: Created by author using Ms Project)

Project tracking

The project is tracked using Gantt chart which is shown above so that the project manager can track the project so that it can be on time and is to be completed by due date.

Project deliverables 

Following are the deliverables of the construction project plan such as:

  • Project planning report
  • Customization plus tutorial manual on the DfMA method
  • Project report and work breakdown structure
  • Seminar presentation to the project team members
  • Risk management checklists
  • Poster and technical presentation
  • AutoCAD customization of the construction work

Project completion

The project management tools are used to complete the construction project work on time and it will require providing training to the staffs and project team members regarding DfMA. It provides knowledge to assist current plus future workers. Then, the productivity of the construction work increases so that it will complete on schedule time and budget.

Risk Assessment

Risk Assessment matrix

 

Likelihood

Consequences

Catastrophic

(Cat)

Major

(Maj)

Moderate

(Mod)

Minor

(Min)

Insignificant

(Ins)

Almost Certain

(AC)

Extreme

(E)

High

(H)

High

(H)

Medium

(M)

Low

(L)

Likely

(L)

High

(H)

High

(H)

Medium

(M)

Medium

(M)

Low

(L)

Possible

(P)

High

(H)

Medium

(M)- Financial risk

Medium

(M)- Socio-political risk

Low

(L)- Environmental risk

Low

(L)

Unlikely

(U)

Medium

(M)

Medium

(M)

Low

(L)- Logistics risk, Management risk

Low

(L)

Low

(L)

Rare

(R)

Medium

(M)- Technical risk

Low

(L)

Low

(L)

Low

(L)

Low

(L)

Identified Risks

Risk Assessment Table

Step 1: Identify the hazard/s

 

Step 2:Assess the risks, Consequence (C), Likelihood (L)& Risk Level.

(see Risk Matrix)

Step 3: List the controls needed to remove or reduce the risks.

What could cause harm?

What could go wrong?

C

L

Level

What controls are required

Technical risk: The technical risks are occurred which can restrict the construction work. It includes uncertainty of the resources, availability of the materials and inadequate site investigation.

It causes change in the project scope and project requirements. There are also design errors in building the houses.

Cat

R

M

Before the project manager starts the project work, then they should consult with the project team to hire possible resources and check the quality of the materials.

Logistical risks: The risks are included unavailability of the transportation facilities and equipments which are required for the construction work.

It causes huge delay in the construction project work and causes huge project losses.

Mod

U

L

Before the project manager starts the project work, they should make a stock of the project resources and materials required for the construction work.

Environmental risks: The risks are included natural disasters and seasonal implications which cause damage to the construction work. The risks are caused when the project team is unfamiliar with the local conditions of the construction site.

The weather risks cause entire damage to the construction of building. There is project delay and losses.

Min

P

L

The Construction professionals should have enough knowledge of the construction site and the local conditions of the site.

Management risks: It causes due to uncertainty in the productivity of the project resources.

Failing to hire skilled staffs can cause disastrous losses to the project.

Mod

U

L

Before staring the project work, it should ensure that the project team members can have sufficient skilled staffs with proper skills of construction work. The staffs should define their roles and responsibilities.

Financial risks: There are some financial risks are inflation, local taxes of the area in addition to availability plus fluctuation of the foreign exchanges. Those are incurred throughout the construction work.

The project is behind the estimated budget which can cause delay in the project work.

Maj

P

M

Before starting the project work, various countries have different taxes so that it requires taking account by the financial manager.

Socio-political risk: There are some customs plus import restrictions and also difficulties of the equipments which are considered as risks for the construction work of building.

There are different project regulations plus code of the construction so that there is project delay and losses.

Mod

P

M

Each of the construction projects is required to have similar codes plus regulations so that the work is completed successfully.

Ethics Issues Related to the Project

This IAP project is undertaken to be outside of the scope of the research ethics of the university as the work is to be done under the industry partner. There are no university papers which are used in the paper and outputs from the work excluded of the academic assessment of the course. The industry partner has being as intellectual property as the outputs is to arise from the work. 

 

Bibliography

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. Amacom.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Lock, D. (2017). The essentials of project management. Routledge.

Milosevic, D. Z., & Martinelli, R. J. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., & Segner, R. O. (2015). Construction project management. John Wiley & Sons.

Turner, R. (2016). Gower handbook of project management. Routledge.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Walker, A. (2015). Project management in construction. John Wiley & Sons.

Young, T. L. (2016). Successful project management. Kogan Page Publishers.

OR

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). Project Plan For Houses In Mumbai. Retrieved from https://myassignmenthelp.com/free-samples/6007eng-project-plan-for-houses-in-mumbai.

"Project Plan For Houses In Mumbai." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/6007eng-project-plan-for-houses-in-mumbai.

My Assignment Help (2020) Project Plan For Houses In Mumbai [Online]. Available from: https://myassignmenthelp.com/free-samples/6007eng-project-plan-for-houses-in-mumbai
[Accessed 24 May 2020].

My Assignment Help. 'Project Plan For Houses In Mumbai' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/6007eng-project-plan-for-houses-in-mumbai> accessed 24 May 2020.

My Assignment Help. Project Plan For Houses In Mumbai [Internet]. My Assignment Help. 2020 [cited 24 May 2020]. Available from: https://myassignmenthelp.com/free-samples/6007eng-project-plan-for-houses-in-mumbai.


MyAssignmenthelp.com has been satisfying students' needs over a decade now. With years of experience in providing assignment help, we are capable of understanding students' requirements better and fulfill them perfectly. To meet the students' needs, we have appointed 3000+ experts, who cover more than 100 subjects while assignment help. Some of our popular services include corporate finance assignment help, MATLAB assignment help, database assignment help, operating system assignment help and web development assignment help.

Latest Project Management Samples

PPMP20009 Leading Lean Projects 6

Download : 0 | Pages : 5

Answer: Weekly Portfolio Learning Table Topic and reading samples. Your personal learning outcomes from this unit. Learnings from your experience. Week 1 Success of a project is directly proportional to the contribution made by the heads of the project   Kerzner (2013) explained the success of a project can be measured through the actions undertaken by three group members including customer’s organ...

Read More arrow

CTEC2121 Organisations Project Management And Research

Download : 0 | Pages : 5
  • Course Code: CTEC2121
  • University: De Montfort University
  • Country: United Kingdom

Answer: Introduction PRINCE2 is a process based project management methodology that is used to implement a project in a controlled environment. In PRINCE2, the project is divided into a number of controllable units so that monitoring and project governance is done in a proper way. Since In PRINCE2, project is implemented in a controlled environment; it provides a greater control of the resources and the ability to manage the project risk more...

Read More arrow

BUSN8005 Project Accounting And Financial Management

Download : 0 | Pages : 5

Answer: Tangible and Intangible Costs A tangible cost is mainly described as a cost that is quantifiable that is related with an identified asset or source. Tangible costs are therefore used to represent the expenses that might arise as a result of purchasing the materials or renting an equipment for a project. The intangible cost on the other hand can be described as an unquantifiable cost that is related to an identifiable sources (Cañ...

Read More arrow

SBM3302 Project Execution Planning And Management

Download : 0 | Pages : 13

Answer: Project Title Project Execution Planning and Management of Refurbishing Project by MICC Enterprise. Introduction Execution time of a project is the considered as the baseline while developing the document as well as governing the document of project operation as well as management. The Project Execution Plan (PEP) helps to establish the proper terms that are to be included for meeting the scope of the project and fulfil all the cont...

Read More arrow

MNG00785 Project Management 2

Download : 0 | Pages : 11
  • Course Code: MNG00785
  • University: Southern Cross University
  • Country: Australia

Answer: Part 1: Project Charter Elements A project charter is defined as an overall basic plan for an upcoming project that serves as the predecessor to the full project plan and emphasizes on some of the basic but critical components of the project plan. In a project charter, there are a number of different elements that are discussed below with specific reference to literature. Project Scope and Objectives According to Kerzner and Kerzner...

Read More arrow
Next
watch

Save Time & improve Grade

Just share Requriment and get customize Solution.

question
We will use e-mail only for:

arrow Communication regarding your orders

arrow To send you invoices, and other billing info

arrow To provide you with information of offers and other benefits

1,316,470

Orders

4.9/5

Overall Rating

5,074

Experts

Our Amazing Features

delivery

On Time Delivery

Our writers make sure that all orders are submitted, prior to the deadline.

work

Plagiarism Free Work

Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.

time

24 X 7 Live Help

Feel free to contact our assignment writing services any time via phone, email or live chat.

subject

Services For All Subjects

Our writers can provide you professional writing assistance on any subject at any level.

price

Best Price Guarantee

Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.

Our Experts

Assignment writing guide
student rating student rating student rating student rating student rating 5/5

184 Order Completed

96% Response Time

Arapera Billing

Masters in Management, MMgt

Wellington, New Zealand

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

285 Order Completed

99% Response Time

Eugene Baranowski

MBA in Supply Chain

London, United Kingdom

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

154 Order Completed

97% Response Time

Harold Alderete

PhD in Economics

London, United Kingdom

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

93 Order Completed

100% Response Time

Jackson Mitchell

MiM (Masters in Management) in Supply Chain Management

New Jersey, United States

Hire Me

FREE Tools

plagiarism

Plagiarism Checker

Get all your documents checked for plagiarism or duplicacy with us.

essay

Essay Typer

Get different kinds of essays typed in minutes with clicks.

edit

GPA Calculator

Calculate your semester grades and cumulative GPa with our GPA Calculator.

referencing

Chemical Equation Balancer

Balance any chemical equation in minutes just by entering the formula.

calculator

Word Counter & Page Calculator

Calculate the number of words and number of pages of all your academic documents.

Refer Just 5 Friends to Earn More than $2000

Check your estimated earning as per your ability

1

1

1

Your Approx Earning

Live Review

Our Mission Client Satisfaction

The work was great I loves how fast the work was done. The prices was great it was not expensive

flag

User Id: 433071 - 24 May 2020

Australia

student rating student rating student rating student rating student rating

The expert didn't address all aspects of the assignment also didn't get my solution on time

flag

User Id: 430334 - 24 May 2020

Australia

student rating student rating student rating student rating student rating

Assignment looks amazing. I hope to score well. Will soon share my grades. I would recommend people like me who are working for livelihood and have studies to complete to take up this site as your best buddy.

flag

User Id: 432467 - 24 May 2020

Australia

student rating student rating student rating student rating student rating

Team My Assignment, you are the best. Assignment was done and submitted and as a result, grade marking was 80. Once again thanks so much

flag

User Id: 392423 - 24 May 2020

Australia

student rating student rating student rating student rating student rating
callback request mobile
Have any Query?