Introduction
Four partners have decided to initiate a start up business that will also include the use of an online website. Hence, the main problem is the significantly large scope of work in the project that will require significant amount of planning as well as funds. However, there is also the opportunity to start a well established business set up that will be instantly popular in the market.
Project Summary
In this project, a new office building will be rented or purchased for setting up the start up business operations centre and a human resource manager will be appointed to recruit personnel required for operations of the business. In addition, a website will be developed through which, the company will be able to operate online.
WBS
The work breakdown structure is shown in the following table as well as the diagram that follows.
WBS
|
Task Name
|
Duration
|
0
|
Start Up Business and Website Development
|
123 days
|
1
|
Project Discussion Phase
|
13 days
|
1.1
|
Call Meeting Between the Partners
|
1 day
|
1.2
|
Discuss Regarding the Possibility of Start Up Business
|
2 days
|
1.3
|
Analyze the Feasibility of the Business
|
4 days
|
1.4
|
Discuss about Possible Investment in the Business
|
2 days
|
1.5
|
Agree Upon the Project
|
3 days
|
1.6
|
Finalize the Project
|
1 day
|
2
|
Project Planning Phase
|
26 days
|
2.1
|
Determine the Final Goal of the Project
|
2 days
|
2.2
|
Project Charter
|
15 days
|
2.2.1
|
Determine Scope of the Project
|
1 day
|
2.2.2
|
Determine the Total Investment Required
|
2 days
|
2.2.3
|
Determine Time Required to Launch the Business
|
2 days
|
2.2.4
|
Assess and Mitigate Risks Associated with the Project
|
5 days
|
2.2.5
|
Develop a Suitable Roadmap for the Project
|
5 days
|
2.3
|
Project Team
|
8 days
|
2.3.1
|
Hire Development Team for Development of Company Website
|
6 days
|
2.3.2
|
Discuss with the Team Regarding the Website
|
2 days
|
2.4
|
Provide Approval
|
1 day
|
3
|
Project Initiation
|
12 days
|
3.1
|
Purchase / Rent Room for Start Up Office
|
5 days
|
3.2
|
Invest in Project for Development of Website and the Office
|
2 days
|
3.3
|
Hire Human Resource Manager for Recruitment
|
5 days
|
4
|
Project Execution
|
56 days
|
4.1
|
Set Up Office Room
|
15 days
|
4.2
|
Install Utilities and Requirements
|
10 days
|
4.3
|
Finalize the Start Up Business
|
5 days
|
4.4
|
Start Recruitment of Personnel
|
5 days
|
4.5
|
Set Up Management Team
|
4 days
|
4.6
|
Develop the Website
|
10 days
|
4.7
|
Test the Website
|
5 days
|
4.8
|
Website Go Live
|
2 days
|
5
|
Project Closing
|
16 days
|
5.1
|
Review Entire Project
|
5 days
|
5.2
|
Start Operations
|
10 days
|
5.3
|
Sign Off
|
1 day
|
Figure 1: Work Breakdown Structure of the Project
![]()
(Source: Created by Author)
Sign Off
Name
|
Signature
|
Mr. A
|
|
Mr. B
|
|
Mr. C
|
|
Mr. D
|
|
References
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Turner, J. R. (2014). Handbook of project-based management(Vol. 92). New York, NY: McGraw-hill.