Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

WBS for BLDG 2023:

WBS

Task Name

1

Construction of Plant-Office-Warehouse

1.1

   Site preparation and utilities

1.1.1

       Site preparation

1.1.1.1

          Land Preparation

1.1.1.2

          Temporary Office

1.1.2

       Utilities

1.1.2.1

          Construction of well

1.1.2.2

          Construction of Overhead Tank (200 CuM capacity)

1.1.2.3

          Sewage Line

1.1.2.4

          Electric Supply

1.1.2.4.1

             Under Ground

1.1.2.4.2

             Above Ground

1.2

   Foundation and concrete work

1.2.1

       Piling work

1.2.1.1

          Plant

1.2.1.2

          Warehouse

1.2.2

       Spread Footing

1.2.2.1

          Office Building

1.3

   Structural Work for plant and Warehouse

1.3.1

       Plant

1.3.1.1

          Structural Column

1.3.1.2

          Roofing

1.3.1.3

          Crane & Beam Erection

1.3.1.4

          Siding work

1.3.2

       Warehouse

1.3.2.1

          Structural Column

1.3.2.2

          Roofing

1.3.2.3

          Monorail & Beam erection

1.3.2.4

          Siding work

1.4

   Interior work for the plant and Warehouse

1.4.1

       Plant

1.4.1.1

          HVAC

1.4.1.2

          Lighting work

1.4.1.3

          Flooring

1.4.1.4

          Partition work

1.4.1.5

          Railroad Siding

1.4.2

       Warehouse

1.4.2.1

          HVAC

1.4.2.2

          Lighting work

1.4.2.3

          Flooring

1.4.2.4

          Partition work

1.5

   The structure and interior work for the office building

1.5.1

       Structure work

1.5.2

       Interior work

1.6

   Site Amenities

1.6.1

       Parking

1.6.2

       Flagpole

1.7

   Handover, practical completion and demobilization

List of Activities:

WBS

Task Name

1

Construction of Plant-Office-Warehouse

1.1

   Site preparation and utilities

1.1.1

       Site preparation

1.1.1.1

          Land Preparation

1.1.1.1.1

             Start Site Preparation work

1.1.1.1.2

             Cleaning of site from rubbish timber and bushes

1.1.1.1.3

             Surveying for plotting site contour

1.1.1.1.4

             Leveling (Cutting & Filling) to maintain slope as per design

1.1.1.2

          Temporary Office

1.1.1.2.1

             Erect Pre-Fabricated Frames

1.1.1.2.2

             Erect Pre-Fabricated Roof

1.1.1.2.3

             Flooring

1.1.1.2.4

             Office Internal work including Sanitary Lines

1.1.1.2.5

             Air Conditioning system

1.1.2

       Utilities

1.1.2.1

          Construction of well

1.1.2.1.1

             Apply and obtain administrative approval

1.1.2.1.2

             Boring

1.1.2.1.3

             Installation of pump

1.1.2.1.4

             Water testing

1.1.2.1.5

             Ready to use Well

1.1.2.2

          Construction of Overhead Tank (200 CuM capacity)

1.1.2.2.1

             Fix Frame / Structure on which tank shall rest

1.1.2.2.2

             Erect tanks of above capacity

1.1.2.2.3

             Fix all necessary plumbing lines

1.1.2.3

          Sewage Line

1.1.2.3.1

             Excavation in trapezoidal section throughout the layout of sewage line

1.1.2.3.2

             Earth filling to maintain proper slop as per design

1.1.2.3.3

             Laying of Sewage Pipeline

1.1.2.3.4

             Backfilling & proper Compaction as per standard

1.1.2.4

          Electric Supply

1.1.2.4.1

             Under Ground

1.1.2.4.1.1

                Excavation for Pole foundation, Manhole & Duct

1.1.2.4.1.2

                Construct Electrical Manhole 1

1.1.2.4.1.3

                Construct Electrical Manhole 2

1.1.2.4.1.4

                Cast & Place Electric Duct Bank

1.1.2.4.1.5

                Backfill Sand / Earth after Cable laying

1.1.2.4.2

             Above Ground

1.1.2.4.2.1

                Erect Power Incoming Poles

1.1.2.4.2.2

                Laying of cables

1.1.2.4.2.3

                Finish Site preparation and utilities work

1.2

   Foundation and concrete work

1.2.1

       Piling work

1.2.1.1

          Plant

1.2.1.1.1

             Start Foundation & Concrete work

1.2.1.1.2

             Boring (5 Nos.) up to 10 meter depth at every 15 meter c/c distance

1.2.1.1.3

             Piling (5 Nos.) of 10 meter depth at every 15 meter c/c distance

1.2.1.1.4

             Breaking of Pile head

1.2.1.1.5

             Bar Bending and fixing of Reinforcement for Plinth Beam

1.2.1.1.6

             Fixing Formwork

1.2.1.1.7

             Casting of Plinth beam

1.2.1.1.8

             Backfilling & Compaction

1.2.1.2

          Warehouse

1.2.1.2.1

             Boring (2 Nos.) up to 10 meter depth at every 15 meter c/c distance

1.2.1.2.2

             Piling (2 Nos.) of 10 meter depth at every 15 meter c/c distance

1.2.1.2.3

             Breaking of Pile head

1.2.1.2.4

             Bar Bending and fixing of Reinforcement for Plinth Beam

1.2.1.2.5

             Fixing Formwork

1.2.1.2.6

             Casting of Plinth beam

1.2.1.2.7

             Backfilling & Compaction

1.2.2

       Spread Footing

1.2.2.1

          Office Building

1.2.2.1.1

             Excavation for spread footing

1.2.2.1.2

             Pour lean concrete for leveling

1.2.2.1.3

             Reinforcement bending & Fixing

1.2.2.1.4

             Fixing Formwork

1.2.2.1.5

             Casting of footing

1.2.2.1.6

             Backfilling & Compaction

1.2.2.1.7

             Finish Foundation & Concrete work

1.3

   Structural Work for plant and Warehouse

1.3.1

       Plant

1.3.1.1

          Structural Column

1.3.1.1.1

             Start Structural Work for plant and Warehouse

1.3.1.1.2

             Erection of column at every 15 meter

1.3.1.1.3

             Alignment & Bolting column with Foundation

1.3.1.2

          Roofing

1.3.1.2.1

             Erection of Joist Steel Bars

1.3.1.2.2

             Placing Pre-Cast concrete Planks above Steel Bars

1.3.1.2.3

             Fix roofing sheet

1.3.1.3

          Crane & Beam Erection

1.3.1.3.1

             Erection of Girder above structural column from one end of plant to other

1.3.1.3.2

             Placing Crane Hoist above girder

1.3.1.3.3

             Arranging other miscellaneous work related to crane assembly

1.3.1.3.4

             Erection of Beam for Piping

1.3.1.4

          Siding work

1.3.1.4.1

             Fix insulated glass panel at top

1.3.1.4.2

             Fix insulated opaque panels at middle and bottom

1.3.2

       Warehouse

1.3.2.1

          Structural Column

1.3.2.1.1

             Erection of column at every 15 meter

1.3.2.1.2

             Alignment & Bolting column with Foundation

1.3.2.2

          Roofing

1.3.2.2.1

             Erection of Joist Steel Bars

1.3.2.2.2

             Placing Pre-Cast concrete Planks above Steel Bars

1.3.2.2.3

             Fix roofing sheet

1.3.2.3

          Monorail & Beam erection

1.3.2.3.1

             Erection of Monorail above structural column from one end of plant to other

1.3.2.4

          Siding work

1.3.2.4.1

             Fix insulated glass panel at top

1.3.2.4.2

             Fix insulated opaque panels at middle and bottom

1.4

   Interior work for the plant and Warehouse

1.4.1

       Plant

1.4.1.1

          HVAC

1.4.1.1.1

             Start Interior work for the plant and Warehouse

1.4.1.1.2

             Erect and install HVAC ducts with ceiling

1.4.1.2

          Lighting work

1.4.1.2.1

             Install & fix fluorescent light fixtures

1.4.1.3

          Flooring

1.4.1.3.1

             Compaction of sand below flooring level

1.4.1.3.2

             Cast Concrete Floor Slab

1.4.1.4

          Partition work

1.4.1.4.1

             Erect Concrete Block as partition wall to Construct Lunch area, Toilet, Locker room & Shop offices

1.4.1.5

          Railroad Siding

1.4.1.5.1

             Placing / Install railroad siding

1.4.2

       Warehouse

1.4.2.1

          HVAC

1.4.2.1.1

             Erect and install HVAC ducts with ceiling

1.4.2.2

          Lighting work

1.4.2.2.1

             Install & fix fluorescent light fixtures

1.4.2.3

          Flooring

1.4.2.3.1

             Compaction of sand below flooring level

1.4.2.3.2

             Cast Concrete Floor Slab

1.4.2.4

          Partition work

1.4.2.4.1

             Erect Concrete Block as partition wall to Construct Warehouse office, Boiler area, Bin storage, Oil Tank & Load Center

1.4.2.4.2

             Finish Interior work for the plant and Warehouse

1.5

   The structure and interior work for the office building

1.5.1

       Structure work

1.5.1.1

          Start structure and interior work for the office building

1.5.1.2

          Erect Pre-Cast Concrete structure

1.5.1.3

          Build masonry wall

1.5.1.4

          Erect Pre-Cast Planks as roof

1.5.1.5

          Place & Fix single-ply over planks

1.5.2

       Interior work

1.5.2.1

          Erect Hung Ceiling

1.5.2.2

          Erect dry wall with metal stud as partition between Reception, Business Office and Offices

1.5.2.3

          Install air conditioning unit

1.5.2.4

          Finish structure and interior work for the office building

1.6

   Site Amenities

1.6.1

       Parking

1.6.1.1

          Start Site Amenities work

1.6.1.2

          Build Parking Area at North of Plant and West of Office

1.6.2

       Flagpole

1.6.2.1

          Construct Flag pole area

1.6.2.2

          Finish Site Amenities work

1.7

   Handover, practical completion and demobilization

Relationship between the activities with duration:

Activity ID

Task Name

Duration

Predecessors

Successors

1

Construction of Plant-Office-Warehouse

300 days

2

   Site preparation and utilities

40 days

3

       Site preparation

15 days

4

          Land Preparation

9 days

5

             Start Site Preparation work

0 days

6,17

6

             Cleaning of site from rubbish timber and bushes

3 days

5

7,23

7

             Surveying for ploting site contour

1 day

6

8

8

             Leveling (Cutting & Filling) to maintain slope as per design

5 days

7

10FF,27,34

9

          Temporary Office

10 days

10

             Erect Pre-Fabricated Frames

4 days

8FF

11FF+3 days

11

             Erect Pre-Fabricated Roof

6 days

10FF+3 days

12FF+1 day

12

             Flooring

3 days

11FF+1 day

13FF,14

13

             Office Internal work including Sanitary Lines

5 days

12FF

14

             Air Conditioning system

2 days

12

15

       Utilities

40 days

16

          Construction of well

10 days

17

             Apply and obtain administrative approval

6 days

5

18

18

             Boring

2 days

17

19

19

             Installation of pump

1 day

18

20

20

             Water testing

1 day

19

21

21

             Ready to use Well

0 days

20

22

          Construction of Overhead Tank (200 CuM capacity)

12 days

23

             Fix Frame / Structure on which tank shall rest

4 days

6

24

24

             Erect tanks of above capacity

2 days

23

25

25

             Fix all necessary plumbing lines

6 days

24

26

          Sewage Line

15 days

27

             Excavation in trapezoidal section throughout the layout of sewage line

2 days

8

28

28

             Earth filling to maintain proper slop as per design

4 days

27

29

29

             Laying of Sewage Pipeline

6 days

28

30

30

             Backfilling & proper Compaction as per standard

3 days

29

33FF

31

          Electric Supply

31 days

32

             Under Ground

31 days

33

                Excavation for Pole foundation, Manhole & Duct

3 days

30FF

36,39

34

                Construct Electrical Manhole 1

6 days

8

35FF

35

                Construct Electrical Manhole 2

6 days

34FF

36

                Cast & Place Electric Duct Bank

12 days

33

37

                Backfill Sand / Earth after Cable laying

2 days

40

41

38

             Above Ground

16 days

39

                Erect Power Incoming Poles

3 days

33

40

40

                Laying of cables

11 days

39

37

41

                Finish Site preparation and utilities work

0 days

37

45FS+1 day

42

   Foundation and concrete work

55 days

43

       Piling work

55 days

44

          Plant

55 days

45

             Start Foundation & Concrete work

0 days

41FS+1 day

46

46

             Boring (5 Nos.) up to 10 meter depth at every 15 meter c/c distance

43 days

45

47FF+5 days,54SS

47

             Piling (5 Nos.) of 10 meter depth at every 15 meter c/c distance

43 days

46FF+5 days

48FF+3 days

48

             Breaking of Pile head

25 days

47FF+3 days

49FF+4 days

49

             Bar Bending and fixing of Reinforcement for Plinth Beam

30 days

48FF+4 days

50SS+3 days

50

             Fixing Formwork

20 days

49SS+3 days

51

51

             Casting of Plinth beam

4 days

50

52

52

             Backfilling & Compaction

3 days

51

69

53

          Warehouse

31 days

54

             Boring (2 Nos.) up to 10 meter depth at every 15 meter c/c distance

17 days

46SS

55FF+5 days,63SS

55

             Piling (2 Nos.) of 10 meter depth at every 15 meter c/c distance

17 days

54FF+5 days

56FF+3 days

56

             Breaking of Pile head

10 days

55FF+3 days

57FF+4 days

57

             Bar Bending and fixing of Reinforcement for Plinth Beam

12 days

56FF+4 days

58SS+3 days

58

             Fixing Formwork

8 days

57SS+3 days

59

59

             Casting of Plinth beam

2 days

58

60

60

             Backfilling & Compaction

1 day

59

69

61

       Spread Footing

55 days

62

          Office Building

55 days

63

             Excavation for spread footing

10 days

54SS

64FF+2 days

64

             Pour lean concrete for leveling

5 days

63FF+2 days

65SS+1 day

65

             Reinforcement bending & Fixing

26 days

64SS+1 day

66FF+2 days

66

             Fixing Formwork

20 days

65FF+2 days

67FF+1 day

67

             Casting of footing

3 days

66FF+1 day

68FF+2 days

68

             Backfilling & Compaction

3 days

67FF+2 days

69

69

             Finish Foundation & Concrete work

0 days

68,60,52

73FS+1 day

70

   Structural Work for plant and Warehouse

40 days

71

       Plant

40 days

72

          Structural Column

18 days

73

             Start Structural Work for plant and Warehouse

0 days

69FS+1 day

74

74

             Erection of column at every 15 meter

18 days

73

75FF,90FF

75

             Alignment & Bolting column with Foundation

15 days

74FF

77FF+3 days,81FF+6 days

76

          Roofing

21 days

77

             Erection of Joist Steel Bars

16 days

75FF+3 days

78FF+4 days

78

             Placing Pre-Cast concrete Planks above Steel Bars

14 days

77FF+4 days

79FF+1 day

79

             Fix roofing sheet

12 days

78FF+1 day

86FF,104FS+3 days

80

          Crane & Beam Erection

40 days

81

             Erection of Girder above structural column from one end of plant to other

24 days

75FF+6 days

82,84FF+2 days

82

             Placing Crane Hoist above girder

10 days

81

83FF+6 days

83

             Arranging other miscellaneous work related to crane assembly

9 days

82FF+6 days

84

             Erection of Beam for Piping

6 days

81FF+2 days

85

          Siding work

18 days

86

             Fix insulated glass panel at top

16 days

79FF

87FF+2 days

87

             Fix insulated opaque panels at middle and bottom

14 days

86FF+2 days

88

       Warehouse

19 days

89

          Structural Column

8 days

90

             Erection of column at every 15 meter

8 days

74FF

91FF

91

             Alignment & Bolting column with Foundation

5 days

90FF

93FF+3 days,97FF+10 days

92

          Roofing

17 days

93

             Erection of Joist Steel Bars

12 days

91FF+3 days

94FF+4 days

94

             Placing Pre-Cast concrete Planks above Steel Bars

8 days

93FF+4 days

95FF+1 day

95

             Fix roofing sheet

6 days

94FF+1 day

99FF

96

          Monorail & Beam erection

14 days

97

             Erection of Monorail above structural column from one end of plant to other

14 days

91FF+10 days

98

          Siding work

10 days

99

             Fix insulated glass panel at top

8 days

95FF

100FF+2 days

100

             Fix insulated opaque panels at middle and bottom

7 days

99FF+2 days

101

   Interior work for the plant and Warehouse

75 days

102

       Plant

75 days

103

          HVAC

60 days

104

             Start Interior work for the plant and Warehouse

0 days

79FS+3 days

105

105

             Erect and install HVAC ducts with ceiling

60 days

104

107,109SS,114SS,117SS

106

          Lighting work

15 days

107

             Install & fix fluorescent light fixtures

15 days

105

125

108

          Flooring

37 days

109

             Compaction of sand below flooring level

25 days

105SS

110

110

             Cast Concrete Floor Slab

12 days

109

112

111

          Partition work

25 days

112

             Erect Concrete Block as partition wall to Construct Lunch area, Toilet, Locker room & Shop offices

25 days

110

113

          Railroad Siding

45 days

114

             Placing / Install railroad siding

45 days

105SS

115

       Warehouse

75 days

116

          HVAC

30 days

117

             Erect and install HVAC ducts with ceiling

30 days

105SS

119,121SS

118

          Lighting work

8 days

119

             Install & fix fluorescent light fixtures

8 days

117

120

          Flooring

19 days

121

             Compaction of sand below flooring level

13 days

117SS

122

122

             Cast Concrete Floor Slab

6 days

121

124

123

          Partition work

56 days

124

             Erect Concrete Block as partition wall to Construct Warehouse office, Boiler area, Bin storage, Oil Tank & Load Center

13 days

122

125

             Finish Interior work for the plant and Warehouse

0 days

107

128FS+1 day

126

   The structure and interior work for the office building

65 days

127

       Structure work

48 days

128

          Start structure and interior work for the office building

0 days

125FS+1 day

129

129

          Erect Pre-Cast Concrete structure

26 days

128

130SS+5 days,131

130

          Build masonry wall

18 days

129SS+5 days

131

131

          Erect Pre-Cast Planks as roof

14 days

129,130

132,134

132

          Place & Fix single-ply over planks

8 days

131

135

133

       Interior work

25 days

134

          Erect Hung Ceiling

12 days

131

136

135

          Erect dry wall with metal stud as partition between Reception, Business Office and Offices

17 days

132

137

136

          Install air conditioning unit

6 days

134

137

          Finish structure and interior work for the office building

0 days

135

140FS+1 day

138

   Site Amenities

25 days

139

       Parking

25 days

140

          Start Site Amenities work

0 days

137FS+1 day

141

141

          Build Parking Area at North of Plant and West of Office

25 days

140

143FF,144

142

       Flagpole

15 days

143

          Construct Flag pole area

15 days

141FF

144

144

          Finish Site Amenities work

0 days

141,143

145

145

   Handover, practical completion and demobilization

7 days

144

While developing the above activities in MS Project, first we need to develop the Calendar (office, 2017) as per site requirement as below:

Working time: 07:00 to 19:00 Hrs

Working Days: Monday to Saturday

Weekly Off: Sunday

Public Holidays: Non-Working days (Australia. Australian Government, 2017)

Attach below the overall Gantt chart for the construction of Plant – Office – Warehouse complex . 

After assigning resource name ‘Worker’ as the only type of resource required to complete the work package ‘Site preparation and utilities’, the resource histogram obtained as below:

From the above histogram, it is clear that we cannot work with only 1 resource per day, so more number of workers is required.

RIC (before leveling): (waste, 2017)

n= 40 days, R= say at 14th June it is 7 Nos., likewise  

RIC = [40 x 435] ÷ [109 x 109]

= 17400 ÷ 11881 = 1.46

RUF (before leveling): (citehr, 2017))

RUF    = Total used Resource ÷ Total Available                       

= 109 ÷ (40 x 20) 

= 109 ÷ 800 = 0.14 

Even though the available resource is more than required, the affect after leveling with respect to the available resources  

References: 

Workbreakdownstructure (2017). Work Breakdown Structure (WBS). [Online]. Available at: https://www.workbreakdownstructure.com/ (Accessed 29 May 2017). 

Gantt (2017). What is a Gantt Chart? [Online]. Available at: https://www.gantt.com/ (Accessed 29 May 2017). 

Office (2017). Set the general working days and times for a project. [Online]. Available at: https://support.office.com/en-us/article/Set-the-general-working-days-and-times-for-a-project-c4587751-2b88-449d-87e5-d3312d16771d (Accessed 29 May 2017). 

Australia. Australian Government (2017). Public holidays. [Online]. Available at: https://www.australia.gov.au/about-australia/special-dates-and-events/public-holidays (Accessed 29 May 2017).

Citehr (2017). Calculation Utilization Rate For Human Resources. [Online]. Available at: https://www.citehr.com/156245-calculation-utilization-rate-human-resources.html (Accessed 29 May 2017).

Waste (2017). Resource Leveling in Construction Projects using Re- Modified Minimum Moment Approach. [Online]. Available at: https://waset.org/publications/8655/resource-leveling-in-construction-projects-using-re-modified-minimum-moment-approach (Accessed 29 May 2017).

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help (2022) WBS For BLDG 2023 [Online]. Available from: https://myassignmenthelp.com/free-samples/bldg2023-construction-planning/critical-path-network-file-A8C6AB.html
[Accessed 20 April 2024].

My Assignment Help. 'WBS For BLDG 2023' (My Assignment Help, 2022) <https://myassignmenthelp.com/free-samples/bldg2023-construction-planning/critical-path-network-file-A8C6AB.html> accessed 20 April 2024.

My Assignment Help. WBS For BLDG 2023 [Internet]. My Assignment Help. 2022 [cited 20 April 2024]. Available from: https://myassignmenthelp.com/free-samples/bldg2023-construction-planning/critical-path-network-file-A8C6AB.html.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close