Introduction
The following assignment has been developed for understanding the development of the activities and the implication of smart project development management. The project of construction of the Apex complex would require the implication of the improved management operations. The significant management would be implied with the help of project management operations and it would also be helpful for taking care of the work related to the management of the works.
- Optimal Schedule and Developing Baseline
Resource Constraints
The resources have been used predominantly and there has been no usage limitation for the resources required in the project. The development of the resource limitations to usage limitation can be understood with the implication of the improved functional development. The resource usages has been limited to the effective and improved management processing. The following table would show the constrained and unconstrained project resources
Resource Name
|
Type
|
Initials
|
Unconstrained Max. Units
|
Constrained Max. Units
|
Std. Rate
|
Geotechnical Engineer
|
Work
|
G
|
100%
|
60%
|
$25.00/hr
|
Soil Lab technician
|
Work
|
S
|
100%
|
100%
|
$17.00/hr
|
Soil investigation Engineer
|
Work
|
S
|
100%
|
60%
|
$21.00/hr
|
Senior architect
|
Work
|
S
|
100%
|
100%
|
$35.00/hr
|
AutoCAD drafts man
|
Work
|
A
|
100%
|
60%
|
$20.00/hr
|
Estimator-Compiler
|
Work
|
E
|
100%
|
60%
|
$22.00/hr
|
Stuctural Engineer
|
Work
|
S
|
100%
|
100%
|
$35.00/hr
|
Snr Stuctural Engineer
|
Work
|
S
|
100%
|
60%
|
$40.00/hr
|
Mechanical systems designer
|
Work
|
M
|
100%
|
100%
|
$30.00/hr
|
Electrical systems designer
|
Work
|
E
|
100%
|
100%
|
$30.00/hr
|
Resource Constraint and Levelling
The unlevelled project resources were AutoCAD drafts man, Estimator-Compiler, and Snr Stuctural Engineer. The max values of the resources for the project had been decreased to 60% of the actual 100% due to the constraint factors. It resulted in overallocation of the work and requirement for the levelling of the work done. The constrained unlevelled project resource usage is given below,
The screenshot has clearly indicated that there is over allocation issues in the completion of the project for task ID 1.2.3 and 1.2.5. It is due to the fact that the resource constraints of AutoCAD draftsmen and estimator compiler. If the resource limitation is applied and the optimum duration of the whole project is considered, it is possible that the over allocation can be dealt with. Hence, we decreased the percentage of resource usage and modify the resource percentage for getting the optimum schedule for the project. The constrained levelled project resource usage is given below,
Table of modified activities
WBS
|
Task Name
|
Cost
|
Predecessors
|
Duration
|
Start
|
Finish
|
0
|
Project Apex
|
$9,079,198.50
|
|
495 days
|
Mon 08-10-18
|
Fri 28-08-20
|
1
|
Preliminaries
|
$108,264.00
|
|
85 days
|
Mon 08-10-18
|
Fri 01-02-19
|
1.1
|
Planning
|
$0.00
|
|
25 days
|
Mon 08-10-18
|
Fri 09-11-18
|
1.1.1
|
Identify mission and Objectives, Create Project Charter
|
$0.00
|
|
7 days
|
Mon 08-10-18
|
Tue 16-10-18
|
1.1.2
|
Create Business Plan and Issue
|
$0.00
|
3
|
5 days
|
Wed 17-10-18
|
Tue 23-10-18
|
1.1.3
|
Create Project Initiation Document and Issue
|
$0.00
|
3
|
12 days
|
Wed 24-10-18
|
Fri 09-11-18
|
1.2
|
Design
|
$108,264.00
|
|
73 days
|
Wed 24-10-18
|
Fri 01-02-19
|
1.1
|
Soil Investigation
|
$17,496.00
|
4
|
3 days
|
Wed 24-10-18
|
Fri 26-10-18
|
1.2
|
Architectural
|
$25,416.00
|
7
|
60 days
|
Mon 29-10-18
|
Fri 01-02-19
|
1.2.3
|
Structural
|
$23,640.00
|
7
|
15 days
|
Mon 29-10-18
|
Fri 16-11-18
|
1.2.4
|
Mechanical
|
$18,072.00
|
9
|
10 days
|
Mon 19-11-18
|
Fri 30-11-18
|
1.2.5
|
Electrical
|
$23,640.00
|
10
|
15 days
|
Mon 03-12-18
|
Fri 21-12-18
|
2
|
Basement and Floors 1 - 9
|
$7,137,142.50
|
|
440 days
|
Mon 24-12-18
|
Fri 28-08-20
|
2.1
|
Earthworks
|
$98,760.00
|
|
44 days
|
Mon 24-12-18
|
Thu 21-02-19
|
2.1.1
|
Survey
|
$15,000.00
|
11
|
5 days
|
Mon 24-12-18
|
Fri 28-12-18
|
2.1.2
|
Excavation
|
$21,200.00
|
14
|
10 days
|
Mon 31-12-18
|
Fri 11-01-19
|
2.1.3
|
Groundworks
|
$62,560.00
|
|
44 days
|
Mon 24-12-18
|
Thu 21-02-19
|
2.1.3.1
|
Grading
|
$24,360.00
|
11
|
5 days
|
Mon 24-12-18
|
Fri 28-12-18
|
2.1.3.2
|
Water Control
|
$4,200.00
|
17
|
29 days
|
Mon 31-12-18
|
Thu 07-02-19
|
2.1.3.3
|
Erosion control
|
$6,000.00
|
17
|
29 days
|
Mon 31-12-18
|
Thu 07-02-19
|
2.1.3.4
|
Underground utilities
|
$28,000.00
|
18,19
|
10 days
|
Fri 08-02-19
|
Thu 21-02-19
|
2.2
|
Structures
|
$4,645,009.00
|
|
136 days
|
Fri 22-02-19
|
Fri 30-08-19
|
2.2.1
|
Reinforcements
|
$4,645,009.00
|
|
136 days
|
Fri 22-02-19
|
Fri 30-08-19
|
2.2.1.1
|
Piles (Precast)
|
$3,651,832.00
|
20
|
14 days
|
Fri 22-02-19
|
Wed 13-03-19
|
2.2.1.2
|
Columns
|
$570,692.00
|
|
44 days
|
Thu 14-03-19
|
Tue 14-05-19
|
2.2.1.2.1
|
Columns (Basement - Floor 2)
|
$212,192.00
|
23
|
28 days
|
Thu 14-03-19
|
Tue 30-04-19
|
2.2.1.2.2
|
Columns (Floor 3 - 4)
|
$158,200.00
|
23
|
10 days
|
Thu 14-03-19
|
Wed 27-03-19
|
2.2.1.2.3
|
Columns (Floor 5 - 6)
|
$111,760.00
|
28
|
20 days
|
Thu 11-04-19
|
Tue 14-05-19
|
2.2.1.2.4
|
Columns (Floor 7 - 9)
|
$88,540.00
|
26
|
10 days
|
Thu 28-03-19
|
Wed 10-04-19
|
2.2.1.3
|
Slab-Beams
|
$385,173.00
|
|
36 days
|
Wed 15-05-19
|
Wed 03-07-19
|
2.2.1.3.1
|
Slab -Beams (Basement - Floor 2)
|
$143,496.00
|
27
|
12 days
|
Wed 15-05-19
|
Thu 30-05-19
|
2.2.1.3.2
|
Slab-Beams (Floor 3- 4)
|
$105,734.00
|
30
|
8 days
|
Fri 31-05-19
|
Tue 11-06-19
|
2.2.1.3.3
|
Slab-Beams (Floor 5 - 6)
|
$75,524.00
|
25,31
|
8 days
|
Wed 12-06-19
|
Fri 21-06-19
|
2.2.1.3.4
|
Slab-Beams (Floor 7 - 9)
|
$60,419.00
|
32
|
8 days
|
Mon 24-06-19
|
Wed 03-07-19
|
2.2.1.4
|
Roofing
|
$37,312.00
|
|
42 days
|
Thu 04-07-19
|
Fri 30-08-19
|
2.2.1.4.1
|
Roofing Trusses
|
$32,000.00
|
33
|
5 days
|
Thu 04-07-19
|
Wed 10-07-19
|
2.2.1.4.2
|
Roofing Cover
|
$5,312.00
|
35
|
3 days
|
Wed 28-08-19
|
Fri 30-08-19
|
2.3
|
Concrete
|
$152,738.50
|
|
36 days
|
Mon 02-09-19
|
Mon 21-10-19
|
2.3.1
|
Columns
|
$66,545.00
|
|
28 days
|
Mon 02-09-19
|
Wed 09-10-19
|
2.3.1.1
|
Columns (Basement - Floor 2)
|
$25,565.00
|
21
|
5 days
|
Mon 02-09-19
|
Fri 06-09-19
|
2.3.1.2
|
Columns Floor( 3 - 4)
|
$13,060.00
|
39
|
5 days
|
Mon 09-09-19
|
Fri 13-09-19
|
2.3.1.3
|
Columns Floor( 5 - 6)
|
$13,060.00
|
40,44
|
5 days
|
Thu 26-09-19
|
Wed 02-10-19
|
2.3.1.4
|
Columns Floor( 7 - 9)
|
$14,860.00
|
41
|
5 days
|
Thu 03-10-19
|
Wed 09-10-19
|
2.3.2
|
Slab-Beams
|
$86,193.50
|
|
26 days
|
Mon 16-09-19
|
Mon 21-10-19
|
2.3.2.1
|
Slab-Beams (Basement - Floor 2)
|
$18,704.00
|
40,45
|
4 days
|
Fri 20-09-19
|
Wed 25-09-19
|
2.3.2.2
|
Slab-Beams Floor( 3 - 4)
|
$29,466.50
|
40
|
4 days
|
Mon 16-09-19
|
Thu 19-09-19
|
2.3.2.3
|
Slab-Beams Floor( 5 - 6)
|
$13,681.50
|
42
|
4 days
|
Thu 10-10-19
|
Tue 15-10-19
|
2.3.2.4
|
Slab-Beams Floor( 7 - 8)
|
$24,341.50
|
46
|
4 days
|
Wed 16-10-19
|
Mon 21-10-19
|
2.3.3
|
Stairway
|
$40,996.00
|
|
8 days
|
Thu 14-03-19
|
Mon 25-03-19
|
2.3.3.1
|
Stairway (Basement - Floor 2)
|
$11,991.50
|
23
|
2 days
|
Thu 14-03-19
|
Fri 15-03-19
|
2.3.3.2
|
Stairway Floor(3 - 4)
|
$5,021.50
|
49
|
2 days
|
Mon 18-03-19
|
Tue 19-03-19
|
2.3.3.3
|
Stairway Floor( 5 -6)
|
$11,991.50
|
50
|
4 days
|
Wed 20-03-19
|
Mon 25-03-19
|
2.3.3.4
|
Stairway Floor( 7 - 8)
|
$11,991.50
|
49
|
4 days
|
Mon 18-03-19
|
Thu 21-03-19
|
2.3.4
|
Patios
|
$3,101.00
|
52
|
1 day
|
Fri 22-03-19
|
Fri 22-03-19
|
2.3.4
|
Blockwall-Masonry
|
$1,087,280.00
|
|
120 days
|
Mon 18-03-19
|
Fri 30-08-19
|
2.4.1
|
Bockwall
|
$1,087,280.00
|
|
120 days
|
Mon 18-03-19
|
Fri 30-08-19
|
2.4.1.1
|
Internal wall
|
$375,000.00
|
49
|
30 days
|
Mon 18-03-19
|
Fri 26-04-19
|
2.4.1.2
|
External wall
|
$425,000.00
|
56
|
45 days
|
Mon 29-04-19
|
Fri 28-06-19
|
2.4.1.3
|
Screening
|
$287,280.00
|
56
|
90 days
|
Mon 29-04-19
|
Fri 30-08-19
|
2.5
|
Interior -Finishes
|
$657,088.00
|
|
220 days
|
Mon 01-07-19
|
Fri 01-05-20
|
2.5..5
|
Partitions
|
$77,223.00
|
57
|
55 days
|
Mon 01-07-19
|
Fri 13-09-19
|
2.5.1
|
Dry wall
|
$85,000.00
|
58,69
|
45 days
|
Mon 16-09-19
|
Fri 15-11-19
|
2.5.2
|
Insulation
|
$463,265.00
|
|
90 days
|
Mon 18-11-19
|
Fri 20-03-20
|
2.5.2.1
|
Interior doors
|
$12,460.00
|
60
|
20 days
|
Mon 18-11-19
|
Fri 13-12-19
|
2.5.2.2
|
Windows
|
$18,080.00
|
60
|
30 days
|
Mon 18-11-19
|
Fri 27-12-19
|
2.5.2.3
|
Security doors
|
$12,400.00
|
62
|
20 days
|
Mon 16-12-19
|
Fri 10-01-20
|
2.5.2.4
|
Tiles
|
$107,605.00
|
60
|
90 days
|
Mon 18-11-19
|
Fri 20-03-20
|
2.5.2.5
|
Glazing works
|
$32,720.00
|
60
|
40 days
|
Mon 18-11-19
|
Fri 10-01-20
|
2.5.2.6
|
Decoration
|
$280,000.00
|
66,64
|
30 days
|
Mon 13-01-20
|
Fri 21-02-20
|
2.5.4
|
Carpeting
|
$31,600.00
|
67
|
50 days
|
Mon 24-02-20
|
Fri 01-05-20
|
2.6
|
MEP systems
|
$41,120.00
|
|
55 days
|
Mon 02-09-19
|
Fri 15-11-19
|
2.6.1
|
Plumbing
|
$41,120.00
|
|
55 days
|
Mon 02-09-19
|
Fri 15-11-19
|
2.6.1.1
|
Plumbing systems (Main Line)
|
$9,760.00
|
36
|
15 days
|
Mon 02-09-19
|
Fri 20-09-19
|
2.6.1.2
|
Plumbing systems (Floor. 1-2)
|
$7,840.00
|
36
|
10 days
|
Mon 21-10-19
|
Fri 01-11-19
|
2.6.1.3
|
Plumbing systems (Floor. 3-4)
|
$7,840.00
|
36,73
|
10 days
|
Mon 04-11-19
|
Fri 15-11-19
|
2.6.1.4
|
Plumbing systems (Floor. 4-6)
|
$7,840.00
|
72
|
10 days
|
Mon 23-09-19
|
Fri 04-10-19
|
2.6.1.5
|
Plumbing systems (Floor. 7-9)
|
$7,840.00
|
75
|
10 days
|
Mon 07-10-19
|
Fri 18-10-19
|
2.6.2
|
Electrical
|
$103,360.00
|
|
45 days
|
Mon 21-10-19
|
Fri 20-12-19
|
2.6.2.1
|
Electrical Fixtures (Distribution)
|
$28,000.00
|
76
|
5 days
|
Mon 21-10-19
|
Fri 25-10-19
|
2.6.2.2
|
Electrical Fixtures (Floor. 1-2)
|
$18,840.00
|
78
|
10 days
|
Mon 28-10-19
|
Fri 08-11-19
|
2.6.2.3
|
Electrical Fixtures (Floor. 3-4)
|
$18,840.00
|
79
|
10 days
|
Mon 11-11-19
|
Fri 22-11-19
|
2.6.2.4
|
Electrical Fixtures (Floor. 5-6)
|
$18,840.00
|
74,80
|
10 days
|
Mon 25-11-19
|
Fri 06-12-19
|
2.6.2.5
|
Electrical Fixtures (Floor. 7-9)
|
$18,840.00
|
81
|
10 days
|
Mon 09-12-19
|
Fri 20-12-19
|
2.6.3
|
Sprinkler
|
$35,740.00
|
|
40 days
|
Mon 23-03-20
|
Fri 15-05-20
|
2.6.3.1
|
Systems Controls
|
$25,000.00
|
65,82
|
10 days
|
Mon 23-03-20
|
Fri 03-04-20
|
2.6.3.2
|
Fire alarms
|
$10,740.00
|
84,68
|
10 days
|
Mon 04-05-20
|
Fri 15-05-20
|
2.6.4
|
Mechanical Systems
|
$271,950.00
|
|
75 days
|
Mon 18-05-20
|
Fri 28-08-20
|
2.6.4.1
|
Mechanical Fixtures (Elevators etc)
|
$95,000.00
|
85
|
15 days
|
Mon 18-05-20
|
Fri 05-06-20
|
2.6.4.2
|
Mechanical Fixtures (Floor 1- 4)
|
$88,950.00
|
87
|
30 days
|
Mon 08-06-20
|
Fri 17-07-20
|
2.6.4.3
|
Mechanical Fixtures (Floor 5- 9)
|
$88,000.00
|
88
|
30 days
|
Mon 20-07-20
|
Fri 28-08-20
|
3
|
External Works
|
$1,707,232.00
|
|
28 days
|
Mon 18-05-20
|
Wed 24-06-20
|
3.1
|
Access roads
|
$877,616.00
|
85
|
14 days
|
Mon 18-05-20
|
Thu 04-06-20
|
3.2
|
Signages
|
$2,000.00
|
91
|
5 days
|
Fri 05-06-20
|
Thu 11-06-20
|
3.3
|
Parking lot
|
$827,616.00
|
91
|
14 days
|
Fri 05-06-20
|
Wed 24-06-20
|
4
|
Quality Assessment
|
$126,560.00
|
|
20 days
|
Thu 25-06-20
|
Wed 22-07-20
|
4.1
|
Testing
|
$55,920.00
|
|
20 days
|
Thu 25-06-20
|
Wed 22-07-20
|
4.1
|
Testing 1
|
$5,592.00
|
92,93
|
2 days
|
Thu 25-06-20
|
Fri 26-06-20
|
4.1
|
Testing 2
|
$5,592.00
|
96
|
2 days
|
Mon 29-06-20
|
Tue 30-06-20
|
4.1
|
Testing 3
|
$5,592.00
|
96
|
2 days
|
Wed 01-07-20
|
Thu 02-07-20
|
4.1
|
Testing 4
|
$5,592.00
|
96
|
2 days
|
Fri 03-07-20
|
Mon 06-07-20
|
4.1
|
Testing 5
|
$5,592.00
|
96
|
2 days
|
Tue 07-07-20
|
Wed 08-07-20
|
4.1
|
Testing 6
|
$5,592.00
|
96
|
2 days
|
Thu 09-07-20
|
Fri 10-07-20
|
4.1
|
Testing 7
|
$5,592.00
|
96
|
2 days
|
Mon 13-07-20
|
Tue 14-07-20
|
4.1
|
Testing 8
|
$5,592.00
|
96
|
2 days
|
Wed 15-07-20
|
Thu 16-07-20
|
4.1
|
Testing 9
|
$5,592.00
|
96
|
2 days
|
Fri 17-07-20
|
Mon 20-07-20
|
4.1
|
Testing 10
|
$5,592.00
|
96
|
2 days
|
Tue 21-07-20
|
Wed 22-07-20
|
4.2
|
Inspections
|
$70,640.00
|
|
8 days
|
Wed 01-07-20
|
Fri 10-07-20
|
4.2
|
Inspections 1
|
$7,064.00
|
97
|
1 day
|
Wed 01-07-20
|
Wed 01-07-20
|
4.2
|
Inspections 2
|
$7,064.00
|
98
|
1 day
|
Fri 03-07-20
|
Fri 03-07-20
|
4.2
|
Inspections 3
|
$7,064.00
|
99
|
1 day
|
Tue 07-07-20
|
Tue 07-07-20
|
4.2
|
Inspections 4
|
$7,064.00
|
107
|
1 day
|
Thu 02-07-20
|
Thu 02-07-20
|
4.2
|
Inspections 5
|
$7,064.00
|
108
|
1 day
|
Mon 06-07-20
|
Mon 06-07-20
|
4.2
|
Inspections 6
|
$7,064.00
|
109
|
1 day
|
Wed 08-07-20
|
Wed 08-07-20
|
4.2
|
Inspections 7
|
$7,064.00
|
110
|
1 day
|
Fri 03-07-20
|
Fri 03-07-20
|
4.2
|
Inspections 8
|
$7,064.00
|
111
|
1 day
|
Tue 07-07-20
|
Tue 07-07-20
|
4.2
|
Inspections 9
|
$7,064.00
|
112
|
1 day
|
Thu 09-07-20
|
Thu 09-07-20
|
4.2
|
Inspections 10
|
$7,064.00
|
113,114,115
|
1 day
|
Fri 10-07-20
|
Fri 10-07-20
|
Contingency calculation
Total Estimated Cost
|
$ 9,079,198.50
|
Total Actual Cost
|
$ 9,533,158.42
|
Remaining Money
|
$ (453,959.92)
|
Contingency
|
$ 1,361,879.78
|
Scope change calculation
Total Estimated Cost
|
$ 9,079,198.50
|
Total estimated days
|
1213.00
|
Total Actual Cost
|
$ 9,176,290.60
|
total actual days
|
$ 1,256.35
|
Remaining days
|
$ (97,092.10)
|
remaining days
|
$ (43.35)
|
Contingency for cost
|
$ 1,361,879.78
|
Contingency for days
|
181.95
|
Scope change
The following assignment has been made for the implication of the scope change management and the utilization of the project management concept. For the project we have increased and reduced the project scope (days and cost).
In the assignment the project had a duration of 495 days and the budget of $9,079,198.50. However the activities were requested to be changed and the changes done in the project were:
WBS
|
Task Name
|
Duration
|
Cost
|
New duration
|
New cost
|
|
1.1.3
|
Create Project Initiation Document and Issue
|
12
|
$ -
|
14.4
|
$ -
|
scope increased by 20%
|
1.1
|
Soil Investigation
|
3
|
$ 17,496.00
|
2.55
|
$ 14,871.60
|
scope reduced by 15%
|
1.2.4
|
Mechanical
|
10
|
$ 18,072.00
|
12.5
|
$ 22,590.00
|
scope increased by 25%
|
2.1.3.3
|
Erosion control
|
29
|
$ 6,000.00
|
34.8
|
$ 7,200.00
|
scope increased by 20%
|
2.1.3.4
|
Underground utilities
|
10
|
$ 28,000.00
|
8.5
|
$ 23,800.00
|
scope reduced by 15%
|
2.2.1.2.2
|
Columns (Floor 3 - 4)
|
10
|
$ 158,200.00
|
12.5
|
$ 197,750.00
|
scope increased by 25%
|
2.2.1.3.4
|
Slab-Beams (Floor 7 - 9)
|
8
|
$ 60,419.00
|
9.6
|
$ 72,502.80
|
scope increased by 20%
|
2.2.1.4.1
|
Roofing Trusses
|
5
|
$ 32,000.00
|
4.25
|
$ 27,200.00
|
scope reduced by 15%
|
2.3.1.2
|
Columns Floor( 3 - 4)
|
5
|
$ 13,060.00
|
6.25
|
$ 16,325.00
|
scope increased by 25%
|
2.3.2.4
|
Slab-Beams Floor( 7 - 8)
|
4
|
$ 24,341.50
|
4.8
|
$ 29,209.80
|
scope increased by 20%
|
2.3.3.1
|
Stairway (Basement - Floor 2)
|
2
|
$ 11,991.50
|
1.7
|
$ 10,192.78
|
scope reduced by 15%
|
2.3.3.4
|
Stairway Floor( 7 - 8)
|
4
|
$ 11,991.50
|
5
|
$ 14,989.38
|
scope increased by 25%
|
2.5.1
|
Dry wall
|
45
|
$ 85,000.00
|
54
|
$ 102,000.00
|
scope increased by 20%
|
2.5.2.1
|
Interior doors
|
20
|
$ 12,460.00
|
17
|
$ 10,591.00
|
scope reduced by 15%
|
2.5.2.4
|
Tiles
|
90
|
$ 107,605.00
|
112.5
|
$ 134,506.25
|
scope increased by 25%
|
References
Eskerod, P., & Jepsen, A. L. (2016). Project stakeholder management. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lock, D. (2017). The essentials of project management. Routledge.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.