Identification Of The Critical Path

tag 45 Download3 Pages 529 Words tag Add in library Click this icon and make it bookmark in your library to refer it later. GOT IT

Question:

• What is the critical path?

• What problems can you identify?

• How can you improve on this plan?
 
 

Answer:

Activities

Duration

ID dates to be purged

1

Estimate Volume

7

Determine resources requirements

2

ID disposition of charts

30

Set budget

30

Gain Approval

3

Obtain resources

1

Purge files

14


Identification of the Critical Path    

PERT chart is a project monitoring tool which has been used for finding out the critical path of a project which is useful for finding out the shortest path for completing the project successfully. The network path with longest total duration should be the critical path. Critical path is the shortest path which needs to be followed by the project manager for completing the project in a successful way. According to this network diagram there are two paths in this network diagram which have been. The paths have been highlighted below

Path 1 duration: 10 days (A’s duration plus B’s duration plus C’s duration)

Path 2 duration: 78 days (D’s duration plus E’s duration plus F’s duration plus G’s duration)

In this case path 1 is the critical path as if there is any delay at all in the path 1 then the entire project will be delayed as the time taken for the predecessor activities is more, then the entire project will be late.

From the network diagram which have been given in the pdf it has been seen that there are two paths and its direction has been given in this way.

Path 1: A-B-C which is of 10 days

Path 2: D-E-F-G-H which is of 78 days

So the path 1 is the critical path for the entire project as the path 1 is the shortest path to be followed by the project manager for completing the project within time. Hence the critical path for this project is A-B-C.

 

Problems identified in the chart

The problem which has been identified in the chart is that the path 1 is not completed as the path is an incomplete path as the path as the start data but it does not have the end date. According to this network diagram the path should be completed as in this way like. It starts from the activity A joins with the activity B. After that it joins with the activity C and after that it should join with the last activity so the path does have that end, but there is a big problem as the slack time is not consistent for the path (Dennis et, al 2015).

Improvement in the Plan

There is only one improvement in the plan which is that if the activity B is to be connected with the last activity and activity C will be connected with the last activity then there would be three paths formed for the network diagram as a result the path for reaching the last activity becomes easier and the project takes a very lesser time to complete it (Pyron, 1994).

 

References

Dennis, A., Wixom, B., Roth, R. and Roth, R. (2015). Systems analysis and design. Hoboken, NJ: Wiley.

Pyron, T. (1994). Using Microsoft® Project 4 for Windows. Indianapolis, Ind.: Que Corporation.

OR

With time, MyAssignmenthelp.com has become one of the best college essay writing services. Our all rounded services give students the confidence to overcome assignment related issues. Our services are fast enough to meet most urgent deadlines. We are capable of delivering fast essay writing services with the help of our specially designed provisions and writers' teams. Our urgent essay help services guarantee most rapid delivery of assignment solutions. Some of our most popular essay services are application essay help, exploratory essay help, literary review essay help and argumentative essay help.

Most Downloaded Sample Of Medical

Medical Nursing Assignment

Download : 192 | Pages : 10

Introduction It takes long to develop the dreadful disease, Lung Carcinoma. Where as the changes start taking place immediately after the beginning of consumption of carcinogenic components. The lining of the bronchi immediately start reacting to these components and abnormalgrowth starts taking place. With the increase in the exposure to the carcinogenic chemicals, the lining starts showing abnormal growth. The leading cause for the same al...

Read More arrow Tags: Australia Arlington Management University of New South Wales 

Argument Essay: Are Computers Changing The Way Humans Think

Download : 539 | Pages : 3

Introduction Is the Web-world shifting our common senses? It appears improbable to me, however it’s better to put down that query to progression environmentalists. In spite of that I can confirm to be that the Web-world is altering our inclinations of thinking, which isn't the identical thing like altering our intelligences. The thinking is changed with changes in the environment, so the web-based environment also changes our thinking....

Read More arrow Tags: Australia Arlington Management University of New South Wales 

Race For Life Cancer Research Blackpool

Download : 83 | Pages : 9

Introduction Race for life is known to be a series of events that are conducted to raise funds for women only. Organization of this event is done is done by the Cancer Research UK which is a British charity. These events conduct several activities such as walking, jogging and running. These races that are conducted are done in the course of 5 kilometres and focus on the aim of raising funds and sponsorships. The funds raised by this event ar...

Read More arrow Tags: Australia Arlington Management University of New South Wales 

Sample APA Style Assignment On Prevalence Of Obesity In USA

Download : 396 | Pages : 7

  Introduction Obesity has emerged as the most pressing nutritional problem facing the developed world. This trend has occurred over a relatively short period of time; in the United States, it appears to have begun in the last quarter of the 20th century. The epidemic in children followed shortly thereafter. The most recent data (1999–2000) from national surveys in the United States suggest that almost two thirds of the adult popul...

Read More arrow Tags: Australia Arlington Management University of New South Wales 

Sample Chicago Style Assignment On Prevalence Of Obesity

Download : 144 | Pages : 6

  Introduction Obesity has emerged as the most pressing nutritional problem facing the developed world. This trend has occurred over a relatively short period of time; in the United States, it appears to have begun in the last quarter of the 20th century. The epidemic in children followed shortly thereafter. The most recent data (1999–2000) from national surveys in the United States suggest that almost two thirds of the adult populat...

Read More arrow Tags: Australia Arlington Management University of New South Wales 
Next
Free plagiarism check online Free plagiarism check online on mobile
Have any Query?