Include the Project description and overview you developed as part of Assessment .
•Identify the desired area of impact - Rank the following areas in terms of importance: Strategy / Customer / Financial / Operational / Social
•With reference to your project, identify one or two of the following types of value:
Define Scope and produce a Scope Management Plan
Define the scope of the project and detail how the scope will be managed.
Provide a list of Resources
Identify and detail the resources for the project using MS Project where appropriate, including:
Using MS Project, develop a schedule using a high level Work Breakdown Structure (WBS). It should include:
Researching for the closure checklist and project evaluation
To prepare for this task, you will be required to provide an annotated bibliography.
Write an Annotated Bibliography for three (3) relevant texts or readings around project evaluation.
Your client is Globex Corp. To learn more about Globex and their business and history, please visit the Globex website(globex.uimagine.edu.au). You should ensure you visit the Riverina Agriculture and Lifestyle Show page accessed via the ‘RALS’ link in the main menu. (note: you will be prompted to enter your CSU username and password to access this site).
As a Virtucon staff member and in order to gather information for your assigned project, you have been granted temporary access to the Globex staff intranet. Please access this by navigating to the ‘Staff’ menu option. You will need to enter:
Factor |
Description |
Ranking |
Customer |
The focus of the customer is high on the project as Globex wants the application for its customers only |
1 |
Financial |
Economical impact on operations would be effective for the development of the successful execution of the activities. |
2 |
Operational |
Operations of the organization is a must as the application is supposed to make it more effective |
3 |
Strategy |
Strategies of implementing the development factors would be eased with the consideration of the factors and development. |
4 |
Social |
Social influence of operations would be implied with the involvement of the successive development factor. |
5 |
Value |
Metrics |
Time Frame |
Better |
Number of operations |
3 months |
Faster |
Delivery time |
2 months |
Cheaper |
Cost Incurred |
5 months |
Do More |
Effectiveness |
8 months |
Resource Name |
Roles |
Financial manager |
Management of the Cash Application |
Project manager |
Management of the project activities |
Project planner |
Project Scheduling |
Developer |
Development of Application |
System engineer |
Integration of system functions |
Designer |
Design development |
Tester |
Testing the system for functions |
System analyst |
Analyzing the system requirements |
Database administrator |
Management of the database |
Human resource manager |
Management of the human resources |
Risk analyst |
Analyzing the project risks |
Programmer |
Programming the application |
System administrator |
Managing system functions |
Software engineer |
Integration of system functions |
Hardware and Network Requirements
Computer System, Router, Switch, and NIC card
Software Requirements
Application UI, Programming, Designing, and Testing Software
FacilitiesThe Gantt chart for the project is shown below,
WBS |
Task Name |
Duration |
Start |
Finish |
M1 |
Kick off |
0 days |
Mon 8/6/18 |
Mon 8/6/18 |
M2 |
Plan Approval |
0 days |
Mon 8/20/18 |
Mon 8/20/18 |
M3 |
Design Approval |
0 days |
Tue 8/28/18 |
Tue 8/28/18 |
M4 |
System Developed |
0 days |
Thu 9/27/18 |
Thu 9/27/18 |
M5 |
Test Documentation |
0 days |
Thu 10/11/18 |
Thu 10/11/18 |
M6 |
System Live |
0 days |
Thu 10/18/18 |
Thu 10/18/18 |
M7 |
Project Closed |
0 days |
Mon 10/22/18 |
Mon 10/22/18 |
Resource Name |
Work |
Standard Rate |
Cost |
Financial manager |
80 hrs |
$ 70.00/hr |
$ 5,600.00 |
Project manager |
80 hrs |
$ 80.00/hr |
$ 6,400.00 |
Project planner |
56 hrs |
$ 40.00/hr |
$ 2,240.00 |
Developer |
64 hrs |
$ 60.00/hr |
$ 3,840.00 |
System engineer |
96 hrs |
$ 75.00/hr |
$ 7,200.00 |
Designer |
32 hrs |
$ 50.00/hr |
$ 1,600.00 |
Tester |
104 hrs |
$ 50.00/hr |
$ 5,200.00 |
System analyst |
32 hrs |
$ 55.00/hr |
$ 1,760.00 |
Database administrator |
64 hrs |
$ 60.00/hr |
$ 3,840.00 |
Human resource manager |
88 hrs |
$ 70.00/hr |
$ 6,160.00 |
Risk analyst |
80 hrs |
$ 40.00/hr |
$ 3,200.00 |
Programmer |
48 hrs |
$ 65.00/hr |
$ 3,120.00 |
System administrator |
128 hrs |
$ 70.00/hr |
$ 8,960.00 |
Software engineer |
104 hrs |
$ 75.00/hr |
$ 7,800.00 |
Hardware and software requirements |
1 |
$ 5,000.00 |
$ 5,000.00 |
Additional cost |
1 |
$ 3,000.00 |
$ 3,000.00 |
Total Budget |
$74,920.00 |
Risk |
Probability (1-5) |
Impact (1-5) |
Rating P*I |
Over budget |
4 |
3 |
8 |
Delay of Schedule |
5 |
2 |
10 |
Performance Issues |
3 |
5 |
15 |
Programming Errors |
2 |
4 |
8 |
Missing Function |
4 |
5 |
20 |
The new cash application for Globex would ensure that the requirements of the client for easing their customer’s operations would be done by following the engineering activities.
Testing methods of White Box, Black Box, User Interface. Prototyping, and Simulation would be used as verification activities.
Quality Control, Evaluation Checklist, and Feasible Project Plan analysis would be used as the validation activities.
Article: A computerized method for delay risk assessment based on fuzzy set theory using MS Project™
Journal: KSCE Journal of Civil Engineering
Authors: Budayan, C., Dikmen, I., Birgonul, M. T., and Ghaziani, A.
Year of Publication: 2018
Synopsis: According to Budayan, Dikmen, Birgonul and Ghaziani (2018), the Ms-Project software can be helpful for defining the influence of the risk management. The analysis of the fuzzy set theory would align with the development of the successive management of the activities and implying the innovative and improved functional management using successful development of project schedule using Ms-Project. The risk assessment is helpful for enduring the analysis of the factors for developing the successful integration and alignment of the cohesive project integration. The analysis would also be helpful for taking care of the risk assessment and development of the factors for the integration management. The integration would be aligned for the management of the successful formation and introducing the utilization and formation.
Article: How does risk management influence production decisions? Evidence from a field experiment
Journal: The Review of Financial Studies (Vol. 30; Issue no. 6)
Authors: Cole, S., Giné, X., and Vickery, J.
Year of Publication: 2017
Synopsis: According to Cole, Gine and Vickery (2017), risk management holds an integral role in defining the management of the successful management and integration of the factors. The production decisions for the project can be effectively dealt with the innovative and improved analysis model. The risk management operations would be helpful for taking care of the factors for the implementation and utilization factors. The innovation would be more effective for the formation of the impressive management and development. The analysis of the factors for the development and alignment of the factors has been largely helpful for integrating the listing of the factors taking care of the improved analysis and development. The easing of the management model would be implied with the consideration and utilization of the successive development model.
Article: Between cost and benefit: investigating effects of cost management control systems on cost efficiency and organisational performance
Journal: Journal of Management Control (Vol. 29; Issue no. 1)
Authors: Diefenbach, U., Wald, A., and Gleich, R.
Year of Publication: 2018
Synopsis: According to Diefenbach, Wald and Gleich (2018), the consideration of the factorial representation of the development model would align with the consideration to the formation and listing the innovative management of the factors. The successful management of the factors would help the organization in taking care of the innovation and development. The cost analysis and the management of the resources act as a major factor for integrating the utilization and development. The completion of the successful project completion would be aligned with the management of the successful cost factors. The consideration for the efficiency analysis of the costing factor for the project is aligned with the utilization of the improved functional development.
Is required information and resources for the project comprehensive? |
þ |
Is the project plan feasible? |
þ |
Has the design being approved by the client? |
þ |
Are all the factors for the risk assessment being considered? |
þ |
Is it possible for the actualization of the project? |
þ |
Has the project be approved by the client? |
þ |
Almeida, H., Hankins, K. W., & Williams, R. (2017). Risk management with supply contracts. The Review of Financial Studies, 30(12), 4179-4215.
Andersen, K., Thorsteinsson, S. E., Thorbergsson, H., & Gudmundsson, K. S. (2017, July). Developing the academic-industrial partnership through student research and projects: Case studies from Iceland. In Professional Communication Conference (ProComm), 2017 IEEE International (pp. 1-5). IEEE.
Budayan, C., Dikmen, I., Birgonul, M. T., & Ghaziani, A. (2018). A computerized method for delay risk assessment based on fuzzy set theory using MS Project™. KSCE Journal of Civil Engineering, 1-12.
Burtonshaw-Gunn, S. A. (2017). Risk and financial management in construction. Routledge.
Christian, D. (2018). Building Cost Management: Case Study Using Costing Methods. IJAME.
Cole, S., Giné, X., & Vickery, J. (2017). How does risk management influence production decisions? Evidence from a field experiment. The Review of Financial Studies, 30(6), 1935-1970.
Cooper, R. (2017). Supply chain development for the lean enterprise: interorganizational cost management. Routledge.
da Silva, R. F., Filgueira, R., Pietri, I., Jiang, M., Sakellariou, R., & Deelman, E. (2017). A characterization of workflow management systems for extreme-scale applications. Future Generation Computer Systems, 75, 228-238.
Diefenbach, U., Wald, A., & Gleich, R. (2018). Between cost and benefit: investigating effects of cost management control systems on cost efficiency and organisational performance. Journal of Management Control, 29(1), 63-89.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harris, E. (2017). Strategic project risk appraisal and management. Routledge.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Hopkin, P. (2018). Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers.
Husin, S., & Malahayati, N. (2018, May). Identifying inaccuracy of MS Project using system analysis. In IOP Conference Series: Materials Science and Engineering (Vol. 352, No. 1, p. 012036). IOP Publishing.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Markou, C., Koulinas, G. K., & Vavatsikos, A. P. (2017). Project resources scheduling and leveling using Multi-Attribute Decision Models: Models implementation and case study. Expert Systems with Applications, 77, 160-169.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), 169-179.
Shakeri, M., Shayestegan, M., Abunima, H., Reza, S. S., Akhtaruzzaman, M., Alamoud, A. R. M., ... & Amin, N. (2017). An intelligent system architecture in home energy management systems (HEMS) for efficient demand response in smart grid. Energy and Buildings, 138, 154-164.
Stair, R., & Reynolds, G. (2017). Fundamentals of information systems. Cengage Learning.
Wager, K. A., Lee, F. W., & Glaser, J. P. (2017). Health care information systems: a practical approach for health care management. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2021). ICT Project Management. Retrieved from https://myassignmenthelp.com/free-samples/itc505-ict-project-management/risk-management-of-globex-corp.html.
"ICT Project Management." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/itc505-ict-project-management/risk-management-of-globex-corp.html.
My Assignment Help (2021) ICT Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/risk-management-of-globex-corp.html
[Accessed 15 April 2021].
My Assignment Help. 'ICT Project Management' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/itc505-ict-project-management/risk-management-of-globex-corp.html> accessed 15 April 2021.
My Assignment Help. ICT Project Management [Internet]. My Assignment Help. 2021 [cited 15 April 2021]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/risk-management-of-globex-corp.html.
Got a problematic term paper to write? Don’t worry for we’ve got your back. Whether you are having a problem understanding the essay topic or using the correct essay format, you will always get the necessary essay help from us. The materials provided by us will also help you learn how to write a term paper. This way, you can quickly write a superior-quality term paper the next time you have been assigned the task. Contact us today for help with your essay outline and essay editing services.
Answer: The project initiation and planning that was covered from week 1 to week 12 The lessons learned were skills, processes, human resource management, procurement management and project manager behavior in project initiating and planning process.Improvement on the lesson learnt will be enhanced by learning from the mistakes done in projects to gain necessary skills and knowledge. Lesson frameworkhow I planned to gather and document ...
Read MoreAnswer: Statement of Work The project is being carried out for ABC organization. The organization is a small-scale finance firm and has decided to implement a mobile application for managing its resources and business operations. The project is a mobile application development project for the client and it will include the primary activities as requirements analysis, application design, and source code development for the application, a...
Read MoreAnswer: In assessing the project, it is assumed that the programming of the project needs to deliver an outcome and paybacks in reference to the approved business case project. The closure report denote the final spending of the project as $688,978 on Opex and approximately 15,965, 644 on Capex over the acknowledged budgeted project of $650,000 and $18 M on Opex and Capex respectively (Stout, 2015). The closure also notes that the program has ...
Read MoreAnswer: Introduction of the Company XYZ is a software firm that is based out of Singapore and develops web applications and mobile applications for its customers. The company was incepted in the year 2009 and works in the domains as finance, healthcare, and commercial. There are currently 60 employees that are associated with the organization. The majority of the clients that are associated with the organization are small and medium sca...
Read MoreAnswer Constraints in Asian Immigrants Human Resource Management Research Statement Human workforce are one of the most prominent factors that defines the success of an organisation or project. Hence, it is of crucial importance to manage the human resources adequately. Additionally, the complexity of managing the human resources gets amplified if, the workforce consists of immigrants (Guo & A1 Ariss, 2015). Hence, the proposed work will...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
i was very satisfied with the responses provided to me for my assignment. It helped me to achieve high marks on my assignment. Thank you experts
Australia
Thanks. I love the fast solutions. I am sure that I will receive an excellent grade, as I usually do
Australia
Thanks for the fast solution. This is a reliable source that is sure to get you a good grade
Australia
Amazing! delivered on time was very patient and thank you so much for your efforts. I really appreciate :)
Australia