OMGT 229 Fundamentals Of Project Management For Local Planning Permission

tag 0 Download16 Pages / 3,785 Words tag Add in library Click this icon and make it bookmark in your library to refer it later. GOT IT
  • Course Code: OMGT 229
  • University: Centennial College
  • Country: Canada

Questions:

a)Please conceive a project that will consist of approximately 30-40 activities. The project should look like a real life scenario where activities are intertwined according to the logic of execution/processing.  The project chosen should be different than to those projects done in class. You are asked to provide in your project, the duration, the sequencing of the activities and corresponding resources.

b)First, solve your problem manually. After drawing the diagram network from both AoA, respectively AoN perspectives (preferably not by hand), you are asked to provide the afferent table and the critical path.(remember the first part of the course)

c)Second, using Microsoft Project, input your data and solve your envisioned project. Provide in printing a view of the overall diagram network, a Gantt chart showing the activities and their sequencing (predecessors), as well as durations, a summary of critical activities, a project overview report, a cost overview report and the list of activities containing the critical path.

 

Answer:

Project introduction

The project ‘Home Interior Design Construction Work’ has been chosen for this assignment. The project manager is responsible to develop a fruitful project plan for interior design of the home. He will arrange the stakeholders of the project. The stakeholders will work in accordance to the project plan. The project stakeholders will follow the project plan and will perform the interior design activities. The project will take 33 weeks to complete. The overall budget allocated for the project is $48,960. The business analyst will make all the contracts. The civil engineer will prepare the interior design work of home.

 

Project sequencing activities

Task Name

Predecessors

Home Interior Design Construction Work

 

   Business Contracts

 

      Questionnaire Fill Out

 

      Contract Sign for Home Interior Design Project

2

   Analysis of Design

 

      Questionnaire Review

3

      Research of Local Planning Permission

5

      Arrange Stakeholders

6

      Evaluation of Preliminary Costs for the Interior Design Works

7

   Contact with Local Authority with regards to Building Control Services and Planning Permission

 

      Documentation Preparation for Initial Contact with Local Authority

8

   Preparation of Design Concept Proposal for Project

 

      Concept Presentation to Client

10

      Client's Feedback

12

   Sourcing of Materials

 

      Technical Documentation Preparation

 

         Project for Engineering Systems and Communications

13

         Plans

16

         Lighting Plans

16

         Detailed Drawings of Ceilings

18

         Working Drawings

19

      Approval from Client's End

20

      Visual Materials Preparation

21

      Initiating Internal Constructing Works

 

         Electricity Lines Installation

22

         Heating System Installation

22

         Plumbing and Waterworks

22

         Air conditioning System, Light and Fan Installation

22

         Plastering Walls

22

         Installation of Tiles

28

         Installation of Canvas, Portraits and Showpiece

28

         Installation of Carpets

30

         Installation of Bed, Table and Chairs

30

      Installation of Furniture and Appliances

 

         Furniture and Appliances Installation at Kitchen

32

         Furniture and Appliances Installation at Bathroom

32

         Installation of Curtains, Hangings and Accessories

35

   Project Closure

36

Project Duration

Task Name

Duration

Start

Finish

Home Interior Design Construction Work

33 wks

Thu 26-04-18

Wed 12-12-18

   Business Contracts

2 wks

Thu 26-04-18

Wed 09-05-18

      Questionnaire Fill Out

1 wk

Thu 26-04-18

Wed 02-05-18

      Contract Sign for Home Interior Design Project

1 wk

Thu 03-05-18

Wed 09-05-18

   Analysis of Design

9 wks

Thu 10-05-18

Wed 11-07-18

      Questionnaire Review

1 wk

Thu 10-05-18

Wed 16-05-18

      Research of Local Planning Permission

2 wks

Thu 17-05-18

Wed 30-05-18

      Arrange Stakeholders

3 wks

Thu 31-05-18

Wed 20-06-18

      Evaluation of Preliminary Costs for the Interior Design Works

3 wks

Thu 21-06-18

Wed 11-07-18

   Contact with Local Authority with regards to Building Control Services and Planning Permission

1 wk

Thu 12-07-18

Wed 18-07-18

      Documentation Preparation for Initial Contact with Local Authority

1 wk

Thu 12-07-18

Wed 18-07-18

   Preparation of Design Concept Proposal for Project

3 wks

Thu 19-07-18

Wed 08-08-18

      Concept Presentation to Client

2 wks

Thu 19-07-18

Wed 01-08-18

      Client's Feedback

1 wk

Thu 02-08-18

Wed 08-08-18

   Sourcing of Materials

17 wks

Thu 09-08-18

Wed 05-12-18

      Technical Documentation Preparation

5 wks

Thu 09-08-18

Wed 12-09-18

         Project for Engineering Systems and Communications

2 wks

Thu 09-08-18

Wed 22-08-18

         Plans

2 wks

Thu 23-08-18

Wed 05-09-18

         Lighting Plans

1 wk

Thu 23-08-18

Wed 29-08-18

         Detailed Drawings of Ceilings

1 wk

Thu 30-08-18

Wed 05-09-18

         Working Drawings

1 wk

Thu 06-09-18

Wed 12-09-18

      Approval from Client's End

2 wks

Thu 13-09-18

Wed 26-09-18

      Visual Materials Preparation

1 wk

Thu 27-09-18

Wed 03-10-18

      Initiating Internal Constructing Works

6 wks

Thu 04-10-18

Wed 14-11-18

         Electricity Lines Installation

2 wks

Thu 04-10-18

Wed 17-10-18

         Heating System Installation

2 wks

Thu 04-10-18

Wed 17-10-18

         Plumbing and Waterworks

2 wks

Thu 04-10-18

Wed 17-10-18

         Air conditioning System, Light and Fan Installation

2 wks

Thu 04-10-18

Wed 17-10-18

         Plastering Walls

2 wks

Thu 04-10-18

Wed 17-10-18

         Installation of Tiles

2 wks

Thu 18-10-18

Wed 31-10-18

         Installation of Canvas, Portraits and Showpiece

2 wks

Thu 18-10-18

Wed 31-10-18

         Installation of Carpets

2 wks

Thu 01-11-18

Wed 14-11-18

         Installation of Bed, Table and Chairs

2 wks

Thu 01-11-18

Wed 14-11-18

      Installation of Furniture and Appliances

3 wks

Thu 15-11-18

Wed 05-12-18

         Furniture and Appliances Installation at Kitchen

2 wks

Thu 15-11-18

Wed 28-11-18

         Furniture and Appliances Installation at Bathroom

2 wks

Thu 15-11-18

Wed 28-11-18

         Installation of Curtains, Hangings and Accessories

1 wk

Thu 29-11-18

Wed 05-12-18

   Project Closure

1 wk

Thu 06-12-18

Wed 12-12-18

Project Budget and corresponding resource allocation

Task Name

Resource Names

Cost

Home Interior Design Construction Work

 

$48,960.00

   Business Contracts

 

$2,000.00

      Questionnaire Fill Out

Business Analyst,Client

$1,000.00

      Contract Sign for Home Interior Design Project

Business Analyst,Client

$1,000.00

   Analysis of Design

 

$12,000.00

      Questionnaire Review

Project Manager

$1,400.00

      Research of Local Planning Permission

Project Manager

$2,800.00

      Arrange Stakeholders

Project Manager

$4,200.00

      Evaluation of Preliminary Costs for the Interior Design Works

Construction Subcontractor

$3,600.00

   Contact with Local Authority with regards to Building Control Services and Planning Permission

 

$1,400.00

      Documentation Preparation for Initial Contact with Local Authority

Project Manager

$1,400.00

   Preparation of Design Concept Proposal for Project

 

$2,800.00

      Concept Presentation to Client

Project Manager

$2,800.00

      Client's Feedback

Client

$0.00

   Sourcing of Materials

 

$29,360.00

      Technical Documentation Preparation

 

$8,000.00

         Project for Engineering Systems and Communications

Construction Subcontractor

$2,400.00

         Plans

Construction Subcontractor

$2,400.00

         Lighting Plans

Construction Subcontractor

$1,200.00

         Detailed Drawings of Ceilings

Civil Engineer

$1,000.00

         Working Drawings

Civil Engineer

$1,000.00

      Approval from Client's End

Client

$0.00

      Visual Materials Preparation

Construction Subcontractor

$1,200.00

      Initiating Internal Constructing Works

 

$12,960.00

         Electricity Lines Installation

Builder

$1,600.00

         Heating System Installation

Builder

$1,600.00

         Plumbing and Waterworks

Builder

$1,600.00

         Air conditioning System, Light and Fan Installation

Electrician

$1,440.00

         Plastering Walls

Mason

$1,280.00

         Installation of Tiles

Builder

$1,600.00

         Installation of Canvas, Portraits and Showpiece

Wood Machinist

$1,280.00

         Installation of Carpets

Mason

$1,280.00

         Installation of Bed, Table and Chairs

Wood Machinist

$1,280.00

      Installation of Furniture and Appliances

 

$7,200.00

         Furniture and Appliances Installation at Kitchen

Mechanical Subcontractor,Wood Machinist

$2,880.00

         Furniture and Appliances Installation at Bathroom

Mechanical Subcontractor,Wood Machinist

$2,880.00

         Installation of Curtains, Hangings and Accessories

Mechanical Subcontractor,Wood Machinist

$1,440.00

   Project Closure

Project Manager

$1,400.00

Resource Sheet

Resource Name

Project Manager

Construction Subcontractor

Client

Builder

Electrician

Plumber

Wood Machinist

Mason

Civil Engineer

Business Analyst

Mechanical Subcontractor

ES = Early Start

LS = Late Start

EF = Early Finish

LF = Late Finish

ID

Task Name

Duration

ES

EF

LS

LF

Total Slack

0

Home Interior Design Construction Work

33 wks

 

 

 

 

0 wks

1

   Business Contracts

2 wks

 

 

 

 

0 wks

2

      Questionnaire Fill Out

1 wk

0

5

0

5

0 wks

3

      Contract Sign for Home Interior Design Project

1 wk

5

10

5

10

0 wks

4

   Analysis of Design

9 wks

 

 

 

 

0 wks

5

      Questionnaire Review

1 wk

10

15

10

15

0 wks

6

      Research of Local Planning Permission

2 wks

15

25

15

25

0 wks

7

      Arrange Stakeholders

3 wks

25

40

25

40

0 wks

8

      Evaluation of Preliminary Costs for the Interior Design Works

3 wks

40

55

40

55

0 wks

9

   Contact with Local Authority with regards to Building Control Services and Planning Permission

1 wk

 

 

 

 

0 wks

10

      Documentation Preparation for Initial Contact with Local Authority

1 wk

55

60

55

60

0 wks

11

   Preparation of Design Concept Proposal for Project

3 wks

 

 

 

 

0 wks

12

      Concept Presentation to Client

2 wks

60

70

60

70

0 wks

13

      Client's Feedback

1 wk

70

75

70

75

0 wks

14

   Sourcing of Materials

17 wks

 

 

 

 

1 wk

15

      Technical Documentation Preparation

5 wks

 

 

 

 

0 wks

16

         Project for Engineering Systems and Communications

2 wks

75

85

75

85

0 wks

17

         Plans

2 wks

85

95

155

165

14 wks

18

         Lighting Plans

1 wk

85

90

85

90

0 wks

19

         Detailed Drawings of Ceilings

1 wk

90

95

90

95

0 wks

20

         Working Drawings

1 wk

95

100

95

100

0 wks

21

      Approval from Client's End

2 wks

100

110

100

110

0 wks

22

      Visual Materials Preparation

1 wk

110

115

110

115

0 wks

23

      Initiating Internal Constructing Works

6 wks

 

 

 

 

4 wks

24

         Electricity Lines Installation

2 wks

115

125

155

165

8 wks

25

         Heating System Installation

2 wks

115

125

155

165

8 wks

26

         Plumbing and Waterworks

2 wks

115

125

155

165

8 wks

27

         Air conditioning System, Light and Fan Installation

2 wks

115

125

155

165

8 wks

28

         Plastering Walls

2 wks

115

125

115

125

0 wks

29

         Installation of Tiles

2 wks

125

135

125

165

6 wks

30

         Installation of Canvas, Portraits and Showpiece

2 wks

125

135

125

135

0 wks

31

         Installation of Carpets

2 wks

135

145

155

165

4 wks

32

         Installation of Bed, Table and Chairs

2 wks

135

145

135

145

0 wks

33

      Installation of Furniture and Appliances

3 wks

 

 

 

 

0 wks

34

         Furniture and Appliances Installation at Kitchen

2 wks

145

155

155

165

2 wks

35

         Furniture and Appliances Installation at Bathroom

2 wks

145

155

145

155

0 wks

36

         Installation of Curtains, Hangings and Accessories

1 wk

155

160

155

160

0 wks

37

   Project Closure

1 wk

160

165

160

165

0 wks

AON diagram is showcased in ‘Collapsed Box’ mode. The AON diagram is shown elaborately in the below diagrams. The diagrams illustrate the list of activities along with early start (ES), early finish (EF), late start (LS), late finish (LF) and total slack.

Project Overview
 

 

 

Project description

 The project is about interior design construction of home

 

 

Expected investment requirement and

 The overall budget for the interior design project is $48, 960

private capital component

 

 

 

Project Deliverables:

 The interior design of the home involves business contracts, design analysis, contact with local authority with regards to building control services and planning permission. The internal construction work associates the electricity lines installation, installation of plumbing and waterworks, installation of carpets, installation of bed, table and chairs. The project duration is 33 weeks

 

 

Project Milestones:

Business Contract will be signed on 9 May. Design Analysis will be completed by 11 July. Contact with local authority will be completed by 18 July. Technical Documentation preparation will be completed by 3 October. Internal Construction Work will be completed by 14 November. Finally the project will be completed by 12 December

 

 

 

Project manager, construction subcontractor, client, builder, electrician, plumber, wood machinist, mason, civil engineer, business analyst, mechanical subcontractor are the stakeholders of the project

Stakeholders Involved:

 

 

 

Project Summary Activities

Task Name

Home Interior Design Construction Work

   Business Contracts

   Analysis of Design

   Contact with Local Authority with regards to Building Control Services and Planning Permission

   Preparation of Design Concept Proposal for Project

   Sourcing of Materials

      Technical Documentation Preparation

      Approval from Client's End

      Visual Materials Preparation

      Initiating Internal Constructing Works

      Installation of Furniture and Appliances

   Project Closure

Project durations

Task Name

Duration

Start

Finish

Home Interior Design Construction Work

33 wks

Thu 26-04-18

Wed 12-12-18

   Business Contracts

2 wks

Thu 26-04-18

Wed 09-05-18

   Analysis of Design

9 wks

Thu 10-05-18

Wed 11-07-18

   Contact with Local Authority with regards to Building Control Services and Planning Permission

1 wk

Thu 12-07-18

Wed 18-07-18

   Preparation of Design Concept Proposal for Project

3 wks

Thu 19-07-18

Wed 08-08-18

   Sourcing of Materials

17 wks

Thu 09-08-18

Wed 05-12-18

      Technical Documentation Preparation

5 wks

Thu 09-08-18

Wed 12-09-18

      Approval from Client's End

2 wks

Thu 13-09-18

Wed 26-09-18

      Visual Materials Preparation

1 wk

Thu 27-09-18

Wed 03-10-18

      Initiating Internal Constructing Works

6 wks

Thu 04-10-18

Wed 14-11-18

      Installation of Furniture and Appliances

3 wks

Thu 15-11-18

Wed 05-12-18

   Project Closure

1 wk

Thu 06-12-18

Wed 12-12-18

Project cost overview

Task Name

Cost

Home Interior Design Construction Work

$48,960.00

   Business Contracts

$2,000.00

   Analysis of Design

$12,000.00

   Contact with Local Authority with regards to Building Control Services and Planning Permission

$1,400.00

   Preparation of Design Concept Proposal for Project

$2,800.00

   Sourcing of Materials

$29,360.00

      Technical Documentation Preparation

$8,000.00

      Approval from Client's End

$0.00

      Visual Materials Preparation

$1,200.00

      Initiating Internal Constructing Works

$12,960.00

      Installation of Furniture and Appliances

$7,200.00

   Project Closure

$1,400.00

List of activities containing critical path

Task Name

Duration

Home Interior Design Construction Work

33 wks

   Business Contracts

2 wks

      Questionnaire Fill Out

1 wk

      Contract Sign for Home Interior Design Project

1 wk

   Analysis of Design

9 wks

      Questionnaire Review

1 wk

      Research of Local Planning Permission

2 wks

      Arrange Stakeholders

3 wks

      Evaluation of Preliminary Costs for the Interior Design Works

3 wks

   Contact with Local Authority with regards to Building Control Services and Planning Permission

1 wk

      Documentation Preparation for Initial Contact with Local Authority

1 wk

   Preparation of Design Concept Proposal for Project

3 wks

      Concept Presentation to Client

2 wks

      Client's Feedback

1 wk

   Sourcing of Materials

17 wks

      Technical Documentation Preparation

5 wks

         Project for Engineering Systems and Communications

2 wks

         Lighting Plans

1 wk

         Detailed Drawings of Ceilings

1 wk

         Working Drawings

1 wk

      Approval from Client's End

2 wks

      Visual Materials Preparation

1 wk

      Initiating Internal Constructing Works

6 wks

         Plastering Walls

2 wks

         Installation of Canvas, Portraits and Showpiece

2 wks

         Installation of Bed, Table and Chairs

2 wks

      Installation of Furniture and Appliances

3 wks

         Furniture and Appliances Installation at Bathroom

2 wks

         Installation of Curtains, Hangings and Accessories

1 wk

   Project Closure

1 wk

Total Duration

17 wks

The above list explains the list of activities containing the critical path. After analysing the critical path, it is found that the duration of the critical path is 17 weeks.

 

References

Bennett Ph D, B. and Brown, J., 2016. The Design, Construction, and Flight of a High Altitude Particle Collector.

Bosch-Sijtsema, P.M. and Tjell, J., 2017. The concept of project space: Studying construction project teams from a spatial perspective. International Journal of Project Management, 35(7), pp.1312-1321.

Boyle, G., 2017. Design project management. Routledge.

Brook, M., 2016. Estimating and tendering for construction work. Taylor & Francis.

Burtonshaw-Gunn, S.A., 2017. Risk and financial management in construction. Routledge.

Clayton, R.A., 2015, September. Improvements in full depth asphalt pavement specifications and construction practices in Western Australia. In AAPA International Flexible Pavements Conference, 16th, 2015, Gold Coast, Queensland, Australia.

Clough, R.H., Sears, G.A., Sears, S.K., Segner, R.O. and Rounds, J.L., 2015. Construction contracting: A practical guide to company management. John Wiley & Sons.

Davis, J. and Russell, L., 2015. The transport and beneficial re-use of Crossrail excavated material. In Crossrail Project: Infrastructure design and construction (pp. 241-250). ICE Publishing.

Eastman, C.M., 2018. Building product models: computer environments, supporting design and construction. CRC press.

Gao, L., Fang, Z., Gao, W., Gu, T., Zhang, L. and Li, Q., 2015, February. The construction of outstanding Engineers’ training-oriented physical chemistry curriculum system. In Future Communication, Information and Computer Science: Proceedings of the 2014 International Conference on Future Communication, Information and Computer Science (FCICS 2014), May 22-23, 2014, Beijing, China. (p. 173). CRC Press.

Gewirth, A.A., Feliu, J.M., Kuwabata, S. and Murakoshi, K., 2016. Preface to the Kohei Uosaki Festschrift: Electrochemistry of Ordered Interfaces? Design, Construction, and Interrogation of Functional Electrochemical Interphases with Atomic/Molecular Resolution.

Islam, H., Zhang, G., Setunge, S. and Bhuiyan, M.A., 2016. Life cycle assessment of shipping container home: A sustainable construction. Energy and Buildings, 128, pp.673-685.

Jin, R., Yang, T., Piroozfar, A., Kang, B.G., Wanatowski, D. and Hancock, C., 2017. Project-based pedagogy in interdisciplinary building design adopting BIM. Engineering, Construction and Architectural Management.

Kog, Y.C., 2017. Project Management and Delay Factors of Public Housing Construction. Practice Periodical on Structural Design and Construction, 23(1), p.04017028.

Lu, W., Fung, A., Peng, Y., Liang, C. and Rowlinson, S., 2015. Demystifying construction project time–effort distribution curves: BIM and non-BIM comparison. Journal of Management in Engineering, 31(6), p.04015010.

Peterson, S., Braun, S., Salazar, J. and Balmaseda, M.S., 2017. Accelerating Pre-construction Project Delivery (No. 17-05044).

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction project management. John Wiley & Sons.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Walker, D.H., 2016. Reflecting on 10 years of focus on innovation, organisational learning and knowledge management literature in a construction project management context. Construction Innovation, 16(2), pp.114-126.

Download Sample

Get 100% money back after download, simply upload your unique content* of similar no. of pages or more. We verify your content and once successfully verified 100% value credited to your wallet within 7 days.

Upload Unique Document

Document Under Evaluation

Get Credits into Your Wallet

*The content must not be available online or in our existing Database to qualify as unique.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). Fundamentals Of Project Management For Local Planning Permission. Retrieved from https://myassignmenthelp.com/free-samples/omgt-229-fundamentals-of-project-management-for-local-planning-permission.

"Fundamentals Of Project Management For Local Planning Permission." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/omgt-229-fundamentals-of-project-management-for-local-planning-permission.

My Assignment Help (2020) Fundamentals Of Project Management For Local Planning Permission [Online]. Available from: https://myassignmenthelp.com/free-samples/omgt-229-fundamentals-of-project-management-for-local-planning-permission
[Accessed 07 August 2020].

My Assignment Help. 'Fundamentals Of Project Management For Local Planning Permission' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/omgt-229-fundamentals-of-project-management-for-local-planning-permission> accessed 07 August 2020.

My Assignment Help. Fundamentals Of Project Management For Local Planning Permission [Internet]. My Assignment Help. 2020 [cited 07 August 2020]. Available from: https://myassignmenthelp.com/free-samples/omgt-229-fundamentals-of-project-management-for-local-planning-permission.


The hardest part of writing an essay is coming up with a good essay conclusion. It needs to engage the readers and leave an everlasting impression on them. If you think your conclusion isn’t going to cut the mustard, get best essay writing services from MyAssignmenthelp.com. Apart from helping you write an essay, we also essay editing and use the referencing tool on your paper to enhance the overall quality.

Latest Management Samples

MPF753 Finance For Consumer Discretionary And Descriptive Analysis

Download : 0 | Pages : 13
  • Course Code: MPF753
  • University: Deakin Business School
  • Country: Australia

Answer: 1. Stating the calculations of descriptive analysis for initial returns and interpret the Australian IPO market: Descriptive Analysis (Initial return): IPO Return Mean 9.423% Standard Error 4.941% Median 5.778% Mode 0.000% Standard Deviation 26.146% Sample Variance 6.836% Kurtosis 607.687% Skewness 144.621% R...

Read More arrow

MA613 Taxation Law For Business Firm And Profit Making Decisions

Download : 0 | Pages : 10

Answer: Answer to question 1:  Small business can be defined as the independently owned and operated organization, which is restricted in size and revenue based on the industry. A small business generally refers to the aggregate turnover, which is derived by the business in the ordinary course of business during the income year along with the yearly turnover of the entities connected with its affiliates (Barkoczy, 2016). The term is gene...

Read More arrow

7AC006 Managing Financial Performance For Performance Measurement

Download : 0 | Pages : 8
  • Course Code: 7AC006
  • University: University Of Wolverhampton
  • Country: United Kingdom

Answer: Introduction: In this report, various measurement techniques have been analyzed which makes it easier for every organization to evaluate the various micro and macro factors which could make an impact over the functions and the performance of the company (Damodaran, 2011).   Performance measurement techniques: Performance measurement is a procedure to collect, analyze, report the information related to the financial performance...

Read More arrow Tags: Australia Sydney Management Managing Financial Performance  University of Sydney MBA 

PADM6200 Nonprofit Organizations

Download : 0 | Pages : 4
  • Course Code: PADM6200
  • University: Hawaii Pacific University
  • Country: United States

Answer: Introduction NCHV or The National Coalition for Homeless Veterans is a USA based non-profit organization formed to secure social welfare for the homeless veterans, who suffer from different kinds of mental as well as physical illness and seeks help to get rid of these (Ainslie & Cooper, 2016). NCHV is determined to eliminate all these problems through structuring, to implement public policies, to promote partnerships and to build ...

Read More arrow Tags: United States Honolulu 42 SWOT Analysis and Recommendations for THE NATIONAL COALITION FOR HOMELESS VETERANS Other 

HLTENN004 Nursing Case Study For Post Traumatic Stress Disorder

Download : 0 | Pages : 10

Answer: Part A: Diagnosis and its effects: The resident, a 60 year old retired Army veteran, (name withheld to maintain privacy of the client), having a history of Post Traumatic Stress Disorder, with which he had been suffering for the last 10 years, and have been recently diagnosed with Alzheimer’s disease. The client developed the PTSD syndrome while on duty, and exposed to the different mental stress commonly seen with war veterans. T...

Read More arrow Tags: Australia Arlington Management University of New South Wales 
Next
watch

Save Time & improve Grade

Just share Requriment and get customize Solution.

question
We will use e-mail only for:

arrow Communication regarding your orders

arrow To send you invoices, and other billing info

arrow To provide you with information of offers and other benefits

1,379,740

Orders

4.9/5

Overall Rating

5,085

Experts

Our Amazing Features

delivery

On Time Delivery

Our writers make sure that all orders are submitted, prior to the deadline.

work

Plagiarism Free Work

Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.

time

24 X 7 Live Help

Feel free to contact our assignment writing services any time via phone, email or live chat.

subject

Services For All Subjects

Our writers can provide you professional writing assistance on any subject at any level.

price

Best Price Guarantee

Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.

Our Experts

Assignment writing guide
student rating student rating student rating student rating student rating 5/5

1265 Order Completed

97% Response Time

James Cook

Masters in Management

Wellington, New Zealand

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

2115 Order Completed

97% Response Time

Kimberley Chen

MPA in Accounting

Singapore, Singapore

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

230 Order Completed

97% Response Time

Liya Han

Master Of Science in Geotechnical Engineering (MSc Geotec)

Singapore, Singapore

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

529 Order Completed

95% Response Time

Ivan Blank

PhD in Functional Human Biology

Wellington, New Zealand

Hire Me

FREE Tools

plagiarism

Plagiarism Checker

Get all your documents checked for plagiarism or duplicacy with us.

essay

Essay Typer

Get different kinds of essays typed in minutes with clicks.

edit

GPA Calculator

Calculate your semester grades and cumulative GPa with our GPA Calculator.

referencing

Chemical Equation Balancer

Balance any chemical equation in minutes just by entering the formula.

calculator

Word Counter & Page Calculator

Calculate the number of words and number of pages of all your academic documents.

Refer Just 5 Friends to Earn More than $2000

Check your estimated earning as per your ability

1

1

1

Your Approx Earning

Live Review

Our Mission Client Satisfaction

Awesome work. Awesome response time. Very thorough & clear. Love the results I get with MAH!

flag

User Id: 383727 - 31 Jul 2020

Australia

student rating student rating student rating student rating student rating

Work was done in a timely manner took it through grammarly checked for plagiarism very well satisfied

flag

User Id: 463334 - 31 Jul 2020

Australia

student rating student rating student rating student rating student rating

Great work for the short notice given. Thank you for never disappointing and helping out.

flag

User Id: 194216 - 31 Jul 2020

Australia

student rating student rating student rating student rating student rating

I received a full point on the assignment. Thank you for all the help with the assignment.

flag

User Id: 411395 - 31 Jul 2020

Australia

student rating student rating student rating student rating student rating
callback request mobile
Have any Query?