The cost estimate for the project is provided in the table below:
Task Name |
Duration |
Cost |
The Bungalow Project |
136 days |
$ 231,000.00 |
Clear ground |
2 wks. |
$ 14,600.00 |
Lay foundation |
3 wks. |
$ 18,000.00 |
Build dwarf walls |
2 wks. |
$ 9,800.00 |
Over site concrete |
1 wk. |
$ 5,600.00 |
Floor joists |
2 wks. |
$ 8,200.00 |
Main walls |
5 wks. |
$ 28,000.00 |
Door and Window and frame |
3 wks. |
$ 12,600.00 |
Ceiling joists |
2 wks. |
$ 8,400.00 |
Roof timbers |
6 wks. |
$ 25,200.00 |
Tiles |
2 wks. |
$ 10,800.00 |
Floorboards |
3 wks. |
$ 12,900.00 |
Celling boards |
2 wks. |
$ 7,800.00 |
Skirting |
1 wk. |
$ 3,800.00 |
Glazing |
2 wks. |
$ 8,000.00 |
Plastering |
2 wks. |
$ 6,600.00 |
3 wks. |
$ 12,600.00 |
|
Plumbing and heating |
4 wks. |
$ 15,600.00 |
Painting |
3 wks. |
$ 22,500.00 |
The tools and techniques that can be utilized for estimating the cost of the project are as follows:
Expert Judgement: It generally utilizes the knowledge as well as experience of the experts who are involved with the project for estimating the cost of the project successfully (Fayard et al., 2014). It is found that this technique can take number of factors into account and thus it can be biased.
Analogous estimation: Analogous estimation utilizes historical data of the similar projects as a basis in order to estimate the cost of the project. This method of estimate is generally can be adjusted for knowing the differences that exists between various projects. This type of estimate is mainly utilized in the initiation phase of the project. It is identified that this method of technique is not much accurate as compared to other methods that are used (Gopalakrishnan et al., 2015).
Parametric estimation: It is found that parametric estimation generally utilizes statistical model for estimating the cost. It generally uses historical data of key cost drivers for calculating a estimate for various parameters including the cost and duration.
Bottom up estimation: It generally utilizes the estimate of different work packages, which are mainly summarized as rolled up for determining the overcall cot that is required for finishing the project (Liu et al., 2015). It is found that this technique of cost estimate is quite accurate as compared to other methods as it generally reflects on the cost from a much more granular perspective.
Three-point estimation: Three-point estimation was mainly originated with the help of program evaluation as well as review technique. This method mainly utilizes three estimates for defining an approximation range for the various activities related cost. The most likely cost estimation is done with the help of the formula= (C0+4Cm+Cp)/6.
Reserve analysis: Reserve analysis is mainly utilized for determining the contingency reserve and it must be properly allocated to the entire project. This method of funding is mainly utilized for estimating the cost uncertainty.
Project management estimating software: It found that project management estimating software includes cost estimation related applications, simulation applications, spreadsheet as well as statistical software related tools (Sunil, Pathirage & Underwood, 2015). This type of software is mainly us at cost estimation related alternatives.
Vendor analysis: This method is mainly utilized for estimating that the cost of the project by making proper comparison with the help of the bids that is mainly submitted by multiple vendors.
1.4 Justification for the budgetary plan
It is found that three-point cost estimation method is mainly utilized for estimating the cost that is associated with the bungalow project. This method is mainly selected as the project considers both optimistic and Pessimistic situations. It is identified from the project that if everything goes right then the schedule of the project will get completed 20% faster whereas if something went wrong then time of the project enhances by 50%. It is found that both the situation creates impact on the cost of the project (Boute, Bruggeman & Vereecke, 2014). This method is generally considered as accurate method of cost estimation. The cost that is estimated through three-point estimation method is provided in the table below:
Three Point Estimates |
||||
WBS ID |
||||
A |
27300 |
18200 |
14560 |
19110 |
B |
52650 |
35100 |
28080 |
36855 |
C |
38100 |
25400 |
20320 |
26670 |
D |
10200 |
6800 |
5440 |
7140 |
E |
15000 |
10000 |
8000 |
10500 |
F |
100500 |
67000 |
53600 |
70350 |
G |
22950 |
15300 |
12240 |
16065 |
H |
15300 |
10200 |
8160 |
10710 |
J |
45900 |
30600 |
24480 |
32130 |
K |
32850 |
21900 |
17520 |
22995 |
L |
23400 |
15600 |
12480 |
16380 |
M |
14400 |
9600 |
7680 |
10080 |
N |
7050 |
4700 |
3760 |
4935 |
P |
14700 |
9800 |
7840 |
10290 |
Q |
25650 |
17100 |
13680 |
17955 |
R |
22950 |
15300 |
12240 |
16065 |
S |
54900 |
36600 |
29280 |
38430 |
T |
41850 |
27900 |
22320 |
29295 |
The roles and responsibilities are listed below:
Supervisor: The supervisors are the persons who are mainly responsible for completing the day-to-day performance of the project. It is found that they generally helps in checking the materials that are used, quality of training delivered, and performance of the team for maintain the quality of the project for avoiding problems and issues (Goetsch & Davis, 2014).
Labourers: The labourers who are mainly involved with the Bungalow project are mainly responsible of laying foundations, developing over site concrete, plumbing as well as plastering for finishing the entire project with proper quality.
Tradesman: The tradesman who are associated with the bungalow project are generally responsible of completing the various activities of the project including development of skirting, plumbing, plastering, main walls and more properly for avoiding quality related challenges (Sanz-Calcedo et al., 2015).
Project manager: The project manager is the person, who is mainly responsible of organizing, planning both the time and resources of the project for finishing the entire project within the time that is estimated. They are also responsible of checking, monitoring as well as assembling the entire project so that no quality related issues could occur within the project.
2.2 Quality planning approach
The quality of the Bungalow project will be maintained properly if the goals and objectives, which are related with the project, are achieved properly. It is found that it is quite necessary to utilize integrated quality approach for proper planning of project in order to maintain quality. Integrated quality approach are mainly utilized for measuring, defining as well as for improving the quality of the project effectively (Molina-Azorín, et al., 2015).
The quality of the project will generally focus on the procedures and processes with the help of which proper project deliverable is developed. It is identified that proper establishment of standard that are associated with the quality are very much beneficial in delivering the entire project successfully with proper quality. The metrics, which should be properly maintained for maintaining the project quality, includes cost, resources, customer satisfaction, product performance and more.
2.3 Quality assurance approach
Quality assurance approach generally reflects on the processes, which are generally used in order to construct the Bungalow project. In order to ensure the quality of the project, it is identified that an iterative procedure will generally be used throughout the project lifecycle (O’Neill, Sohal & Teng, 2016). It is found that this iterative procedure generally includes measurement of various metrics, improving the process as well as analysis of data. It is the responsibility of the project manager to conduct quality-monitoring processes on a daily basis for monitoring the performance of the project.
2.4 Quality control approach
The quality of the Bungalow project needs to be maintained and for this the challenges and issues, which are mainly associated with the project, needs to be controlled (Zeng, Phan & Matsui, 2015). It is the responsibility of both the quality analyst as well as the project manager to work together and focus on monitoring the activities that are performed for ensuring that proper quality is maintained while performing the project activities. The quality control approaches, which are mainly used for controlling the project quality, are listed below:
It is found that for improving the project quality, it is very much essential for the project managers to take some steps that are very much helpful in resolving the quality related issues, which are mainly associated with the project (Sanz-Calcedo et al., 2014). The steps that are needed to be followed for improving the quality are listed below:
It is identified that by following the steps, which are provided above, the issues related with the project can be resolved and the project manager can be able to improve the quality of the project.
Boute, R., Bruggeman, W., & Vereecke, A. (2014). Cost Management in the Supply Chain: an integrated approach. Cost Management, 11-15.
Fayard, D., Lee, L. S., Leitch, R. A., & Kettinger, W. J. (2014). Interorganizational cost management in supply chains: Practices and payoffs. Management accounting quarterly, 15(3), 1-9.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence. Upper Saddle River, NJ: pearson.
Gopalakrishnan, M., Libby, T., Samuels, J. A., & Swenson, D. (2015). The effect of cost goal specificity and new product development process on cost reduction performance. Accounting, Organizations and Society, 42, 1-11.
Liu, L., Sun, J., Ni, Y., Yang, S., & Song, P. A. (2018). Discussion on cost control experience in construction project management. Smart Construction Research, 2(3).
Molina-Azorín, J. F., Tarí, J. J., Pereira-Moliner, J., López-Gamero, M. D., & Pertusa-Ortega, E. M. (2015). The effects of quality and environmental management on competitive advantage: A mixed methods study in the hotel industry. Tourism Management, 50, 41-54.
O’Neill, P., Sohal, A., & Teng, C. W. (2016). Quality management approaches and their impact on firms? financial performance–An Australian study. International Journal of Production Economics, 171, 381-393.
Sanz-Calcedo, J. G., González, A. G., López, O., Salgado, D. R., Cambero, I., & Herrera, J. M. (2015). Analysis on integrated management of the quality, environment and safety on the industrial projects. Procedia Engineering, 132, 140-145.
Sunil, K., Pathirage, C., & Underwood, J. (2015, June). The importance of integrating cost management with building information modeling (BIM). International Postgraduate Research Conference (IPGRC 2015).
Zeng, J., Phan, C. A., & Matsui, Y. (2015). The impact of hard and soft quality management on quality and innovation performance: An empirical study. International journal of production economics, 162, 216-226.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2021). Project Planning And Budgeting. Retrieved from https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/similar-projects.html.
"Project Planning And Budgeting." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/similar-projects.html.
My Assignment Help (2021) Project Planning And Budgeting [Online]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/similar-projects.html
[Accessed 16 April 2021].
My Assignment Help. 'Project Planning And Budgeting' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/similar-projects.html> accessed 16 April 2021.
My Assignment Help. Project Planning And Budgeting [Internet]. My Assignment Help. 2021 [cited 16 April 2021]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/similar-projects.html.
MyAssignmenthelp.com is the perfect solution to render quality solution for all sort of academic issues. We have hired professionals from different fields of study to provide assistance with different subjects. We successfully have provided different types of assignment solutions on 100+ subjects. We have hired industry experts to deliver nursing assignment, hr assignment and finance assignment help. To offer quality content with IT assignments, we have hired IT professionals to render programming language assignment help and IT assignment help for other types of IT assignments as well.
Answer: Introduction The report discusses the activity-on-node, Gantt chart and critical path for the project plan of new hybrid handheld game console project. The main activities of the project plan are requirements specification, content specification, design, implementation, integration and subcontracting. In this report, the project management tool such as Gantt chart is used to represent the time for each project activities needed to com...
Read MoreAnswer: The project initiation and planning that was covered from week 1 to week 12 The lessons learned were skills, processes, human resource management, procurement management and project manager behavior in project initiating and planning process.Improvement on the lesson learnt will be enhanced by learning from the mistakes done in projects to gain necessary skills and knowledge. Lesson frameworkhow I planned to gather and document ...
Read MoreAnswer: Statement of Work The project is being carried out for ABC organization. The organization is a small-scale finance firm and has decided to implement a mobile application for managing its resources and business operations. The project is a mobile application development project for the client and it will include the primary activities as requirements analysis, application design, and source code development for the application, a...
Read MoreAnswer: In assessing the project, it is assumed that the programming of the project needs to deliver an outcome and paybacks in reference to the approved business case project. The closure report denote the final spending of the project as $688,978 on Opex and approximately 15,965, 644 on Capex over the acknowledged budgeted project of $650,000 and $18 M on Opex and Capex respectively (Stout, 2015). The closure also notes that the program has ...
Read MoreAnswer: Introduction of the Company XYZ is a software firm that is based out of Singapore and develops web applications and mobile applications for its customers. The company was incepted in the year 2009 and works in the domains as finance, healthcare, and commercial. There are currently 60 employees that are associated with the organization. The majority of the clients that are associated with the organization are small and medium sca...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
Great work by team i got good marks in every assessment i got credit in every subject
Australia
Best service forever i was try lot of websites but my friend recommended this one then i got positive reviews and positive comments from the tutors
Australia
The tutor was very helpful and got the job done quite quickly considering how little time they had to do the assessment. The critical reflections were outstanding and well written! Thank you very much for the hard work!
Australia
They are fast in revising work and making sure its done properly. great CSS, in addition work is promptly done
Australia