Introduction

This project is based on the purchase and implementation of a Big Data Analytics package for Intelligent Information Inc that will enhance the existing business operations and marketing policies of the company (Marz and Warren 2015). The implementation of the Big Data Analytics Package has been suggested by the CIO due to a number of reasons. Firstly, the Big Data Analytics Package will be able to provide an integrated platform on which all the various required operations from different stakeholder groups can be performed all at once. This will replace the need for separate platforms for each department that are not only hard to manage but also have too much maintenance and management costs (Wamba et al. 2015). Secondly, with the new analytics platform almost of the operations will become automated and not further require too much human interference. This will also reduce the operational errors caused by the manual management systems.

Project Charter

Project Background

The CIO of Intelligent Information Inc wants to deploy a suitable big data platform that will help various stakeholder groups of the company. Some of the important requirements include identification of potential customers, improvement of service, management and maintenance of IoT sensors, fraud detection and prevention and others (Dhamodaran, Sachin and Kumar 2015). The main challenge of the development is that all of the requirements should be met such that all of these should be integrated within one common platform. In other words, there should not be separate systems for the different requirements; there will be one common platform through all of the required operations can be performed.

Project Scope Statement

Based on the background and requirements of the project, the project scope can be determined as follows.

Scope 1 – Purchase and implementation of a Big Data Analytics Package is within the scope of the project.

Scope 2 – Integration of all stakeholder groups is within the scope of the project.

Project Objectives

The objectives of the project are as follows.

  • To hire a suitable consultant for helping to identify best analytics package
  • To recruit project team consisting of technical experts
  • To procure sufficient budget for the project
  • To deploy the new Big Data Analytics Platform
  • To train the existing employees to use the system
 

Implementation Plan

Project Schedule

The estimated project schedule is shown in the following table.

Task Name

Duration

Start

Finish

Implementation of Big Data Analytics

142 days

Mon 02-04-18

Tue 16-10-18

   Project Initiation

10 days

Mon 02-04-18

Fri 13-04-18

      Appointment of Project Manager

2 days

Mon 02-04-18

Tue 03-04-18

      Listing of Project Requirements

2 days

Wed 04-04-18

Thu 05-04-18

      Meeting between Primary Stakeholders

1 day

Fri 06-04-18

Fri 06-04-18

      Preparation of List of Deliverables

1 day

Mon 09-04-18

Mon 09-04-18

      Consultation with Big Data Expert

2 days

Tue 10-04-18

Wed 11-04-18

      Finalization of Plan

2 days

Thu 12-04-18

Fri 13-04-18

   Project Preparations

32 days

Mon 16-04-18

Tue 29-05-18

      Preparation of Project Charter

5 days

Mon 16-04-18

Fri 20-04-18

      Determination of Project Scope

2 days

Mon 23-04-18

Tue 24-04-18

      Determination of Project Objectives

1 day

Wed 25-04-18

Wed 25-04-18

      Preparation of Project Schedule

2 days

Thu 26-04-18

Fri 27-04-18

      Estimation of Project Budget

3 days

Mon 30-04-18

Wed 02-05-18

      Assign Roles to Stakeholders

4 days

Thu 03-05-18

Tue 08-05-18

      Preparation of Stakeholder management Plan

2 days

Wed 09-05-18

Thu 10-05-18

      Analysis of Potential Risks

4 days

Fri 11-05-18

Wed 16-05-18

      Preparation of Risk management Strategy

3 days

Thu 17-05-18

Mon 21-05-18

      Procurement of Project Budget

2 days

Tue 22-05-18

Wed 23-05-18

      Allocation of Duties and Roles

2 days

Thu 24-05-18

Fri 25-05-18

      Deployment of Project Teams

2 days

Mon 28-05-18

Tue 29-05-18

   Project Execution

88 days

Wed 30-05-18

Fri 28-09-18

      Purchase of Necessary Hardware

15 days

Wed 30-05-18

Tue 19-06-18

      Purchase of Necessary Software

10 days

Wed 20-06-18

Tue 03-07-18

      Installation of Hardware and Software

15 days

Wed 04-07-18

Tue 24-07-18

      Installation of Big Data Platform

5 days

Wed 25-07-18

Tue 31-07-18

      Purchase of Big Data Analytics Package

4 days

Wed 01-08-18

Mon 06-08-18

      Phase 1: Marketing

15 days

Tue 07-08-18

Mon 27-08-18

         Installation of Sales Forecast Feature

5 days

Tue 07-08-18

Mon 13-08-18

         Installation of Potential Customer Identification Feature

5 days

Tue 14-08-18

Mon 20-08-18

         Testing of the System

5 days

Tue 21-08-18

Mon 27-08-18

      Phase 2: Operations

9 days

Tue 28-08-18

Fri 07-09-18

         Link the Platform to Existing IoT Sensors

2 days

Tue 28-08-18

Wed 29-08-18

         Control the Sensors using the Big Data

2 days

Thu 30-08-18

Fri 31-08-18

         Testing of the System

5 days

Mon 03-09-18

Fri 07-09-18

      Phase 3: Risks

15 days

Mon 10-09-18

Fri 28-09-18

         Install Fraud Detection Feature

5 days

Mon 10-09-18

Fri 14-09-18

         Install Fraud Prevention Feature

5 days

Mon 17-09-18

Fri 21-09-18

         Testing of the System

5 days

Mon 24-09-18

Fri 28-09-18

   Project Closing

12 days

Mon 01-10-18

Tue 16-10-18

      Project Handover

5 days

Mon 01-10-18

Fri 05-10-18

      Project Documentation

5 days

Mon 08-10-18

Fri 12-10-18

      Stakeholder Sign Off

1 day

Mon 15-10-18

Mon 15-10-18

      Final Closing

1 day

Tue 16-10-18

Tue 16-10-18

Project Budget

The overall budget of the project is estimated as follows.

Resources / Requirements

Estimated Cost

Hardware Requirements

$50,000

Necessary Software

$10,000

Big Data Analytics Platform

$40,000

Development Costs

$10,000

Developer Wages and Consultation Fees

$15,000

Stakeholder Wages and Payments

$25,000

TOTAL

$1,500,000

Risk Management Plan

The risk management plan for the project is developed using risk register matrix as follows.

Risk Description

Chance of Occurrence

Impact on Project

Mitigation Strategy

Scope Creep caused due to inappropriate definition of project scope

High

High

Define scope statement properly during development of the project charter

Budget overshoot due to additional costs and expenses

High

Very High

Develop accurate budget estimation and keep 10-20% of the budget as contingency money (Gandomi and Haider 2015)

Cyber attacks through various online media during setting up of the big data platform

Very High

Extreme

Install strong firewalls, anti-virus softwares and ad blockers to prevent any kind of malwares and broken files to enter into the system

Poor management and maintenance of the system due to lack of sufficient technical expertise in big data

Very High

Medium

Conduct training sessions for all the stakeholder groups after the project is over

Stakeholder Register

The stakeholder register for the project is developed as follows.

Stakeholder Name

Stakeholder Designation

Stakeholder Category

Stakeholder Role

PLEASE FILL NAME

IS Project Manager

External

Analysis of the requirements, execution, monitoring and control of project and related human resources

George Smith

VP of Operations

Internal

Management of the operational aspects of the project including development of IoT control using the integrated Big Data platform

Sam Johnson

VP of Marketing

Internal

Management of the marketing aspects of the project including development of business analytics in the platform

Vinh Tran

Risk Manager

Internal

Assessment and management of project risks as well as managing the risk management feature of the big data platform

Jack Smith

CFO, Sponsor

Internal

Providing sufficient funds for the project

Susan Wong

CIO, Steering Company Member

Internal

Manage and employ external stakeholders for the project

Robert Beric

Business Consultant

External

Provide business suggestions and recommendations including selection of Big Data Analytics Platform

Jason Johnson

Hardware Technician

External

Upgradation of the existing hardware at the company

Magnus Olsson

Big Data Expert

External

Development of the Proposed Platform

Gary Ebbert

Trainer

External

Train stakeholder groups for using the big data platform

Stakeholder Management Strategy

In order to develop an appropriate stakeholder management strategy, an RACI matrix is developed as follows.

 

Charter Development

Budget Allocation

Risk Management

Big Data Platform Development

System Testing

Staff Training

IS Project Manager

R

A

R

A

A

I

VP of Operations

C

I

C

R

C

I

VP of Marketing

C

I

C

R

C

I

Risk Manager

C

I

R

I

I

I

CFO, Sponsor

C

R

I

I

I

I

CIO

C

I

I

I

I

I

Business Consultant

R

I

I

I

C

I

Hardware Technician

C

I

C

R

C

I

Big Data Expert

C

I

C

R

R

I

Trainer

I

I

I

I

I

R


Furthermore, as per the stakeholder management strategy, each stakeholder must follow the following guidelines.

Communication – The stakeholders must communicate with each other via appropriate medium throughout the project.

Cooperation – The stakeholders must cooperate with each other throughout the project (Kerzner and Kerzner 2017).

Performance – The stakeholders must exhibit maximum enhanced performance throughout the project.

Adherence to Policy – The stakeholders must stick to company guidelines and policies at all situations.

Conclusion

In this report, an initial project plan has been developed for the proposed implementation plan of the Big Data Analytics Package for Intelligent Information Inc. As per the estimated plan, the overall project duration is around 6 months and the estimated budget for the project is $1,500,000. As per the proposed plan, ten different internal and external stakeholders have been appointed for the project who will manage various aspects of the same.

 

References

Dhamodaran, S., Sachin, K.R. and Kumar, R., 2015. Big data implementation of natural disaster monitoring and alerting system in real time social network using hadoop technology. Indian Journal of Science and Technology, 8(22), p.1.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Gandomi, A. and Haider, M., 2015. Beyond the hype: Big data concepts, methods, and analytics. International Journal of Information Management, 35(2), pp.137-144.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Hashem, I.A.T., Yaqoob, I., Anuar, N.B., Mokhtar, S., Gani, A. and Khan, S.U., 2015. The rise of “big data” on cloud computing: Review and open research issues. Information Systems, 47, pp.98-115.

Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Marz, N. and Warren, J., 2015. Big Data: Principles and best practices of scalable realtime data systems. Manning Publications Co..

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Wamba, S.F., Akter, S., Edwards, A., Chopin, G. and Gnanzou, D., 2015. How ‘big data’can make big impact: Findings from a systematic review and a longitudinal case study. International Journal of Production Economics, 165, pp.234-246.

Wang, Y., Kung, L. and Byrd, T.A., 2018. Big data analytics: Understanding its capabilities and potential benefits for healthcare organizations. Technological Forecasting and Social Change, 126, pp.3-13.

Download Sample

Get 100% money back after download, simply upload your unique content* of similar no. of pages or more. We verify your content and once successfully verified 100% value credited to your wallet within 7 days.

Upload Unique Document

Document Under Evaluation

Get Credits into Your Wallet

*The content must not be available online or in our existing Database to qualify as unique.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2019). Project Management Systems Approach To Planning. Retrieved from https://myassignmenthelp.com/free-samples/project-management-systems-approach-to-planning.

"Project Management Systems Approach To Planning." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/project-management-systems-approach-to-planning.

My Assignment Help (2019) Project Management Systems Approach To Planning [Online]. Available from: https://myassignmenthelp.com/free-samples/project-management-systems-approach-to-planning
[Accessed 14 July 2020].

My Assignment Help. 'Project Management Systems Approach To Planning' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/project-management-systems-approach-to-planning> accessed 14 July 2020.

My Assignment Help. Project Management Systems Approach To Planning [Internet]. My Assignment Help. 2019 [cited 14 July 2020]. Available from: https://myassignmenthelp.com/free-samples/project-management-systems-approach-to-planning.


We have MLA Citation machine, APA Citation Machine, Harvard Referencing Generator, Chicago Referencing Generator etc to get proper references for all your papers. Done with drafting your papers. Generate all the references according to the format prescribed in the standard guidelines with out tools. Often papers get rejected owing to unintentional plagiarism arising from faulty referencing or simply non-referencing. Why to compromise the grades when you have drafted everything to precision? Get references and secure your grades.

Latest Management Samples

SIM335 Managing Projects Method

Download : 0 | Pages : 15
  • Course Code: SIM335
  • University: University Of Sunderland
  • Country: United Kingdom

Answer: Introduction: A project is a set of activities and methods that are carried out to achieve a specific set of goals and objectives. The following are the primary characteristics of a project. Every project has a defined list of deliverables and milestones to be achieved. A project has a series of phases that mark its life cycle. There are resources assigned to the projects for the execution of the tasks and activities. Project h...

Read More arrow

MN404 Fundamentals Of Operating Systems And Programming For Communications

Download : 0 | Pages : 4

Answer: The five most vital services of the Operating System are: Program Execution: The Operating framework gives the users a domain, for executing programs, proficiently. The user needs not to ever stress over the low-level works like Resource allocation, memory management and many more internal tasks. Communications: In the modern multi-tasking and multi-functional environment, it is vital for programs and processes to communicate among...

Read More arrow

HSH717 Health Economics For Primary Theoretical And Conceptual Framework

Download : 0 | Pages : 11

Answer: Introduction Of the primary theoretical and conceptual framework of economics, the most eminent ones are the concepts of demand and supply and also the notion of price elasticity of demand. In economics the concept of marker refers to the open platform where the buyer and the sellers of different products or services interact with one another to decide on the price and quantity of the concerned product or service. While the buyers rep...

Read More arrow Tags: Australia Melbourne Management Poster for dissertation University of Melbourne 

COIT20249 Professional Skills For Information Technology For Authentication

Download : 0 | Pages : 11
  • Course Code: COIT20249
  • University: Central Queensland University
  • Country: Australia

Answer: Introduction  Brief introduction of the case study In the provided case scenario, the author has been asked to analyze if incorporating the 3D printing technology in the business process of the company will be advantageous or not. The mentioned organization is associated with producing computers and printers for various business and is running in Victoria for over 10 years now. The company is planning to expand its services to ...

Read More arrow

BUS708 Statistics And Data Analysis For Australian Taxation Office

Download : 0 | Pages : 6

Answer: Introduction: The data set is collected from the Australian Taxation Office (ATO). The data set would help to find the gender gap of salary between men and women. The reasons of gender gap generate the discrimination of hiring in the job. The salary as well as occupation according to the different gender varies significantly. The data set summarises the analysis regarding job profile of women and men in different industries. Their sal...

Read More arrow
Next
watch

Save Time & improve Grade

Just share Requriment and get customize Solution.

question
We will use e-mail only for:

arrow Communication regarding your orders

arrow To send you invoices, and other billing info

arrow To provide you with information of offers and other benefits

1,361,360

Orders

4.9/5

Overall Rating

5,081

Experts

Our Amazing Features

delivery

On Time Delivery

Our writers make sure that all orders are submitted, prior to the deadline.

work

Plagiarism Free Work

Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.

time

24 X 7 Live Help

Feel free to contact our assignment writing services any time via phone, email or live chat.

subject

Services For All Subjects

Our writers can provide you professional writing assistance on any subject at any level.

price

Best Price Guarantee

Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.

Our Experts

Assignment writing guide
student rating student rating student rating student rating student rating 5/5

798 Order Completed

97% Response Time

Benjamin Blakeman

MSc in Medical Technology

London, United Kingdom

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

1758 Order Completed

99% Response Time

William Martinez

MS in Biology

Washington, United States

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

2632 Order Completed

100% Response Time

Albert Ambrosio

MSc in Nursing

London, United Kingdom

Hire Me
Assignment writing guide
student rating student rating student rating student rating student rating 5/5

2115 Order Completed

97% Response Time

Kimberley Chen

MPA in Accounting

Singapore, Singapore

Hire Me

FREE Tools

plagiarism

Plagiarism Checker

Get all your documents checked for plagiarism or duplicacy with us.

essay

Essay Typer

Get different kinds of essays typed in minutes with clicks.

edit

GPA Calculator

Calculate your semester grades and cumulative GPa with our GPA Calculator.

referencing

Chemical Equation Balancer

Balance any chemical equation in minutes just by entering the formula.

calculator

Word Counter & Page Calculator

Calculate the number of words and number of pages of all your academic documents.

Refer Just 5 Friends to Earn More than $2000

Check your estimated earning as per your ability

1

1

1

Your Approx Earning

Live Review

Our Mission Client Satisfaction

The work done by assignment help is fabulous it helped me alot very reliable and accurate

flag

User Id: 339691 - 14 Jul 2020

Australia

student rating student rating student rating student rating student rating

my assignment was delivered on time. There is no doubt that it was a good service.

flag

User Id: 436898 - 14 Jul 2020

Australia

student rating student rating student rating student rating student rating

The solution was on point and I have received best feedback from lecturer regarding the assessment. Because of My Assessment Help, I could able to submit the assessment on time. Thank you

flag

User Id: 194375 - 14 Jul 2020

Australia

student rating student rating student rating student rating student rating

very good service and assignment is very helpful and getting gpood gread as well.definately using again and again. best price in the market as well.

flag

User Id: 454603 - 14 Jul 2020

Australia

student rating student rating student rating student rating student rating
callback request mobile
Have any Query?