In order to get the desired level of success in the development of a project, the project planning and appropriate methodology selection is very important. The project of developing an e-procurement system for the Museums Victoria is a software system development project. This project would be completed by following the waterfall model of the software development. In other words, the traditional steps of the software development life cycle (SDLC) would be followed by the project manager for the development of the e-procure system.
In this report, the different stages of the chosen methodology have been described in details with the specific activities of the project development work in each of the selected stages. The methodology chosen for this project has been aligned with the declared milestones of the project.
The waterfall model is the first and traditional software development model, which is also known as the linear-sequential life cycle model. This is one of the simplest software development model, which is very easy to understand and use in the practical field. This type of methodology is generally used in the simple project which don’t have any uncertain steps (Schwalbe 2015). In this case, the project has some specific stages and all the milestones are clearly described in the previous report. Based on the case scenario and the milestones of the projects, the waterfall model has been selected as the appropriate method for the project work of e-procure system development (Kerzner 2013).
Figure 1: Steps of water fall model
(Source: Pathak and Saha 2013)
The pictorial representation of the chosen methodology of the project management work has been given in the above figure. All the stages of the method have been given in the figure. These steps would be followed for performing the whole project of the e-procure management system and completing the declared milestones of the project.
This is the preliminary stage of project management work. In this stages the basics details regarding the background of the project have been gathered for developing the project scope and specifications. This step has already done at the starting of the project. The background details of the project have been collected and the tender report has been produced. Through the requirement gathering and analysis phase, the project manager understood the deliverables of the project (Mohammadi et al. 2015). In more simple words, the requirements of the new e-procure management system have been understood by collecting the details existing software and the status of the procure management system of Museum Victoria. Interview with the project owners have been conducted for completing the activities of this step. After completing this step the project scope and the milestone of the project have been developed (Highsmith 2013).
Stakeholder management is another part of this step of the methodology. The stakeholder management is generally divided into two sub activities; stakeholder analysis and communication plan. Stakeholder analysis refers to the identification of all the stakeholders of the project and ensure that all the project stakeholders would be benefited from the outcome of the project. In this phase the polls of all the stakeholders have been gathered (Dubois and Tamburrelli 2013).
After the stakeholder management plan, a communication plan would be developed in this phase. This plan is for ensuring that all the stakeholders are kept involve based on their needs and interests.
Based on the information gathering of the project, the requirement and analysis phase needs to collect two types of requirements; they are functional requirements and non-functional requirements. Functional requirements are the use cases or user scenarios for interacting with the new system (Papadopoulos 2015). These use cases are described in more details in the design phase of the project management. Non-functional requirements are the software and hardware components required for the development and use of the new system to be developed in this project. In this context, the project manager should ensure that the performance characteristics of the solution need to be met (Moniruzzaman and Hossain 2013).
The necessities investigation and documentation is in a perfect world not a direct procedure, as the group ought to meet with the partners a few times amid the prerequisites stage and present to them their present comprehension of the necessities for the answer for gather input and conceivably missing necessities. Models or screen mockups are regularly helpful to guarantee that the partners and the group have a similar translation of the necessities. Frequently the partners' prerequisites advance amid the necessities exchange, as the dialog turns out to be more concrete (Papadopoulos 2015). Particularly amid the waterfall approach it is essential that the prerequisites are totally caught and conceded to before the group moves to the plan stage, as each new or changing necessity implies that the group needs to backpedal to the prerequisites stage, which may negate work that was at that point done in a before stage.
In this phase, the existing IT infrastructure of the user organizations would be checked for supporting the newly developed system. If there is anything that needs to modified or updated then the project manager needs to document it properly and take approval from the project owner (Schwalbe 2015).
After combing all the details regarding the background of the project, the detailed project schedule would be developed (Raval and Rathod 2014). In the project schedule, the starting and end date of each of the activities of the project, resource allocation and budget would be given in details.
This is the phase where the detailed design of the complete system would be developed. Each of the individual components of the system would be described in this phase. This would be done in such a level, where the developer can directly translate the designs into required codes in the next phase (Dubois and Tamburrelli 2013). The different types of activities and components of this phase are discussed in the next section.
Use case development – The high level use cases would be developed in this phase. The use cases would describe the interaction and behavior of the system with the users of the system or the others systems. Separate use cases would be developed for each of the interaction with the system (Papadopoulos 2015). In this step, the user stories would be defined, which are not actually components of classical or traditional waterfall model. In this case, the agile approach of the software development would be mixed with the waterfall approach (Schwalbe 2015).
Flowchart development –
Flowchart would be developed after the development of the use case. This would describe the flow of information and the processes of the new system. The flow charts would be built using the following basic components:
Start and end – Each of the flow charts would have a start element for indicating that the process is starting. Similarly the end element would describe the ending of the process.
Processing steps – rectangle shape boxes would be used in the flow chart for indicating the processes of the system.
Arrows – The flow direction would be shown through the arrows in the flowchart of the e-procure management system.
Decision points – The decision points would be used in the flowcharts for indicating the conditional checkpoints of the system.
Input / Output – Parallelogram shape boxes would be used in the flowcharts for indicting the read/write operations.
After the development of the use cases and flowcharts of the system, the developers would directly implement the code for the design of the system.
Since the plan is done and idealize (at any rate it should be seen as impeccable), it is converted into code. Engineers take the flowcharts, UML charts, and the other plan archives and make an interpretation of them into code, segment by part or question by protest. Every part is unit-tried all alone and a code survey ought to be finished. Normally the reconciliation is done toward the finish of the coding stage or toward the start of the test stage (Highsmith 2013). This is regularly the ideal opportunity for amazements, as things may not fit or cooperate as arranged, and the group may need to backpedal to the outline stage to roll out the fitting improvements. Contingent upon how intense the calendar was, the venture may get in a bad position comfortable point, as the arrangement was to coordinate the parts to frame a superbly working framework. Yet, now there is a deferral because of the coordination issues (Moniruzzaman and Hossain 2013). The danger of a major astonishment toward the end can be lessened by presenting distinctive turning points amid the coding stage, and soon thereafter in time the framework is coordinated and needs to give a specific level of usefulness. These breakthroughs ought to in a perfect world be trailed by an arrangement of tests to check that the usefulness works accurately.
This is the phase, where the developed system would be checked for the efficiency. The developer would first check the system for understanding whether the system is able to the meet the specification of the project. According to Dubois and Tamburrelli (2013), the goal of the testing phase is to identify the bugs of the system. In the first phase of the testing the testing team would check for the bugs by themselves. Different types of test case scenarios would be used for testing the system. After fixing the identified bugs, the system would be tested from the user ends. The various types of testing that would be performed are Integration & function verification test, Globalization verification test, System verification test, Performance verification test and Acceptance test (Mohammadi et al. 2015). In case any problem found from the user ends, then again the modification would be done at the designers end. The e-procure system for the Museum Victoria would not be completely developed until there is no more defects in the develop software system.
After the complete development of the system, i.e., testing and modifying the system, the e-procure system would be installed in the practical environment. In this case, the e-procure management system would be installed into the computer systems of the Museum Victoria. In this phase, the deployment team of the developer organization would install the system into the computers of the users (Pathak and Saha 2013). If there is any up-gradations required in the existing computer systems or IT environment of the users, then the deployment team would fix this first. The approval for this need to be taken form the owner at the initial level.
This is the after installation service, which is usually known as the support phase. This phase should start immediately after the hand over the e-procure management system. The responsibilities of the support service are handed over to a support team from the developer and tester team (Dubois and Tamburrelli 2013). Generally call centers are there for providing supports to the big projects. In this case, a support team would be available for the support services of the e-procure management system. The specialists of the support team would be developed by several professionals with deep knowledge regarding the system.
The project development would be completed within the time and budget declared at the initial phase. As the milestones of the project were declared at the beginning level of the project work, the waterfall model would be efficient enough for completion the project of the development of e-procure management system for Museum Victoria. However, some agile approaches would also be used for the project development as discussed in this report. Although the pictorial representation of the classical waterfall model indicates the step by step approach one after another, sometimes the loop would be required for the project management of the e-procure system development.
Dubois, D.J. and Tamburrelli, G., 2013, August. Understanding gamification mechanisms for software development. In Proceedings of the 2013 9th Joint Meeting on Foundations of Software Engineering (pp. 659-662). ACM.
Highsmith, J., 2013. Adaptive software development: a collaborative approach to managing complex systems. Addison-Wesley.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kumar, G. and Bhatia, P.K., 2014, February. Comparative analysis of software engineering models from traditional to modern methodologies. In Advanced Computing & Communication Technologies (ACCT), 2014 Fourth International Conference on (pp. 189-196). IEEE.
Mohammadi, N.G., Bandyszak, T., Paulus, S., Meland, P.H., Weyer, T. and Pohl, K., 2015. Extending Software Development Methodologies to Support Trustworthiness-by-Design. In CAiSE Forum (pp. 213-220).
Moniruzzaman, A.B.M. and Hossain, D.S.A., 2013. Comparative study on agile software development methodologies. arXiv preprint arXiv:1307.3356.
Papadopoulos, G., 2015. Moving from Traditional to Agile Software Development Methodologies Also on Large, Distributed Projects. Procedia-Social and Behavioral Sciences, 175, pp.455-463.
Pathak, K. and Saha, A., 2013. Review of agile software development methodologies. International Journal, 3(2).
Raval, R.R. and Rathod, H.M., 2014. Improvements in Agile Model using Hybrid Theory for Software Development in Software Engineering. International Journal of Computer Applications, 90(16).
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2018). Project Planning And Methodology. Retrieved from https://myassignmenthelp.com/free-samples/project-planning-and-methodology.
"Project Planning And Methodology." My Assignment Help, 2018, https://myassignmenthelp.com/free-samples/project-planning-and-methodology.
My Assignment Help (2018) Project Planning And Methodology [Online]. Available from: https://myassignmenthelp.com/free-samples/project-planning-and-methodology
[Accessed 20 January 2021].
My Assignment Help. 'Project Planning And Methodology' (My Assignment Help, 2018) <https://myassignmenthelp.com/free-samples/project-planning-and-methodology> accessed 20 January 2021.
My Assignment Help. Project Planning And Methodology [Internet]. My Assignment Help. 2018 [cited 20 January 2021]. Available from: https://myassignmenthelp.com/free-samples/project-planning-and-methodology.
MyAssignmenthelp.com is the perfect solution to render quality solution for all sort of academic issues. We have hired professionals from different fields of study to provide assistance with different subjects. We successfully have provided different types of assignment solutions on 100+ subjects. We have hired industry experts to deliver nursing assignment, hr assignment and finance assignment help. To offer quality content with IT assignments, we have hired IT professionals to render programming language assignment help and IT assignment help for other types of IT assignments as well.
Answer: 1. Methodology and its Role in Project Management The systematic and theoretical analysis of various methods, being applied to a typical field is termed as methodology. The methodology consists of all the theoretical analyses of the principles and methods with proper details (Heagney, 2016). These principles and methods are related to the branch of knowledge. This methodology even encompasses the several concepts like paradigms, quant...
Read MoreAnswer: 1 Measurable organizational Value (MOV) Area of Impact Rank (1 - 5) Operational 1 Customer 2 Financial 3 Social 4 Strategy 5 1.2 Desired project plan value The expected value which is associated with the project are reflected below:: Faster:...
Read MoreAnswer: Introduction The trends and technologies is growing at a very faster rate in the market of mobile phones. The evolution of telephone is going in the direction of making it compact in size. The purpose of this project is to plan a designing of the foldable mobile phones by applying the principles of NTCP diamond model. Project Overview The designing and planning of the foldable mobile phones is done on giving emphasis to the NTCP mod...
Read MoreAnswer Communications objectives: This section will highlight the main objectives of the communications that are a part of this project, which can be briefly summarized as mentioned in, the below points: This project is mainly targeting the homemakers as well as the students of hotel management as well as hospitality management, since these are the people who are more interested about food and cooking, and will generally be more interested...
Read MoreAnswer Projects Negotiation and Conflict Report The Projects Project 1: Forward strategy for payroll system The project characteristics of project 1 are mainly dependent on the perspective of Turner and Cochrane Four quadrant. The justifications for these characteristics are based on the development of application, product alignment as well as engineering. It is found that the implications that are related with the payroll syst...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
Im certain very pleased with the work done.All my requirements were very in detail meet. Thank you
Australia
You wont believe who just got 93% on the first assignment i asked you guys to do for me. Keep up the good work guys. I'm definitely going to tell my friends
Australia
The outcome was very good and satisfactory.I am planning to submit more assignments in near future.
Australia
Work delivered as requested, ahead of the deadline. Fully referenced, could not have asked for more. Thanks guys & gals!
Australia