Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

This Brief sets out what is required to be done by each team and should be read in conjunction with the instructions given through lectures and the unit of study guide.
The SBM3302 group assignment has two major deliverables:

1) Delivery of Tender Documentation
2) Presentation (Bid opening session)

In your tutorial groups, generate complete set of documentation for the request for proposal (RFP) that is allocated to your group by your lecturer.The required documents to submit for the tender do not vary for each group; but the detail of the required service or work differs on case by case basis. You need to also take into account all the constraints and deadline imposed on your project and address them accordingly.

Scope of work

The paper mainly reflects on the SBM3302 Ltd that generally invites number of eligible bidders in order to complete the “Darling Harbour Swing Bridge Replacement”. It is identified that in this project number of works are generally done including replacement of bridge superstructure, swing span and changes in the substructure as well as completion of various types of mechanical as well as electrical renovation.  Additionally the project also engages in replacing the operator house as well as fender system. It is identified that for reducing the impact of bridge construction on the public, it is ordered to complete the entire swing span of the bridge within the time period of 10 days in which the entire bridge remains closed. The project construction will be initiated on 11th September 2018 and it will be successfully completed within 5th of December 2018 by utilizing budget of around AUD 31,474,000.

 The scope of work is provided below:

  • Replacement of the entire Bridge  “Darling Harbour Swing”
  • To replace swing span, superstructure, federal system as well as operator house
  • To finish both electrical as well as mechanical overhaul
  • To finish the bridge construction project within 10 days in which the bridge remains closed for minimizing the impact of project construction on the public.

 It is identified that the project “Darling Harbour Swing Bridge” replacement will be generally completed within the timeframe of 62 days. It is identified that the construction of the project will be initiated on 11th September 2018 and it will be successfully gets completed within 5th December 2018. It is found that the replacement of swing harbour will be done within 10 days in which the entire bridge remains closed so that the people does not have to face any type of negative impact due to the construction of the bridge. It is found that the planning phase of the project will be finished within 16 days whereas the initiation phase of the project will be executed within 10 days. In addition to this, execution phase of the project will be finished within 32 days where the closure of the project gets finished within 4 days. The entire project of Darling Harbour Swing Bridge replacement will be successfully completed within 62 days by utilizing budget of around AUD 31,464,000. In addition to this, it is identified that if any type of changes is required within the project then the project manager must takes approval from the higher authority of the organization before proceeding within the changes in the project.

The project “Darling Harbour Swing Bridge replacement must be finished within 62 days. It is found that for finishing the project of bridge construction within the expected budget and time, the project manager plays an important role in dealing with the various phases project appropriately. It is found that the project manager is mainly responsible of finishing the various project stages that are mainly illustrated below:

Period of performance

Planning phase: In the planning phase of the project, the project manager is responsible of developing the project plan, project resource plan, quality management plan, risk management plan, procurement plan as well as financial plan. This phase of the project is quite useful in creating proper set of plans for controlling the team through the execution as well as closure phase of the project. The plans which are made during this phase generally assists in managing the cost, time, quality, change as well as risks and issues of the project. This is also helpful in managing both the staffs as well as external suppliers for ensuring that the entire project will be delivered on proper budget as well as time.

Initiation phase of the project:  It is found that in the initiation phase, the project manager is mainly responsible of developing the business case, undertaking feasibility analysis as well as helps in establishing project charter. It is identified that in this phase, the project team members are also appointed within the project for finishing the work of the project. It is identified that in this phase, the objectives, scope, purpose as well as deliverables of the project are properly produced for finishing the project within the expected time and budget without compromising the quality of the project.

Execution phase: It is identified that in the project execution phase, the entire work of the construction is completed. The work that are done in the execution phase of the project include replacing superstructure, swing span, operator house, federal system as well as changes within modification of substructure. Additionally, the mechanical and electrical overhaul of the entire project must be completed. It is analyzed that the replacement of the swing must be done within 10 days in which the bridge is closed so that the people does not have suffer due to the problems as well as challenges that generally occur due to the construction of the bridge. The execution phase of the project should be successfully finished within the expected budget and time without making any compromise within the quality of the project.

Closure phase: In the project closure phase, the work that are generally undertaken include post project review, stakeholder sign off as well as documentation of the project. It is identified that post project review is mainly done in order to make sure that the entire project is done properly and each of the project objectives are successfully met. After this the stakeholders of the project approves project closure by un-assigning the resources that are mainly associated with this project. After then a documentation process is done for documenting the processes as well as stages of the project successfully. Documentation is considered as legal procedure that is done for keeping record of the things that are generally done within the project.

Work requirements

The schedule for the project “Darling Harbour Swing Bridge” replacement is provided below. It is found that the bridge construction project will be finished within 62 days and the time that is essential for executing each of the project activities are generally provided in the table below:

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Completion of Darling Harbour Swing Bridge Replacement

62 days

Tue 11-09-18

Wed 05-12-18

   Project planning phase

16 days

Tue 11-09-18

Tue 02-10-18

      Development of project plan

3 days

Tue 11-09-18

Thu 13-09-18

Project manager

      Development of project resource plan

2 days

Fri 14-09-18

Mon 17-09-18

2

Project planner

      Development of project financial plan

2 days

Tue 18-09-18

Wed 19-09-18

3

Project manager

      Development of quality plan

3 days

Thu 20-09-18

Mon 24-09-18

4

Project planner

      Development of risk management plan

2 days

Tue 25-09-18

Wed 26-09-18

5

Project manager, Sub-contractor

      Development of communication plan

2 days

Thu 27-09-18

Fri 28-09-18

6

Project manager, Architect

      Development of procurement plan

2 days

Mon 01-10-18

Tue 02-10-18

7

Project planner

      Milestone 1:Completion of project planning phase

0 days

Tue 02-10-18

Tue 02-10-18

8

   Project initiation phase

10 days

Wed 03-10-18

Tue 16-10-18

      Development of business case

2 days

Wed 03-10-18

Thu 04-10-18

9

Architect, Contractor

      Undertaking feasibility study

3 days

Fri 05-10-18

Tue 09-10-18

11

Project planner

      Establishing charter of the project

3 days

Wed 10-10-18

Fri 12-10-18

12

Project manager

      Appointing team members of the project

2 days

Mon 15-10-18

Tue 16-10-18

13

Project planner

      Milestone 2: Completion of initiation phase of the project

0 days

Tue 16-10-18

Tue 16-10-18

14

   Project execution phase

32 days

Wed 17-10-18

Thu 29-11-18

      Superstructure replacement

4 days

Wed 17-10-18

Mon 22-10-18

15

Architect, Sub-contractor

      Swing span replacement

6 days

Tue 23-10-18

Tue 30-10-18

17

Architect, Contractor

      Modifying substructure

3 days

Wed 31-10-18

Fri 02-11-18

18

Contractor, Supervisor, Material cost[1]

      Completion of mechanical overhaul

4 days

Mon 05-11-18

Thu 08-11-18

19

Contractor, Sub-contractor, Supervisor

      Completion of electrical overhaul

4 days

Fri 09-11-18

Wed 14-11-18

20

Architect, Contractor, Supervisor, Equipment cost[1]

      Operator house replacement

5 days

Thu 15-11-18

Wed 21-11-18

21

Contractor, Sub-contractor, Additional cost[1]

      Replacement of fender system

6 days

Thu 22-11-18

Thu 29-11-18

22

Architect, Contractor

      Milestone 3:Completion of project execution phase

0 days

Thu 29-11-18

Thu 29-11-18

23

   Project closure phase

4 days

Fri 30-11-18

Wed 05-12-18

      Post project review

2 days

Fri 30-11-18

Mon 03-12-18

24

Supervisor

       Stakeholder sign off

1 day

Tue 04-12-18

Tue 04-12-18

26

Project planner

      Documentation

1 day

Wed 05-12-18

Wed 05-12-18

27

Project manager

      Milestone 4:Completion of project closure phase

0 days

Wed 05-12-18

Wed 05-12-18

28

 

 The project acceptance criteria are provided below:

  • Darling harbour Swing bridge replacement
  • Superstructure replacement
  • Swing span replacement
  • Substructure modification
  • Mechanical overhaul completion
  • Electrical overhaul completion
  • Operator house replacement

  The work breakdown structure that is provided below is for the project “Darling harbour Swing bridge replacement. It is identified that work breakdown structure is one of the deliverable of the project that generally organizes the entire work of the team into number of manageable sections. It is identified that the project management body of knowledge generally defines WBS as one of the deliverable oriented hierarchical decomposition of the entire work for executing it with the help of various team members of the project. It generally defines the entire scope into number of manageable chunks so that the project team can easily understand about the various phases of the project and can be able to complete them successfully within the expected time and budget.

The milestone of the entire schedule of the project is mainly provided in the below table:-

Milestone

Date of completion

      Milestone 1:Completion of project planning phase

Tue 02-10-18

      Milestone 2: Completion of initiation phase of the project

Tue 16-10-18

      Milestone 3:Completion of project execution phase

Thu 29-11-18

      Milestone 4:Completion of project closure phase

Wed 05-12-18

The project “Darling harbour Swing” bridge replacement must be finished within the budget of AUD 31,474,000. It is identified that the cost that is needed for executing each of the activities as well as phases of the project “Darling Harbour Swing Bridge replacement” is generally provided in the table below:

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

Completion of Darling Harbour Swing Bridge Replacement

62 days

Tue 11-09-18

Wed 05-12-18

AUD 31,474,000.00

   Project planning phase

16 days

Tue 11-09-18

Tue 02-10-18

AUD 21,920.00

      Development of project plan

3 days

Tue 11-09-18

Thu 13-09-18

Project manager

AUD 3,600.00

      Development of project resource plan

2 days

Fri 14-09-18

Mon 17-09-18

2

Project planner

AUD 2,080.00

      Development of project financial plan

2 days

Tue 18-09-18

Wed 19-09-18

3

Project manager

AUD 2,400.00

      Development of quality plan

3 days

Thu 20-09-18

Mon 24-09-18

4

Project planner

AUD 3,120.00

      Development of risk management plan

2 days

Tue 25-09-18

Wed 26-09-18

5

Project manager, Sub-contractor

AUD 4,320.00

      Development of communication plan

2 days

Thu 27-09-18

Fri 28-09-18

6

Project manager, Architect

AUD 4,320.00

      Development of procurement plan

2 days

Mon 01-10-18

Tue 02-10-18

7

Project planner

AUD 2,080.00

      Milestone 1:Completion of project planning phase

0 days

Tue 02-10-18

Tue 02-10-18

8

AUD 0.00

   Project initiation phase

10 days

Wed 03-10-18

Tue 16-10-18

AUD 12,320.00

      Development of business case

2 days

Wed 03-10-18

Thu 04-10-18

9

Architect ,Contractor

AUD 3,520.00

      Undertaking feasibility study

3 days

Fri 05-10-18

Tue 09-10-18

11

Project planner

AUD 3,120.00

      Establishing charter of the project

3 days

Wed 10-10-18

Fri 12-10-18

12

Project manager

AUD 3,600.00

      Appointing team members of the project

2 days

Mon 15-10-18

Tue 16-10-18

13

Project planner

AUD 2,080.00

      Milestone 2: Completion of initiation phase of the project

0 days

Tue 16-10-18

Tue 16-10-18

14

AUD 0.00

   Project execution phase

32 days

Wed 17-10-18

Thu 29-11-18

AUD 31,435,600.00

      Superstructure replacement

4 days

Wed 17-10-18

Mon 22-10-18

15

Architect, Sub-contractor

AUD 7,680.00

      Swing span replacement

6 days

Tue 23-10-18

Tue 30-10-18

17

Architect, Contractor

AUD 10,560.00

      Modifying substructure

3 days

Wed 31-10-18

Fri 02-11-18

18

Contractor, Supervisor, Material cost[1]

AUD 11,376,240.00

      Completion of mechanical overhaul

4 days

Mon 05-11-18

Thu 08-11-18

19

Contractor, Sub-contractor, Supervisor

AUD 10,880.00

      Completion of electrical overhaul

4 days

Fri 09-11-18

Wed 14-11-18

20

Architect, Contractor, Supervisor, Equipment cost[1]

AUD 10,010,880.00

      Operator house replacement

5 days

Thu 15-11-18

Wed 21-11-18

21

Contractor, Sub-contractor, Additional cost[1]

AUD 10,008,800.00

      Replacement of fender system

6 days

Thu 22-11-18

Thu 29-11-18

22

Architect, Contractor

AUD 10,560.00

      Milestone 3:Completion of project execution phase

0 days

Thu 29-11-18

Thu 29-11-18

23

AUD 0.00

   Project closure phase

4 days

Fri 30-11-18

Wed 05-12-18

AUD 4,160.00

      Post project review

2 days

Fri 30-11-18

Mon 03-12-18

24

Supervisor

AUD 1,920.00

       Stakeholder sign off

1 day

Tue 04-12-18

Tue 04-12-18

26

Project planner

AUD 1,040.00

      Documentation

1 day

Wed 05-12-18

Wed 05-12-18

27

Project manager

AUD 1,200.00

      Milestone 4:Completion of project closure phase

0 days

Wed 05-12-18

Wed 05-12-18

28

AUD 0.00

Project Process

Process quality standard/ Stakeholders expectation

Quality Assurance activity

 Frequency

Responsible

 Development of project risk plan

The risks that are associated with the project must be properly specified. It is identified that the risks that are related with the project must be successfully analyzed by the risk manager so that they can get to know about the risks that is affecting the project negatively.

 Peer review of the various types of risks that are mainly related with the project “Darling Harbour Swing Bridge replacement”.

 The peer review of the project risks must be done on the regular interval so that the project managers does not face any type of risks as well as challenges that are related with the project

 The responsible person is the risk analyst.

 Replacement of superstructure

 Proper specification of the requirement is mainly provided in order to replace the superstructure. It is identified that the resources as well as materials that are mainly needed in order to replace the superstructure must be properly estimated.

 It is very much essential to review the materials as well as equipment’s that are needed for replacing the superstructure.

 The requirements that are needed for the replacement of superstructure must be reviewed on a regular interval for replacing the superstructure successfully without facing any type of problem or issues.

 It is identified that contractor is the responsible person.

 Proper training to the team members

 Providing proper training facility to the team members of the project.

 It is very much essential to provide proper training facility to the team members of the project so that they can be able to finish the project successfully within the expected budget and time without facing any type of problem as well as issues.

 The training facility needs to review from type to type in order to ensure that the proper facility of training is provided to the team members of the project.

 The trainer is the person who is mainly responsible for providing proper facility of training to the team members of the project.

Creating resource plan

 It is necessary to ensure that the materials that are mainly utilized within the project is of good quality.

 It is very much essential; to review the quality of the materials that are mainly needed in order to replace the Darling Harbour Swing Bridge successfully without facing any type of quality related issues as well as challenges.

 The materials of the project needs to be checked before utilizing them within the project.

 It is identified that quality analyst is the very much responsible person who mainly engages in maintaining the quality of the material.

 Appointment of team members

 It is necessary to hire experienced team members within the project.

 The knowledge as well as experience of the project managers must be tested properly before recruiting them within the project.

 It is necessary to review the performance of the project team member on regular interval in order to make sure that they are performing properly within the project.

 Human resource manager is the most responsible person in the project.

Contract type

It is found that this project mainly follows management contracting method for executing the entire project successfully. It is found that in this type of contract, the project contractors are generally paid amount so that they can execute all the activities of the project successfully within the expected budget and time. This, it is found that in this type of contract that some of the project work are completed by the project contractor before entering into the design phase of the project. There are numerous advantages of this type of contract and the advantages of the contract mainly include shorter time requirement for construction, getting appropriate advice during the design phase. Additionally it is found that in this type of contract, the entire budget that is needed can be estimated however the budget cannot be accurately identified until the entire work o9f the project is completed successfully.

Delivery mode

The deliver mode that is used in the project “Darling Harbour Swing Bridge” replacement is design build delivery model. This delivery mode is considered most suitable for this project. This is because in this type of delivery mode both the contractor as well as designers are generally hired in order to finish the entire project work successfully within the expected budget and time. It is found that this mode of delivery is used as it mainly helps in minimizing the entire time for the delivery of the project schedule. The idea of design build generally helps in brining improved communication among the team members as well as with the higher level authority. However as this is considered as complex technique for delivery as the packed timetable and entire esteem methodology of designing generally results in investment of funds for the project owner. The DB approach is considered to be suitable for less confounded undertaking where the owner of the project has proper reasonable task idea as well as definition before requesting offers and generally needs firm costs that is affirmed ahead of schedule all the time.

Schedule

Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Costantino, F., Di Gravio, G., & Nonino, F. (2015). Project selection in project portfolio management: An artificial neural network model based on critical success factors. International Journal of Project Management, 33(8), 1744-1754.

Daniel, P. A., & Daniel, C. (2018). Complexity, uncertainty and mental models: From a paradigm of regulation to a paradigm of emergence in project management. International Journal of Project Management, 36(1), 184-197.

Eskerod, P., Huemann, M., & Savage, G. (2015). Project stakeholder management—past and present. Project Management Journal, 46(6), 6-14.

Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International journal of project management, 32(2), 327-340.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), 169-179.

Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66.

Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.

Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.

Teller, J., Kock, A., & Gemünden, H. G. (2014). Risk management in project portfolios is more than managing project risks: A contingency perspective on risk management. Project Management Journal, 45(4), 67-80.

Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). SBM3302 Group Assignment: Deliverables, Scope, Work Requirements, And Schedule. Retrieved from https://myassignmenthelp.com/free-samples/sbm3302-completion-of-darling-harbour-swing-bridge-replacement.

"SBM3302 Group Assignment: Deliverables, Scope, Work Requirements, And Schedule." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/sbm3302-completion-of-darling-harbour-swing-bridge-replacement.

My Assignment Help (2020) SBM3302 Group Assignment: Deliverables, Scope, Work Requirements, And Schedule [Online]. Available from: https://myassignmenthelp.com/free-samples/sbm3302-completion-of-darling-harbour-swing-bridge-replacement
[Accessed 25 April 2024].

My Assignment Help. 'SBM3302 Group Assignment: Deliverables, Scope, Work Requirements, And Schedule' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/sbm3302-completion-of-darling-harbour-swing-bridge-replacement> accessed 25 April 2024.

My Assignment Help. SBM3302 Group Assignment: Deliverables, Scope, Work Requirements, And Schedule [Internet]. My Assignment Help. 2020 [cited 25 April 2024]. Available from: https://myassignmenthelp.com/free-samples/sbm3302-completion-of-darling-harbour-swing-bridge-replacement.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close