This assessment allows student to apply theoretical concepts to practice by analysing case studies and proposing a suitable design. The portfolio assessment covers the following topics: information system development, system development approaches, data Modeling, IS project management, system requirements, user and system interfaces, and system testing, deployment and maintenance.
Basic Instructions:
You are creating a customer database for the Max league baseball team. The project starts with system design, this followed by the design phase which includes subsystem A design, then subsystem B design, and subsystem C design (5 days). The next step is then programming, which includes program A, program B and program . The last step is testing . Considering those tasks, their duration and predecessors,
A- Prepare a work breakdown structure showing tasks, durations and predecessor tasks
An IS project manager for a software developing was given the following information to start developing for his project. It starts with research, understanding system requirements , install required applications , writing algorithms and coding, debugging and testing and finally deploying and maintained.
Considering those tasks, their duration and predecessors,
This portfolio is about a NSW car rental company that mainly deals with renting of their vehicles to their customers where they book through the company’s staffs, however the company has a database that records the details of the vehicles ,customers and the staffs in the varies database tables as illustrated in the below entities, attributes and entity relational diagram.
Below are the various NSW car rental company database entities and the respective attributes.
Entity |
Attributes |
Data types |
Size |
Constraints |
Staffs |
Staff_ number First_name last _name street_number street_name suburb post-code city state gender date_of_birth office_number office_phone_number |
Int Varchar Varchar Int Varchar Varchar Varchar Varchar Varchar Varchar Date Int Int |
20 20 20 20 20 20 20 20 20 20 20 20 20 |
Primary key |
Customers |
Customer_number First_name Last_name Street_Number Street_Name Suburb Post-Code City State Gender Date_Of_Birth Telephone_Number License_Number |
Int Varchar Varchar Int Varchar Varchar Varchar Varchar Varchar Varchar Varchar Int Int |
20 20 20 20 20 20 20 20 20 20 20 20 20 |
Primary key |
Vehicle |
Car_Registration_no Make Model Colour_of_vehicle Rental_price_per_day |
Int Varchar Varchar Varchar Int |
20 20 20 20 20 |
Primary key |
Bookedcars |
Bookingno Car_Registration_no Customer_number Date_borrowed Return_date Total_cost Staff_number Terms_and_condition |
Int
Int Date Date Int Int varchar |
20 20 20 20 20 20 20 20 |
Primary key Foreign key Foreign key
Foreign key |
(Singh, 2016)
In this portfolio a project that involves creating of the customer database for the max league base ball team is to be implemented through the various steps of system development life cycle and they will involve various activities where each and every activity is covered within a specific set of time frame in order to ensure that the system had been completed within the set time limit.
Below are the work breakdown structures, the start and finish dates for the project implementation (Wixom, 2016).
Task Name |
Duration |
Predecessor |
System design |
5 days |
- |
subsystem A design |
5 days |
System design |
subsystem B design |
4 days |
subsystem A design |
subsystem C design |
5 days |
subsystem B design |
Program A |
9 days |
subsystem C design |
Program B |
5 days |
Program A |
Program C |
8 days |
Program B |
Testing |
4 days |
Program C |
TASK |
Start date |
Finish date |
System design |
3/9/2018 |
7/9/2018 |
subsystem A design |
8/9/2018 |
12/9/2018 |
subsystem B design |
13/9/2018 |
16/9/2018 |
subsystem C design |
17/9/2018 |
21/9/2018 |
Program A |
22/9/2018 |
30/9/2018 |
Program B |
1/10/2018 |
5/10/2018 |
Program C |
6/10/2018 |
13/10/2018 |
Testing |
14/10/2018 |
18/10/2018 |
In this portfolio a project that involves creating of the IS software system project that is to be managed by the project manager and it will be implemented through the various steps of system development life cycle and they will involve various activities where each and every activity is covered within a specific set of time frame in order to ensure that the system had been completed within the set time limit.
Below are the work breakdown structures, the start and finish dates for the project implementation.
It starts with research (15 days), understanding system requirements (14 days), install required applications (7 days), writing algorithms and coding (20 days), debugging and testing (8 days) and finally deploying and maintained (5 days)
Task Name |
Duration |
Predecessor |
Research |
15 days |
- |
understanding system requirements |
14 days |
Research |
Installing required applications |
7 days |
understanding system requirements |
writing algorithms and coding |
20 days |
Installing required applications |
Debugging and testing |
8 days |
writing algorithms and coding |
Deploying and maintenance |
5 days |
Debugging and testing |
TASK |
Start date |
Finish date |
Research |
3/9/2018 |
17/9/2018 |
understanding system requirements |
18/9/2018 |
1/10/2018 |
Installing required applications |
2/10/2018 |
8/10/2018 |
writing algorithms and coding |
9/10/2018 |
28/10/2018 |
Debugging and testing |
29/10/2018 |
4/11/2018 |
Deploying and maintenance |
5/11/2018 |
9/11/2018 |
This portfolio covers the car rental system design which is a new system to be used by the carhire which is a car rental company in Australia since 2010.
In this the various services will be implemented in the company which includes the database management systems and networking server, installation of network infrastructure and also development of the mobile system which will all be implemented in the carhire project.
Below are the various processes to be used in the system implementation which are illustrated in the system development life cycle.
This stage is where the company current system is analyzed to identify the problem in it and justify need for the new system where the car rental system will be selected as the possible solution this stage is will take a period of 3 days.
This is the second stage after identifying the problem where the project manager is involved to outline the various possible activities, how they can be done and organizing the experts to do those tasks, in this case the time required will be 4 days.
In this stage the system analysts will be involved and they will be able to gather the requirements to implement the database system, network infrastructure and mobile application and this will take a total of 7 days.
This is the stage that will be done after the gathering of system requirements and it will be carried out by the system designers where the various project segments will be designed to make a foot print for the system building and this stage will cover a total of 5 days( Gupta, 2015).
This is the fifth stage which will be carried out after the designing of the system components where the system developers, network designers and app developers are involved to build, test and then integrate the project components where it will be completed within 4 days.
This is the final stage of the system development where the entire system is deployed and then it is tested further to test some problems which are repaired as part of system maintenance and this stage takes a total of 15 days.
Task Name |
Duration |
Predecessor |
Identifying the problem. |
3 days |
- |
Planning and monitoring the project. |
4 days |
Identifying the problem. |
Gathering the system requirements. |
7 days |
Planning and monitoring the project. |
Designing the system’s components. |
5 days |
Gathering the system requirements. |
Building, testing, and integrating system’s components. |
4 days |
System deployment and maintenance. |
System deployment and maintenance. |
15 days |
Building, testing, and integrating system’s components. |
Below are some of the assumptions made in the car rentals system.
The Sydney dentist centre currently uses the old system of storing information in the Microsoft office access database and they currently aims at improving their record storage by migrating their records to new database system of Microsoft SQL server database management system (Longworth,2012).
Below are the plans that will be used to test the migration tool before it is fully deployed and testing the success of the database migration.
To successfully deploy the system database without any error below are the major test plan steps to be used.
The database will be tested for its integrity before the migration process and this will cover the following:
The SQL server databases system has different type of security systems with the Microsoft office access database and thus different ways of authentication are used in login in the database systems where passwords will be required to manage the database, moreover there will be requirements of windows authentications or use of database authentication .Therefore the security tests will be done to ensure that the access database had mapped the SQL server database users ,roles and objects accordingly (Downs, 2011).
In the data migration the database index and the constraints tend to affect the performance in the process of migration of data, however during the migration process if the triggers are fired will end up corrupting the data and end up in production of undesirable results. Therefore before the migration is done the stored data will require to be checked and ensure that it is correct and complete during the migration and also it will be validated after it is migrated (Jain, 2010).
Identifying whether the tests is passedAfter the migration of the database from the Microsoft access to Microsoft SQL server the new database is to be tested in whole where the various aspects will be covered including the database architectures, objects, data, and user, connectivity, security and performance tests and this will be achieved using the process to validate the migration below.
The following validations will be done to test whether the test plan is passed.
The test plan will be “passed” if all the above validations are successful else there was an error in the database migration process (Laplante, 2013).
Laplante,P.(2013).Real-Time Systems Design and Analysis: Tools for the Practitioner. New Jersey:Wiley.
Jain,S.(2010). A Level Made Simple Structured System Analysis and Design. New Delhi:Bpb Publications.
Downs, E.(2011). Structured Systems Analysis and Design Method: Applications and Context. New Jersey: Prentice-Hall.
Longworth, G.(2012). Introducing Structured Systems Analysis and Design Method. New Jersey: Blackwell Publishers.
Goyal, A. (2011). systems Analysis and Design Paperback.INDIA:Prentice Hall India Learning Private Limited.
Gupta,B.(2015). Power System Analysis and Design.New Delhi: S Chand & Company.
Singh,B.(2016). Systems Analysis and Design.Delhi:New Age International Private Limited.
Wixom,D.(2016). Systems Analysis and Design.New Jersey:Wiley publishers.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2021). SBM4201 System Analysis And Design. Retrieved from https://myassignmenthelp.com/free-samples/sbm4201-systems-analysis-and-design/introducing-structured-systems-analysis.html.
"SBM4201 System Analysis And Design." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/sbm4201-systems-analysis-and-design/introducing-structured-systems-analysis.html.
My Assignment Help (2021) SBM4201 System Analysis And Design [Online]. Available from: https://myassignmenthelp.com/free-samples/sbm4201-systems-analysis-and-design/introducing-structured-systems-analysis.html
[Accessed 26 February 2021].
My Assignment Help. 'SBM4201 System Analysis And Design' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/sbm4201-systems-analysis-and-design/introducing-structured-systems-analysis.html> accessed 26 February 2021.
My Assignment Help. SBM4201 System Analysis And Design [Internet]. My Assignment Help. 2021 [cited 26 February 2021]. Available from: https://myassignmenthelp.com/free-samples/sbm4201-systems-analysis-and-design/introducing-structured-systems-analysis.html.
Get affordable papers now from MyAssignmenthelp.com. Here, you need to pay only a nominal amount for the essay. Even though the prices are low, we do not compromise on the quality part. Our experts run thorough plagiarism check on the papers before delivering it to you. Pay for your essay using safe and secure payment gateways like PayPal, credit/debit card or net banking. You can also use our essay typer tool for free of cost. It generates quality essays on your chosen topic in an instant. However, the paid service offers customisation of the essay as per your requirements.
Answer: Introduction Ingogo company is a firm under the industry of Taxi booking and logistics based in Australia. It majors in online bookings and payments of taxis. This company was the first in the country to offer transportation services, it provide their clients a fixed fares that includes price commissions. Taxi drivers process prices using the company’s customised android application software. The company currently offer services...
Read MoreAnswer: Introduction This report is focused on a case study of “International Charity Foundation” (ICF) which provides assistance through funding to the young people so that they can realise their potential. The organization offers medical as well as educational assistance to the children in different countries. Presently, the business process is carried out manually and paper based therefore it consumes more time along with incre...
Read MoreAnswer: 1.Validation of the statement The construction program is equipped with changes and improvement plan so that the quality product can be developed at the end of the construction program. The performance of the project depends on the variation in the designing and process used for developing the building and other architectural plan (Azim, 2010). The variations are the change in the order plan to manage the changing request and demand o...
Read MoreAnswer: Introduction Motivation can be considered to be a major reason behind the actions of people, their needs and desires. The direction of a person towards a certain behaviour can be selected with the help of motivation. The internal and the external factors which are able to stimulate high levels of energy and desire within people so that they are interested in a job or a certain job role on a continuous basis are considered to be a part...
Read MoreAnswer: Virtual Reality Onboarding The virtual reality onboarding refers to the matters wherein the concerned potential employees are hired within the given organisation. The onboarding of the employees refer to the hiring of the various employees. Use of virtual reality onboarding by restaurants The restaurants generally use the various technologies that are related to the onboarding of the concerned employees thro...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
I am very satisfied with the service. I would recommend for my friends to try it out.
Australia
The assignment of my knowledge has been done and submitted to the school and it was great
Australia
I got a great score on my assignment. thank you guys, been using your service for quite some time now and never have regretted my decision.
Australia
I had a great expert to help me! They helped me get a good grade instead of getting a F.
Australia