Topic: Construction and materials technology
Learning Outcomes:
There should be a title page identifying the program name, module title, assessment title, your name and student number, your tutor’s name and the date of submission.
Electronic submission only. The assignment should be in a pdf format (scan all pages of assignment including the A3 papers with drawings) and uploaded into Turnitin via the Moodle class area. If you experience problems in uploading your work, then you must send an electronic copy of your assessment to your Module Tutor via email before the due date/time.
Please note that when you submit your work to Moodle, it will automatically be checked for matches against other electronic information. The individual percentage text matches may be used as evidence in an academic misconduct investigation (see Section 13 in the Module Guide).
Requests for extensions which take a submission date past the end of the module (normally week 15) must be made using the Mitigating Circumstances procedures.
Some students with registered disabilities will be eligible for revised submission deadlines. Revised submission deadlines do not require the completion extension request paperwork.
Please note that the failure of data storage systems is not considered to be a valid reason for an extension. It is therefore important that you keep multiple copies of your work on different storage devices before submitting it.
Earthworks Management – Brief
Chainage |
Ground Level |
Chainage |
Ground Level |
3000 |
70 |
3770 |
62 |
3070 |
69.5 |
3840 |
63.1 |
3140 |
69.4 |
3910 |
61.5 |
3210 |
69 |
3980 |
59.7 |
3280 |
68.1 |
4050 |
59 |
3350 |
68.3 |
4120 |
58 |
3420 |
68.7 |
4190 |
59 |
3490 |
69 |
4260 |
61.9 |
3560 |
67.1 |
4330 |
76.5 |
3630 |
61.4 |
4400 |
77 |
3700 |
62.7 |
Chainage (m)
Existing Ground Level (mAOD)
Proposed Motorway Level (mAOD to 2 decimal places) Depth of Fill (-) / Height of Cut (+) (m to 2 decimal places) Cross-section Area (m2 to 2 decimal places) Volume (cut + / fill -) between each chainage interval (to nearest m3) Cumulative Volume (to nearest m3)
Provide an example of manual calculations using sketches for at least three chainages for the aboveThe tables must reflect the earthworks management for the whole of the proposed works.
d) Produce the MHD above (to the same scales). Using the rates provided below, evaluate the true cost of the earthworks operation when considering both Freehaul and Overhaul aspects of earthworks. (include all Formulae).Freehaul Distance 550m
Freehaul Rate £2.2 per m3
Overhaul Rate 90p per station metre
Importing Rate £1.85 per m3
Tipping Rate £2.65 per m3
At tender stage the Estimator allowed a lump sum figure of £580,000 (from experience and rough calculations). Comment on the suitability (or otherwise), of the Estimator’s approximation and discuss sustainable earthwork management.