Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

Develop a set of relevant and achievable goals appropriate for the project described in the Case Study. Explain how your goals will be measured as the project progresses. 

Write a brief scope statement for the Case Study project. Describe the processes and or methods you used to determine the scope of the project. You should identify all stakeholders and the relative weighting (importance) of each in determining the scope along with other relevant factors identified in readings and other resources. Key deliverables (What is the product or service the project is to deliver?) and acceptance criteria (How will we know we have produced the intended product or service?) should be included. 

Finally, provide an overview of the Case Study project’s overall process, life cycle or methodology. This should describe the life cycle stages, methods and processes that will be used to monitor and control the project successfully through to completion and a discussion of how 'success' will be measured. 

Project Goals and Objectives

The main goals of the multinational oil company are to repair the oil tanks for improving the conditions of tanks of Western Australian site and for reducing the amount of money that is mainly spent by the organization on the environmental fines. In addition to this, it is found that by improving the condition of the fuel tanks assists in enhancing the availability of the tanks in the area if Western Australian site.

 The factors that assists in measuring the project goals are elaborated below:

 Availability: If the tank of the Western Australian site is easily available then it can be reflected that all the tanks have been repaired and the project goals are successfully achieved.

 Tank repair completion: If the project of Australian site gets completed within the time that is expected then it can be assumed that the project goals are achieved.

Environmental fines reduction: If the money that is paid on environmental fines reduces, then it will be reflected that the goals of the project is achieved.

  Budget: The repair of the tank gets accomplished within the budget that is provided then it can be analyzed that the goals of the project are effectively achieved.

 The project scope statement is mainly categorized into in scope and out scope.

In-scope: Project in-scope includes:

  • Western Australian site tank repair
  • Environmental fines reduction
  • Increasing availability of the tanks
  • Project completion within the assumed time and approved budget

Out-scope: Out scope of the project includes:

  • Proper details about the project suppliers
  • Information about all the materials that are needed are not elaborated

 The processes as well as methods that are helpful in identifying the scope are elaborated below:

 Focusing on project objectives and aim: If the aim and objectives are determined then it is quite easily to develop the project scope for progressing with the work of the project (Joslin & Muller, 2015).

Analyzing needs of the project: The project manager analyzes the requirements and needs of the project then it will be found as one of the significant step for developing the project scope.

Analyzing project budget and availability of time:  If appropriate analysis about project time and project budget is made then it will be quite easy to determine the project scope (Hornstein, 2015).

Reflecting on constraints and assumptions: It is found that information related with constraints and assumptions of the project are found to be very much essential for determining project scope.

 The stakeholders who are involved with the project are listed below:

Stakeholder

Responsibilities

Power

Interest

Project manager

  The project manager takes the responsibility of executing, managing as well as initiating the entire project of repairing the fuel tanks WA site.

High

High

Project planner

 The project planner takes the responsibility of creating proper plan for executing the entire project on time.

Medium

High

Supervisor

The supervisor takes the responsibility of supervising the project activities in order to repair the tan of the project.

High

Medium

Contractor

 The contractor takes the responsibility of contract for finishing the repair of the tank within the expected budget and time.

Medium

High

Construction manager

 The construction manager takes the responsibility of managing as well as executing each of the activities of the project so that the tank of Western Australian tank can be properly repaired.

High

Medium

Finance manager

The project financial manager is mainly responsible of creating and managing the financial plan of the project for finishing the entire project.

Medium

Medium

The key project deliverables are listed below:

  • Repair tank 1 which generally have the capacity of 1 million liters of unleaded petrol
  • Repair tank 2 which generally have the capacity of 3 million liters of unleaded petrol
  • Repair the tank 3 that which have capacity of 7 liters of unleaded petrol
  • Resolving the problems and challenges that are associated with the Western Australian site

Project acceptance criteria includes the following:

  • Repair of the tanks must be completed within expected time
  • The project is beneficial in resolving challenges and issues
  • The project will reduce the environmental fines

 It is found that tank repairing project generally undergoes through seven phases of the project. The phases of the project mainly include identification, project preparation, project appraisal, implementation, project monitoring as well as evaluation.

Measuring Project Success

 It is analyzed that the project of Australian site is mainly repaired by utilizing the Agile methodology (Svejvig & Andersen, 2015). It is found that this methodology is mainly used as by using this methodology, the project managers needs to undertake testing as well as quality analysis after completing each of the phase of the project. Additionally, it is found that with the help of this methodology, proper customer service, enhanced project control as well as project related risks can be properly minimized.

The steps or procedures that are generally used for controlling the project are elaborated below:

Controlling project schedule: It is quite essential to use earned value analysis for controlling the budget as well as schedule of the project (Hornstein, 2015). It is found that appropriate management of schedule helps in monitoring the entire project successfully.

Performing quality control: It is necessary to deliver proper quality of the project and for this it is quite essential to perform proper quality control related steps. IN addition to this, it is quite essential to check the project quality for ensuring that the steps that are undertaken assists in delivering proper quality based project.

Controlling project risks: The risks that are present within the project must be determined in each phase of the project so that the risks can be resolved for making sure that the project that was undertaken does not get affected due to the risks (Too & Weaver, 2014).

Report performance: It is found that for monitoring the progress of the project, it is quite essential to make documentation of the project performance. It is found that maintenance of report performance as well as project status report assists in monitoring and controlling the project.

The project success can be analyzed with the help of the steps that are elaborated below:

Reduction in environmental fines: If the environmental fines reduces then it can be analyzed that the project which was undertaken is successful (Chih & Zwikael, 2015).

Timely completion of project: If the project gets completed within the time and budget that is approved by the higher authority of the organization then the project is considered to e successful.

Proper repair of the tank: If the tanks of WA site are properly repaired then it can be analyzed that the project which was undertaken are successful (Conforto et al., 2014).

Enhanced availability of tank: If the number of tanks that are available in Western Australian Site increases then it can be analyzed that the tanks are repaired properly and thus the project can be considered to be successful.

Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.

Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management, 33(2), 352-362.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), 126-139.

Riol, H., & Thuillier, D. (2015). Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), 251-269.

Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.

Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2021). Managing An Essay On Repairing Fuel Tanks In Western Australia For A Multinational Oil Company.. Retrieved from https://myassignmenthelp.com/free-samples/bg007-project-management/explanation-about-measuring-project-goals.html.

"Managing An Essay On Repairing Fuel Tanks In Western Australia For A Multinational Oil Company.." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/bg007-project-management/explanation-about-measuring-project-goals.html.

My Assignment Help (2021) Managing An Essay On Repairing Fuel Tanks In Western Australia For A Multinational Oil Company. [Online]. Available from: https://myassignmenthelp.com/free-samples/bg007-project-management/explanation-about-measuring-project-goals.html
[Accessed 19 April 2024].

My Assignment Help. 'Managing An Essay On Repairing Fuel Tanks In Western Australia For A Multinational Oil Company.' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/bg007-project-management/explanation-about-measuring-project-goals.html> accessed 19 April 2024.

My Assignment Help. Managing An Essay On Repairing Fuel Tanks In Western Australia For A Multinational Oil Company. [Internet]. My Assignment Help. 2021 [cited 19 April 2024]. Available from: https://myassignmenthelp.com/free-samples/bg007-project-management/explanation-about-measuring-project-goals.html.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close