Task 1: WBS (level 2/3) – Word doc or MS Project
You need to create level 3-4 WBS. It should have a minimum of Use the indented format and level 1 as 4 phases of project life cycle.
Task 2: Gantt chart – Firstly you need to do Activity Estimation i.e. estimate the duration of each activity and Secondly dependencies between eh activities need to be determined before you can create a schedule and MS Project builds the Gann chart. You also need to allocate resources to each activity ( 1 resource per activity) from the table given below (PS: You do not need to use all the resources listed below, you may use the ones you need to complete your project) Gantt chart should include all the resources allocated in this project. You should attach the MS project screen shots to prove your workings.
The Resource table to be used for allocating resources is as below
$ per Hour |
|
Project Manager |
80 |
Systems Analysis |
60 |
Graphic Designer |
50 |
Application Programmer |
50 |
Web System Expert |
70 |
Program Team member_1 |
50 |
Program Team Member_2 |
50 |
Quality Assurance Tester |
60 |
Database Administrator |
50 |
Team Member_1 |
35 |
Team Member_2 |
35 |
Working Days |
5 days per week ( No Over time required) |
Working Hours |
8 hours per day ( 8.30 - 5.30pm) - 1 hour for lunch |
Task 3: Create a time-phased budget for your example project using bottom-up estimating. As you allocate resources to the activity your budget is being created. After you extract the Gantt chart, revisit the activity list and be sure to check direct labour costs for you and your team has been added and add 20% for fringe.
In this section, State all assumptions and constraints you have used when creating your budget. Give examples of known knowns and known unknowns (these are financial risks) on your project. Describe how you have budgeted for both of them plus how you have budgeted for unknown unknowns
Task 4: Risk Register
Create a risk register In the form of a risk register as per the format and example below
Task5 : Quality Management Plan.
It should include a short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client.
Develop and describe 3 quality issues related to this project that your project team could implement to ensure quality
Task6: Closure checklist and project evaluation.
Develop a closure checklist that the project team will use to ensure that the project has been closed properly.
Develop a project evaluation –outline and discuss how your project’s MOV will be evaluated.
WBS in Indented Format
Following are the key assumptions that has been considered in relation to this particular project –
- The project will be completed within 178 days where 5 working days have been considered in a week along with the 8 working hours per day.
- The project will be completed within the assigned budget
- There will be no margin error for the project estimation
- All the needed materials in order to project execution will be available without incurring procurement of over headed cost.
- The allocated cost for the daily activities will be remain same
- The event resources will be distributed within the various activities of the project
Following are the constraints that have been identified for this particular project –
- The budget that allocated for this project of AUD 50000
- The allocated resources for this particular project will be available until the project finish
- The project budget has been allocated according to the schedule time
- The project manager added 20% fringe to the project budget.
The selected budget for this project is AUS 50000. The budget is prepared according to the project activities and required resources. The resources are also allocated according to the budget after confirming that all the resources will be available until project completion (Snyder, 2014). The project manager also followed the budget estimation technique using the tool that is demonstrating the confidence of the budget preparation accordingly.
In this project, the budgeting has been done for known knows and known unknown for this project of the building of website development for social media research center (Kerzner, 2013). The examples of known knowns on the project that have been identified are as below:
- In the project team, needed additional members in project team that may lead in increasing direct labor cost.
- Extension of the project due to changes in scope resulting into increase in project cost.
- The examples of known unknowns on the project that have been identified are as below:
- Request for changes in project scope may increase the budget.
- The resource costs may increase with time during the project.
The budgeting for the unknown unknowns have been done by adding 20% for fringe that is 10,000.00 AUD have been kept reserved in terms of resolving the issues or risks that may occur in the project (Schwalbe, 2015).
Risk ID |
Description and Cause |
Proximity |
Likelihood |
Consequence |
Level |
Treatment Response |
Treatment |
R01 |
Delay in project charter approval |
High |
4.Likely |
4.Major |
High |
Reduce |
The project manager need to take action proactively for distrbuting the project charter aming the office so that it can be approved on priority |
R02 |
Over budgeting for the project |
High |
3.Possible |
4.Major |
High |
Avoid |
Proper techniques need to be apply for budget preparations |
R03 |
Changes in project scope and requirements |
Low |
2.Unlikely |
2.Minor |
Low |
Transfer |
Before staring the project, need to clarify the requirement from the client so that there will be less chance of changes in project charter as well as in requirements |
R04 |
Changes in blueprint design for web application |
Low |
2.Unlikely |
4.Major |
Medium |
Avoid |
The development team should be proactive |
The project team had been focusing on the development of the website for the development of the operations of the Social Media Research Centre. The website development would be evaluated for the development of the effective communication in the development of the operations and formation of the smart development models in the organization. The project team had been deployed for the formation of the standard quality of the operations in the project. The project team had been deployed for forming the accurate development model for the web application development.
The three major quality issues for the project of development of the website for social media research center are,
Loop hole in budget: The major issue in the development of the social media research center is loop hole or issue in the budget (Haycock & Parry, 2014). The uneven distribution of the budget would result in forming the issues in the budget.
Design Flaws in the website: The most significant issue of the website development project is the design issues or the flaws in the designing process. The design issues would result in forming the errors of integration of the website with the processes of the organization.
Database Flaw: The flaw in the development of the database design would cause the deployment issues in the process of the social media research center (Simons, 2013). The flaw in database would cause the errors for implementing the systematic database structure of the website.
The closure checklist had been made for evaluating the aspects of the project that had been completed. A checklist for the project had been given below,
WBS development had been completed for the project |
Documents had been made and reviewed in the project |
Project charter documents had been made |
Feedbacks on the project had been developed |
Evaluation of the project operations had been done comprehensively |
Project had been completed |
Clients |
The website would tend to attract more users towards using the services of social media research centre |
Economics |
The traffic readings would help in generating revenue for the operations |
Social |
Social connectivity in the project operations would be eased by the development of the website |
Connectivity |
Simplified connection between the customers and users would be appreciated and developed by the use of website |
References
Boyle, G. (2017). Design project management. Routledge.
Elmhedwi, T. R., Elmabrouk, S. K., & Sherif, M. A. (2015, March). Practical risk management plan of Wi-Fi network deployment; case study. In Industrial Engineering and Operations Management (IEOM), 2015 International Conference on (pp. 1-10). IEEE.
Haycock, K., & Parry, K. (2014). Project Management Plan Fall 2014.
Hill, G. M. (2013). The complete project management office handbook. CRC Press.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Pritchard, C. (2013). The project management communications toolkit. Artech House.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Simons, R. (2013). Performance Measurement and Control Systems for Implementing Strategy Text and Cases: Pearson New International Edition. Pearson Higher Ed.
Snyder, C. S. (2014). A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2021). Project Management Tasks Require Careful Planning And Execution.. Retrieved from https://myassignmenthelp.com/free-samples/itc505-ict-project-management/evaluated-for-development-of-the-effective.html.
"Project Management Tasks Require Careful Planning And Execution.." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/itc505-ict-project-management/evaluated-for-development-of-the-effective.html.
My Assignment Help (2021) Project Management Tasks Require Careful Planning And Execution. [Online]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/evaluated-for-development-of-the-effective.html
[Accessed 23 November 2024].
My Assignment Help. 'Project Management Tasks Require Careful Planning And Execution.' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/itc505-ict-project-management/evaluated-for-development-of-the-effective.html> accessed 23 November 2024.
My Assignment Help. Project Management Tasks Require Careful Planning And Execution. [Internet]. My Assignment Help. 2021 [cited 23 November 2024]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/evaluated-for-development-of-the-effective.html.