The objectives of the project are:
- To develop the replicated panels for A-123 flight as requested by Sim Corporation.
- To complete the panels and the documentations associated with it within a period of 10 weeks from the day the project starts (the project is expected to start from January 12, 2009).
- To complete the entire project within a budget of £ 19,400 and in accordance to the quality requirements mentioned in the tender documents.
- To demonstrate the use of appropriate project management procedures within the organization
The information provided in the case study indicates that the project deliverable includes the following:
- Feasibility study documentation
- 3 D studies documentation
- Developing product description
- Assembly drawings
- Product manuals
- System Test procedure
- Project specification
- Tested and validated flight panels
The project milestones are as follows:
Task Name |
Duration |
Start |
Finish |
Development of A 123 flight simulator |
50.75 days |
Mon 1/12/09 |
Mon 3/23/09 |
planning starts |
0 days |
Mon 1/12/09 |
Mon 1/12/09 |
Other project activities |
1.13 days |
Mon 1/12/09 |
Tue 1/13/09 |
Task prior to CDR |
48.75 days |
Mon 1/12/09 |
Thu 3/19/09 |
feasibility studies |
5 days |
Mon 1/12/09 |
Fri 1/16/09 |
Feasibility study documentation |
2 days |
Mon 1/19/09 |
Tue 1/20/09 |
3 D studies |
7 days |
Wed 1/21/09 |
Thu 1/29/09 |
Collect data from 3 D models |
10 days |
Fri 1/30/09 |
Thu 2/12/09 |
Convert data into electronic files |
4 hrs |
Fri 2/13/09 |
Fri 2/13/09 |
Developing product description |
6 days |
Fri 2/13/09 |
Mon 2/23/09 |
assembly drawing |
1.25 days |
Mon 2/23/09 |
Tue 2/24/09 |
manual development |
14 hrs |
Tue 2/24/09 |
Thu 2/26/09 |
Electronic board designing |
15.25 days |
Thu 2/26/09 |
Thu 3/19/09 |
CDR submitted |
0 days |
Thu 3/19/09 |
Thu 3/19/09 |
Procurement |
2 days |
Fri 2/13/09 |
Tue 2/17/09 |
Assembling |
15.38 days |
Tue 2/17/09 |
Tue 3/10/09 |
FAT |
2 days |
Thu 3/19/09 |
Mon 3/23/09 |
Simulator delivered to client |
0 days |
Fri 3/20/09 |
Fri 3/20/09 |
The following technical elements are required for the successful implementation of the project:
- The CA aerospace protocol has to be utilized in designing the communication between the panels
- The utilization of COTS for ensuring post service support in future is mandated.
- The critical design review (CDR) and the Factory Acceptance Testing (FAT) methods have to be utilized.
The limits exclusions of the project are being outlined in the section below:
- The raw materials to be utilized in developing the panel would be procured from external sources: LFC Engineering would be responsible for the task of assembling these raw materials and parts.
- The electrical board would be designed by LFC engineering: however, the production of the same would essentially be outsourced to some external vendor.
- As per the negotiations made after the tender process, LFC Engineering would be responsible for designing and developing only 5panels for flight A-123.
Name and designation |
Comments |
Date |
Please insert |
Project charter accepted and approved |
Please insert |
The work breakdown structure of the project is as follows:
Figure: Work breakdown structure of the project
(Source: Developed by author)
- Organizational breakdown structure project
The organizational breakdown structure of the project is as follows:
Figure: The organizational breakdown structure of the project
(Source: Developed by author)
The following table depicts the roles and responsibilities of the various resources associated with the project:
|
|
RACI Chart (Roles and Responsibilities Matrix) |
|
||
Process Name / Description: |
Development of A 123 flight simulator |
||||
|
|||||
Created On: |
Mar-17 |
Revision: |
3/25/2017 |
|
|
Created by: |
Please insert name |
||||
|
General manager |
Project Leader |
CAD designer |
Head of technical Office |
Project Management team (internal technicians, external consultant, part time resource) |
Project Related Activities |
I |
R |
- |
- |
R |
Feasibility study and documentation |
I |
A |
- |
- |
R |
3D study, modeling and documentation and product description |
I |
A |
- |
- |
R |
assembly drawing |
I |
A |
- |
- |
R |
manual development |
I |
A |
R |
R |
- |
Electronic board designing |
I |
R |
- |
- |
R |
Procurement |
I |
R |
- |
- |
- |
Assembling and installation |
I |
A |
- |
- |
R |
Testing and validation
|
I
|
A
|
C
|
C
|
R
|
|
R = Responsible, A = Accountable, C = Consulted, I = Informed |
The project schedule is as follows:
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
0 |
Development of A 123 flight simulator |
50.75 days |
Mon 1/12/09 |
Mon 3/23/09 |
|
|
1 |
planning starts |
0 days |
Mon 1/12/09 |
Mon 1/12/09 |
|
|
2 |
Other project activities |
1.13 days |
Mon 1/12/09 |
Tue 1/13/09 |
|
|
2.1 |
Assigning resources |
1 day |
Mon 1/12/09 |
Mon 1/12/09 |
1 |
Ludovico, overtime cost, resource cost[1] |
2.2 |
client calls |
1 hr |
Tue 1/13/09 |
Tue 1/13/09 |
3 |
Ludovico |
2.3 |
Updating register |
1 hr |
Mon 1/12/09 |
Mon 1/12/09 |
1 |
Internal technician 2 |
2.4 |
Weekly coordination meeting |
1 hr |
Mon 1/12/09 |
Mon 1/12/09 |
1 |
Internal technician 2 |
3 |
Task prior to CDR |
48.75 days |
Mon 1/12/09 |
Thu 3/19/09 |
|
|
3.1 |
feasibility studies |
5 days |
Mon 1/12/09 |
Fri 1/16/09 |
1 |
Internal technician 3 |
3.2 |
Feasibility study documentation |
2 days |
Mon 1/19/09 |
Tue 1/20/09 |
8 |
Internal technician 2 |
3.3 |
3 D studies |
7 days |
Wed 1/21/09 |
Thu 1/29/09 |
9 |
Internal technicians 3 |
3.4 |
Collect data from 3 D models |
10 days |
Fri 1/30/09 |
Thu 2/12/09 |
10 |
Internal technician 4 |
3.5 |
Convert data into electronic files |
4 hrs |
Fri 2/13/09 |
Fri 2/13/09 |
11 |
internal technician 5 |
3.6 |
Developing product description |
6 days |
Fri 2/13/09 |
Mon 2/23/09 |
12 |
Internal technician 3 |
3.7 |
assembly drawing |
1.25 days |
Mon 2/23/09 |
Tue 2/24/09 |
|
|
3.7.1 |
assembly drawing 1 |
2 hrs |
Mon 2/23/09 |
Mon 2/23/09 |
13 |
Part time resource |
3.7.2 |
assembly drawing 2 |
2 hrs |
Mon 2/23/09 |
Mon 2/23/09 |
15 |
Part time resource |
3.7.3 |
assembly drawing 3 |
2 hrs |
Tue 2/24/09 |
Tue 2/24/09 |
16 |
Part time resource |
3.7.4 |
assembly drawing 4 |
2 hrs |
Tue 2/24/09 |
Tue 2/24/09 |
17 |
Part time resource |
3.7.5 |
assembly drawing 5 |
2 hrs |
Tue 2/24/09 |
Tue 2/24/09 |
18 |
Part time resource |
3.8 |
manual development |
14 hrs |
Tue 2/24/09 |
Thu 2/26/09 |
19 |
fernanado, Poldo |
3.9 |
Electronic board designing |
15.25 days |
Thu 2/26/09 |
Thu 3/19/09 |
|
|
3.9.1 |
chose specification |
6 days |
Thu 2/26/09 |
Fri 3/6/09 |
20 |
harness and wiring[1],Internal technician 3 |
3.9.2 |
Develop specification document |
3 days |
Fri 3/6/09 |
Wed 3/11/09 |
22 |
Internal technician 2 |
3.9.3 |
Configuration of electric board |
16 hrs |
Wed 3/11/09 |
Fri 3/13/09 |
23 |
Ludovico |
3.9.4 |
System Test procedure |
4 days |
Fri 3/13/09 |
Thu 3/19/09 |
24 |
Internal technician 3 |
3.9.5 |
Develop project specification |
0.25 days |
Thu 3/19/09 |
Thu 3/19/09 |
25 |
Internal technician 4 |
3.10 |
CDR submitted |
0 days |
Thu 3/19/09 |
Thu 3/19/09 |
26 |
|
4 |
Procurement |
2 days |
Fri 2/13/09 |
Tue 2/17/09 |
|
|
4.1 |
Research suppliers |
0.5 days |
Fri 2/13/09 |
Fri 2/13/09 |
12 |
Ludovico |
4.2 |
Request quotes |
0.5 days |
Mon 2/16/09 |
Mon 2/16/09 |
29 |
Ludovico |
4.3 |
chose suppliers |
0.25 days |
Mon 2/16/09 |
Mon 2/16/09 |
30 |
Ludovico |
4.4 |
Manage procurement. Including delivery |
0.75 days |
Mon 2/16/09 |
Tue 2/17/09 |
31 |
Ludovico |
5 |
Assembling |
15.38 days |
Tue 2/17/09 |
Tue 3/10/09 |
|
|
5.1 |
Installation of all parts |
7 days |
Tue 2/17/09 |
Thu 2/26/09 |
32 |
external consultant[1], Dzus screws and bolts[1],harness and wiring[1],packaging and delivery cost[1],painting and surface treatment[1],Plates and support[1] |
5.2 |
Installation of electric board |
47 hrs |
Thu 2/26/09 |
Fri 3/6/09 |
34 |
Internal technician 4,CAN electric board[1] |
5.3 |
Firmware and software installation |
20 hrs |
Fri 3/6/09 |
Tue 3/10/09 |
35 |
internal technician 5 |
6 |
FAT |
2 days |
Thu 3/19/09 |
Mon 3/23/09 |
|
|
6.1 |
testing and validation 1 |
1 day |
Thu 3/19/09 |
Fri 3/20/09 |
36,26 |
Internal technician 3 |
6.2 |
testing and validation 2 |
0.5 days |
Fri 3/20/09 |
Mon 3/23/09 |
38 |
internal technician 5 |
6.3 |
testing and validation 3 |
0.5 days |
Mon 3/23/09 |
Mon 3/23/09 |
39 |
Internal technician 2 |
7 |
Simulator delivered to client |
0 days |
Fri 3/20/09 |
Fri 3/20/09 |
38,5,6 |
|
The Gantt chart of the project is:
Figure: Gantt chart of the project
(Source: Developed by author)
The cost breakdown structure of the project has been provide below:
Figure: Cost Breakdown structure of the project
(Source: Developed by author)
The Planned Value chart of the project is s follows:
Figure: Planned value chart of the project
(Source: Developed by author)
Beringer, C., Jonas, D. and Kock, A., 2013. Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 31(6), pp.830-846.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2015. PMP Project Management Professional Exam Deluxe Study Guide: Updated for the 2015 Exam. John Wiley & Sons.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Lientz, B. and Rea, K., 2016. Breakthrough technology project management. Routledge.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Martinsuo, M., 2013. Project portfolio management in practice and in context. International Journal of Project Management, 31(6), pp.794-803.
Morris, P.W., 2013. Reconstructing project management. John Wiley & Sons.
Pemsel, S. and Wiewiora, A., 2013. Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), pp.31-42.
Phillips, J., 2013. PMP, Project Management Professional (Certification Study Guides). McGraw-Hill Osborne Media.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2022). Project Charter: A-123 Flight Simulator Development. Retrieved from https://myassignmenthelp.com/free-samples/ma6088-research-project-management/develop-the-replicated-panels-file-A81257.html.
"Project Charter: A-123 Flight Simulator Development." My Assignment Help, 2022, https://myassignmenthelp.com/free-samples/ma6088-research-project-management/develop-the-replicated-panels-file-A81257.html.
My Assignment Help (2022) Project Charter: A-123 Flight Simulator Development [Online]. Available from: https://myassignmenthelp.com/free-samples/ma6088-research-project-management/develop-the-replicated-panels-file-A81257.html
[Accessed 13 November 2024].
My Assignment Help. 'Project Charter: A-123 Flight Simulator Development' (My Assignment Help, 2022) <https://myassignmenthelp.com/free-samples/ma6088-research-project-management/develop-the-replicated-panels-file-A81257.html> accessed 13 November 2024.
My Assignment Help. Project Charter: A-123 Flight Simulator Development [Internet]. My Assignment Help. 2022 [cited 13 November 2024]. Available from: https://myassignmenthelp.com/free-samples/ma6088-research-project-management/develop-the-replicated-panels-file-A81257.html.