Projects generally do not go to plan. In this task you are required to update the milestone plan and schedule (completed in Assessment 2) and provide your client with a Progress Report, based on information in this brief. This information advises you of potential problems for your case scenario and you will need to consider how to address these issues.
Prepare a Progress Report for submission to the family (as your client). The report needs to include:
- an Introduction outlining the purpose of the report and what is contains;
- the project status detailing completions, slips and delays;
- implications of any changes made on the resources required to complete the project;
- details of all adjustments made to the schedule, and why you made these adjustments; and
- a personal reflection on the process.
Lacks logical flow and structure; Argument supported by theory sourced from non-academic literature. No discussion of academic research. Cites very few sources.
Some errors in logical flow and structure; Argument supported by basic discussion of relevant theory sourced from a minimal number of academic sources. if any discussion of relevant research.
Generally sound logical flow and structure; Argument supported by broad discussion of relevant theory sourced from academic literature. Relevant research acknowledged but not discussed. Cites several academic sources.
Issues Faced During the Project
This report defines and elaborates the crucial importance of using project management phases in order to deliver a proper initiation, planning and execution of a project. The purpose of the report is to show the progress and current status of “location shifting project.” Jeff has recently secured a new designation of Marketing director interstate and thus Jeff and Kelly along with their family started to plan a shifting from Maroochydore, on the Sunshine Coast, Qld to Perth. The new destination was already secured and they had to leave their current location on 20th January, 2019. The new job was about to start on 5th February. The days between 5th February and 20th January they have planned to take an apartment as rent new Perth as they can shift to their new apartment on 29th January. The total budget estimated for the entire shifting project was $15,000.
Due to sudden difficulties the previously planned project was interrupted partly due to this reason the project progress details are also changed. The modified project plans including the progress report are elaborated below. The new school of Jeff and Kelly’s children will start on 31st January therefore they have to shift to Perth before that. The modifications of the previously developed project plan is elaborated and detailed in the report section.
As per the current status Australia has bit with a harmful epidemic flu and Kelly has become ill. Due to this reason Kelly cannot take any of the relocation responsibilities these days. The doctor has advised Kelly to take rest for two weeks starting from 15th January. As they have to leave their current location on 20th January therefore, they planned to stay in their current location for more 14 days (that is till 29th January). Apart from this, the truck that was carrying the belongings of Jeff and Kelly was broken down near South Africa basically in n absolutely remote location. It is the responsibility of the Jeff and Kelly only to take respective responsibilities to repair the broken truck. They planned to reach Perth by 27th January first but then due to Kelly’s bad health condition it was delayed by 29th January. Above all, due to the broken truck issue the entire scenario was delayed by 30th January. On the other hand, due to Australia day celebration in Perth the numbers of flights are found to be limited. Due to this reason from Maroochydore, on the Sunshine Coast, Qld they will take flight on 29th January night so that they can reach Perth by 30th January and easily join the school on 31st January. On 30th January theory belongings will also be reached to Perth.
Adjustments Made to the Project Plan
After analyzing the entire scenario of the family relocation project to Perth it is determined that Kelly’s flu and sudden breakdown of the Truck was the two major issues. These issues should be considered once again for re-planning and re-developing the project properly. The doctor told Kelly to take 2 weeks rest without travelling. Therefore, the numbers of days in Maroochydore, on the Sunshine Coast, Qld was extended by 14 days. After theses 14 days on 29th January they will take their flight and reach Perth by 30th January. Then the children will e easily able to join their new school session from 31st January.
As it was initially told that the net budget of the project cannot exceed the value of $1500 thus, the re-planning was also done based on those aspects. The resources assigned to the project are aligned to the project requirements and success criteria and other assumptions also. Moreover, it is determined that the planned project will take total 29 days for successful implementation. Currently, the project is its planning phase. Due to the bad health condition of Kelly the entire project was Re-planned. The re-planned schedule has successfully made adjustment in the net budget without over allocation of cost and over allocation of budget also. The modified resources are as follows:
Name of the Resource |
Type |
Std. Rate |
Base Calendar |
Jeff and Kelly |
Work |
$0.00/hr |
Standard |
Project planner |
Work |
$25.00/hr |
Standard |
Truck reloading and planning |
Material |
$2,000.00 |
|
Packaging Cost |
Material |
$500.00 |
|
Logistic cost |
Material |
$1,165.00 |
|
Truck repairing cost |
Material |
$1,800.00 |
|
Others cost |
Material |
$950.00 |
|
Doctors fees |
Material |
$20.00 |
|
medicine cost |
Material |
$200.00 |
|
additional accommodation cost |
Material |
$2,800.00 |
Though, the order of the project is sequential but still it is not mandatory that each time one activity will start with the completion of the previous activity. Simultaneously, two or more than two activities can move towards progress. As Kelly has to take bed rest for around 14 days therefore for the activity consulting to doctor for the bad health condition of Kelly the predecessor set on Start to Start (SS) with a lag of 1 day. It will increase the number of days by 0.5 days but without affecting the total budget estimated for the project. Apart from this, another adjustment was also done in flight ticket booking project activity. The predecessor set for this activity was adjusted with Start to Finish (SF) by 2 day (lag). With successful analysis of the case scenario it is defined that if these adjustments are done and implemented orderly then the project will be completed within 26.5 days instead of 29 days within the estimate budget of $15000. After making adjustment the changes that are occurred elaborated and listed below:
Task Name |
Duration |
Predecessors |
Updated schedule for Family relocation to Perth project |
26.5 days |
|
Project initialization |
3 days |
|
Initial planning for relocation |
0.5 days |
|
Determine final date to relocate |
0.5 days |
2 |
consulting to the project planner and agent |
1 day |
3 |
Confirmation of final date |
1 day |
4 |
Milestone 1: Date selection and final relocation plan completed |
0 days |
5 |
Planning |
17 days |
|
Activities outlining |
1 day |
6 |
Proper scheduling the activities |
0.5 days |
8 |
Consulting to doctor for Kelly's bad health |
0.5 days |
9 |
14 days bed rest in Maroochydore, on the Sunshine Coast, Qld |
14 days |
10SS+1 day |
Extending numbers of days in Sunshine Coast, Qld Apartment |
0.5 days |
11 |
Flight tickets booked on 29th night to Perth |
0.5 days |
12SF-2 days |
Planning contingency |
0.5 days |
13 |
resource allocation |
0.5 days |
13 |
Milestone 2: Approving all plans |
0 days |
15,14 |
Pre-relocation activity planning |
6.5 days |
|
Recruiting movers and packers |
0.5 days |
16,9 |
Selling the things that are not required |
2 days |
18 |
Pre-approval mortgage |
1 day |
19,9 |
Keeping Copious Notes |
0.5 days |
20 |
Relocating from the old apartment |
0.5 days |
21 |
Contact to agent for truck service |
0.5 days |
22 |
Truck send to garage near South Africa |
0.5 days |
22 |
Repairing of the Truck |
0.5 days |
23,24 |
Reloading truck with the belongings |
1 day |
25 |
Milestone 3: Truck reloading and final move to Perth |
0 days |
26 |
Post Relocation activities |
2 days |
|
Final arrival to new apartment in Perth |
0.5 days |
27 |
unloading Trucks |
0.5 days |
29 |
Belongings unpacking and accommodating those |
0.5 days |
30 |
Join School in Perth |
0.5 days |
31 |
Milestone 4: Successful completion of project closure phase |
0 days |
32 |
After analyzing the entire project case scenario it is defined that project plan s the most crucial thing that needs to be followed by the project participants always to avoid over allocation of time and over allocation of budget as well. Project delays and project slips can be easily avoided if the project is planned properly before implementation. Apart from project plan there are certain knowledge areas also those are to be followed accordingly by the project planner, Jeff ad Kelly as well to avoid any issues even during the project progress period also. Adjustment in day counts is one of the very important parts for this project. Thus, it is felt that time and cost management features should definitely be followed before implementing the project. The truck using by them to carry their belongings was broken down in a remote location thus communication is the other important knowledge area should definitely be followed. Besides this, resource management is the other think must be followed by Jeff and Kelly while developing their family relocation project plan. Fr individual project activities proper resources are to be assigned and as soon as the resources are assigned it become their responsibilities to accomplish the activity within the assigned timeframe and budget as well.
New Timeline for Completion
Due to sudden attack of Flu to Kelly the previously planned project scenario was changed. Apart from this, sudden break down of the truck in a remote location is another issue which extended the numbers of days by 3. However, parallel work progresses are done in this project plan to avoid time consumptions and issues with additional cost.
Though, the entire project is not changed accordingly but still some of the activities are modified to complete the project before 31st January. Changes accommodated in some of the project activities are elaborated in the appendix section 2.
The updated Gantt chart will help Jeff and Kelly to visualize all the needful changes those are incorporated regarding the project activities. It is very important for the project planner, Jeff and Kelly to understand the complete project outline so that during implementation o error can occur. The details of the Gantt chart is elaborated in the below Appendix 3.
References
Ahern, T., Leavy, B., and Byrne, P. J. 2014. Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), 1371-1381.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., and Wang, Q. 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists. Educational Policy, 29(1), 257-277.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., and de Almeida, L. F. M. 2014. Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.
Conger, S. 2015. Six sigma and business process management. In Handbook on Business Process Management 1 (pp. 127-146). Springer, Berlin, Heidelberg.
First, M. B. 2016. Adopting a continuous improvement model for future DSM revisions. World Psychiatry, 15(3), 223-224.
Heldman, K. 2015. PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley and Sons.
Hornstein, H. A. 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., and Müller, R. 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., and Villanueva, P. 2014. Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327-340.
Mir, F. A., and Pinnington, A. H. 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Sanchez, M. A. 2015. Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.
Todorovic, M. L., Petrovi?, D. ?., Mihic, M. M., Obradovic, V. L., and Bushuyev, S. D. 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2020). Family Relocation To Perth Essay: Progress Report & Plan Adjustments.. Retrieved from https://myassignmenthelp.com/free-samples/mba642-project-initiation-planning-and-execution1.
"Family Relocation To Perth Essay: Progress Report & Plan Adjustments.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/mba642-project-initiation-planning-and-execution1.
My Assignment Help (2020) Family Relocation To Perth Essay: Progress Report & Plan Adjustments. [Online]. Available from: https://myassignmenthelp.com/free-samples/mba642-project-initiation-planning-and-execution1
[Accessed 26 December 2024].
My Assignment Help. 'Family Relocation To Perth Essay: Progress Report & Plan Adjustments.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/mba642-project-initiation-planning-and-execution1> accessed 26 December 2024.
My Assignment Help. Family Relocation To Perth Essay: Progress Report & Plan Adjustments. [Internet]. My Assignment Help. 2020 [cited 26 December 2024]. Available from: https://myassignmenthelp.com/free-samples/mba642-project-initiation-planning-and-execution1.