Briefly Describe the Project Cost and Schedule Control For Destination Family.
The project is focusing on developing the re-union of the destination family living in Palm Island, Florida. It helps in encouraging strong bonding between the family members for preserving the cultural values of the family. The arrangement of the trip helps in bringing 150 families together under a single platform where they can enjoy, share feeling, vision, and others among them. It helps in generating a feeling of refreshment in them. The focus of the project is to develop a plan for the family trip to make them memorable. The numbers of activities are designed for target audience such as women, men, elderly person, and children. The musical shows should be arranged for getting pleasant feeling to the family members. The proactive development of the activities helps in developing synchronisation for the successful completion of the project. In this paper, we are going to focus on the scope statement for indulging the activities required for the successful implementation of reunion family trip program for the destination location. The scheduling of the project activities helps in completing the project within the period of 33 days and estimated budget is $427,520.00.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
0 |
Family reunion project |
33 days |
Tue 01-05-18 |
Thu 14-06-18 |
|
1 |
Initiation phase |
3 days |
Tue 01-05-18 |
Thu 03-05-18 |
|
1.1 |
Arrangement of meetings with the family for initializing the plan of the trip for reunion |
1 day |
Tue 01-05-18 |
Tue 01-05-18 |
Event coordinator |
1.2 |
Taking approval on the date of the trip which is suitable for 150 families together |
1 day |
Wed 02-05-18 |
Wed 02-05-18 |
Event manager |
1.3 |
Approaching an Event Manager for developing a complete breakdown of trip plan for the reunion of the families |
1 day |
Thu 03-05-18 |
Thu 03-05-18 |
Event manager |
2 |
Planning phase |
10 days |
Fri 04-05-18 |
Thu 17-05-18 |
|
2.1 |
Selection of destination for the planned trip |
2 days |
Fri 04-05-18 |
Mon 07-05-18 |
Event planner |
2.2 |
Taking approval of selected destination from the families |
1 day |
Tue 08-05-18 |
Tue 08-05-18 |
Event planner |
2.3 |
Allocating cost to the resources required |
1 day |
Tue 08-05-18 |
Tue 08-05-18 |
Event planner |
2.4 |
Developing the overall budget for the approved project |
1 day |
Tue 08-05-18 |
Tue 08-05-18 |
Event planner |
2.5 |
Minimizing the budget according to the suitability of the families by |
1 day |
Tue 08-05-18 |
Tue 08-05-18 |
Event planner |
2.6 |
Finalization of date of the trip |
3 days |
Wed 09-05-18 |
Fri 11-05-18 |
Event planner |
2.7 |
Booking of the to and fro flight ticket |
2 days |
Mon 14-05-18 |
Tue 15-05-18 |
Event organizer, Event planner |
2.8 |
Booking of the hotel accommodation for 150 families |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event planner, Expenditure for travelling[1] |
2.9 |
Synchronization of the activities for arranging family adventures program |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event planner, Expenditure for travelling[1] |
2.10 |
Provision of activities for all age groups such as Kids, Women, and Men |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event planner, Expenditure for travelling[1] |
2.11 |
Taking approval from the family members |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event planner, Expenditure for travelling[1] |
2.12 |
Signing Off from the head off the family for clearance |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event planner, Expenditure for travelling[1] |
3 |
Execution phase |
18 days |
Fri 18-05-18 |
Tue 12-06-18 |
|
3.1 |
Family adventure |
3 days |
Fri 18-05-18 |
Tue 22-05-18 |
Event coordinator, Event planner |
3.2 |
Ski resort |
3 days |
Wed 23-05-18 |
Fri 25-05-18 |
Event organizer, Accommodation cost[1] |
3.3 |
Charlotte Harbour tours |
3 days |
Mon 28-05-18 |
Wed 30-05-18 |
Event coordinator |
3.4 |
Hooked on SUP |
1 day |
Thu 31-05-18 |
Thu 31-05-18 |
Event organizer |
3.5 |
Arranging of trip to stump pass beach and the state park |
3 days |
Fri 01-06-18 |
Tue 05-06-18 |
Event manager, Expenditure for travelling[1] |
3.6 |
Arranging trip to the gulf Island |
1 day |
Wed 06-06-18 |
Wed 06-06-18 |
Event coordinator |
3.7 |
Ordering of Food according to the personal requirement of the family |
1 day |
Thu 07-06-18 |
Thu 07-06-18 |
Event organizer, Other additional cost[1] |
3.8 |
Arranging group photo session |
1 day |
Fri 08-06-18 |
Fri 08-06-18 |
Event coordinator |
3.9 |
Taking group photos for all time memories |
1 day |
Mon 11-06-18 |
Mon 11-06-18 |
Event coordinator |
3.10 |
Deployment of musical show for the entertainment |
1 day |
Tue 12-06-18 |
Tue 12-06-18 |
Event manager |
3.11 |
Analysis of the requirement placed by the family members |
1 day |
Tue 12-06-18 |
Tue 12-06-18 |
Event manager |
3.12 |
Recommendation of the trip activities should be included for the success of the reunion family program |
1 day |
Tue 12-06-18 |
Tue 12-06-18 |
Event manager |
4 |
Closure phase |
2 days |
Wed 13-06-18 |
Thu 14-06-18 |
|
4.1 |
Feedback from the family members |
1 day |
Wed 13-06-18 |
Wed 13-06-18 |
Event manager |
4.2 |
Returning to home |
1 day |
Thu 14-06-18 |
Thu 14-06-18 |
Event manager |
From the above schedule for the project, it has been identified that Budget at Completion (BAC) is $427,520 and the duration for the project is 33 days. The Planned Value (PV) to execute the project is estimated to be $200,000 but the Actual Cost (AC) is $250,000. The work that has been completed till date is determined to be 50%.
Earned Value (EV) for the project is formulated as below:
Total project budget * % of work completed in project
= $427,520 * 50%
= $213,760
Cost Variance (CV) for the project is formulated as below:
Earned Value (EV) - Actual Cost (AC)
= $213,760 - $250,000
= (-) $36,240
From the value of cost variance, it can be said that the project is over-budget as it has a negative value.
Schedule Variance (SV) for the project is formulated as below:
Earned value (EV) - Planned value (PV)
= $213,760 - $200,000
= $13,760
From the value of schedule variance, it can be said that the project is ahead of schedule as it has a positive value.
Cost performance Index (CPI) for the project is formulated as below:
Earned Value (EV) / Actual cost (AC)
= $213,760 / $250,000
= 0.86
From the value of Cost Performance Index, it can be said that the project is over-budget as amount being spent is greater than the estimated cost.
Schedule 1
Schedule performance Index (SPI) for the project is formulated as below:
= Earned Value (EV) / Planned Value (PV)
= $213,760 / $200,000
= 1.07
From the value of Schedule Performance Index, it can be said that more work has been completed than the planned completion percentage.
The value of EAC is formulated as below:
AC + [(BAC-EV) / (CPI*SPI)]
= $250,000 + [($427520 - $213760) / (0.86 * 1.07)]
= $517,200
Hence, it has been identified that the estimate at completion for the project is $517,200 which means that additional cost of $89,680.00 will be required to complete the project.
Based on the performance analysis, it can be said that the project is over budget and hence the corrective actions that could be applied to put the project back on track are mentioned as below:
- Reallocation of resource: This action will help to identify the possible reasons behind the over budgeting of project. The over allocation of the resources can also be resolved so that the project can be completed as per the estimated budget.
- Checking of dependencies: The proper application of dependencies can be used to resolve the issue of over budget as some tasks can be carried out simultaneously with other task. So, eventually it will help to reduce the cost overhead as per the progress of project.
- Checking of activities that are time constrained: The time constrained activities have to be checked properly such that the task could be completed with different approach.
- Crashing the schedule: The budget of the project could be reduced with the application of additional resources in critical path. The activities to be completed as per estimated schedule for the entire project.
The revised Estimate at Completion (EAC) value for the project after implementing corrective actions is presented as below:
AC + [(BAC-EV) / (CPI*SPI)]
= $250,000 + [($428,240 - $256,944) / (1.02*1.28)]
= $250,000 + [$171,296 / 1.3] = $ (250,000 + 131,766.15) = $381,766.15
Hence, it has been identified that the EAC for revised project schedule is $381,766.15 which means that the project could be completed within the estimated budget.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
0 |
Family reunion project |
43 days |
Tue 01-05-18 |
Thu 28-06-18 |
|
1 |
Initiation phase |
3 days |
Tue 01-05-18 |
Thu 03-05-18 |
|
1.1 |
Arrangement of meetings with the family for initializing the plan of the trip for reunion |
1 day |
Tue 01-05-18 |
Tue 01-05-18 |
Event coordinator |
1.2 |
Taking approval on the date of the trip which is suitable for 150 families together |
1 day |
Wed 02-05-18 |
Wed 02-05-18 |
Event manager |
1.3 |
Approaching an Event Manager for developing a complete breakdown of trip plan for the reunion of the families |
1 day |
Thu 03-05-18 |
Thu 03-05-18 |
Event manager |
2 |
Planning phase |
20 days |
Fri 04-05-18 |
Thu 31-05-18 |
|
2.1 |
Selection of destination for the planned trip |
2 days |
Fri 04-05-18 |
Mon 07-05-18 |
Event planner |
2.2 |
Taking approval of selected destination from the families |
1 day |
Thu 10-05-18 |
Thu 10-05-18 |
Event planner |
2.3 |
Allocating cost to the resources required |
3 days |
Tue 08-05-18 |
Thu 10-05-18 |
Event planner |
2.4 |
Developing the overall budget for the approved project |
1 day |
Thu 10-05-18 |
Thu 10-05-18 |
Event planner |
2.5 |
Minimizing the budget according to the suitability of the families by |
1 day |
Thu 10-05-18 |
Thu 10-05-18 |
Event planner |
2.6 |
Finalization of date of the trip |
3 days |
Fri 11-05-18 |
Tue 15-05-18 |
Event planner |
2.7 |
Booking of the to and fro flight ticket |
2 days |
Wed 16-05-18 |
Thu 17-05-18 |
Event organizer, Event planner |
2.8 |
Booking of the hotel accommodation for 150 families |
2 days |
Fri 18-05-18 |
Mon 21-05-18 |
Event planner, Expenditure for travelling[1] |
2.9 |
Synchronization of the activities for arranging family adventures program |
2 days |
Tue 22-05-18 |
Wed 23-05-18 |
Event planner, Expenditure for travelling[1] |
2.10 |
Provision of activities for all age groups such as Kids, Women, and Men |
2 days |
Thu 24-05-18 |
Fri 25-05-18 |
Event planner, Expenditure for travelling[1] |
2.11 |
Taking approval from the family members |
2 days |
Mon 28-05-18 |
Tue 29-05-18 |
Event planner, Expenditure for travelling[1] |
2.12 |
Signing Off from the head off the family for clearance |
2 days |
Wed 30-05-18 |
Thu 31-05-18 |
Event planner, Expenditure for travelling[1] |
3 |
Execution phase |
18 days |
Fri 01-06-18 |
Tue 26-06-18 |
|
3.1 |
Family adventure |
3 days |
Fri 01-06-18 |
Tue 05-06-18 |
Event coordinator, Event planner |
3.2 |
Ski resort |
3 days |
Wed 06-06-18 |
Fri 08-06-18 |
Event organizer, Accommodation cost[1] |
3.3 |
Charlotte Harbour tours |
3 days |
Mon 11-06-18 |
Wed 13-06-18 |
Event coordinator |
3.4 |
Hooked on SUP |
1 day |
Thu 14-06-18 |
Thu 14-06-18 |
Event organizer |
3.5 |
Arranging of trip to stump pass beach and the state park |
3 days |
Fri 15-06-18 |
Tue 19-06-18 |
Event manager, Expenditure for travelling[1] |
3.6 |
Arranging trip to the gulf Island |
1 day |
Wed 20-06-18 |
Wed 20-06-18 |
Event coordinator |
3.7 |
Ordering of Food according to the personal requirement of the family |
1 day |
Thu 21-06-18 |
Thu 21-06-18 |
Event organizer, Other additional cost[1] |
3.8 |
Arranging group photo session |
1 day |
Fri 22-06-18 |
Fri 22-06-18 |
Event coordinator |
3.9 |
Taking group photos for all time memories |
1 day |
Mon 25-06-18 |
Mon 25-06-18 |
Event coordinator |
3.10 |
Deployment of musical show for the entertainment |
1 day |
Tue 26-06-18 |
Tue 26-06-18 |
Event manager |
3.11 |
Analysis of the requirement placed by the family members |
1 day |
Tue 26-06-18 |
Tue 26-06-18 |
Event manager |
3.12 |
Recommendation of the trip activities should be included for the success of the reunion family program |
1 day |
Tue 26-06-18 |
Tue 26-06-18 |
Event manager |
4 |
Closure phase |
2 days |
Wed 27-06-18 |
Thu 28-06-18 |
|
4.1 |
Feedback from the family members |
1 day |
Wed 27-06-18 |
Wed 27-06-18 |
Event manager |
4.2 |
Returning to home |
1 day |
Thu 28-06-18 |
Thu 28-06-18 |
Event manager |
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.
Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management, 33(2), 352-362.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Muller, R. (2017). Project governance. Routledge.
Portny, S. E. (2017). Project management for dummies. John Wiley & Sons.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, R. (2016). Gower handbook of project management. Routledge.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2020). Project Cost And Schedule Control For Destination Family. Retrieved from https://myassignmenthelp.com/free-samples/proj592-project-cost-and-schedule-control/corrective-actions.html.
"Project Cost And Schedule Control For Destination Family." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/proj592-project-cost-and-schedule-control/corrective-actions.html.
My Assignment Help (2020) Project Cost And Schedule Control For Destination Family [Online]. Available from: https://myassignmenthelp.com/free-samples/proj592-project-cost-and-schedule-control/corrective-actions.html
[Accessed 22 December 2024].
My Assignment Help. 'Project Cost And Schedule Control For Destination Family' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/proj592-project-cost-and-schedule-control/corrective-actions.html> accessed 22 December 2024.
My Assignment Help. Project Cost And Schedule Control For Destination Family [Internet]. My Assignment Help. 2020 [cited 22 December 2024]. Available from: https://myassignmenthelp.com/free-samples/proj592-project-cost-and-schedule-control/corrective-actions.html.