The System Development Life Cycle
Discuss about the Case Study Of The High Quality Institute.
The system development procedure is very important for any type of organization. The report henceforth is concerned with the case study of the high quality institute. The organization is looking to develop a system that would be helpful in their organization procedures. The organization is looking to incorporate two systems within the development which are the Undergraduate Learning System (ULS) and Postgraduate Learning System (PLS).
The detailed description of both the system which are to be developed in incorporation are provided in this report. The software developer staff at the IT department assigned the task of developing both learning systems from scratch.
The report consists of the information about the system development lifecycle of the software and also the work Breakdown structure of the development of the project, Additionally the ER Diagram associated with the development and the cost calculation is also provided in this report.
The system development life cycle is very important for any type of development of the software is very important. For the current project the waterfall model is selected and the processes that are involved in the model for the development of the system are; Analysis and feasibility phase, the planning and requirement phase, design phase, the testing phase, the deployment phase and the maintenance phase.
For the analysis phase the work should be strong about the deficiency that would be existing in the current structure for deciding the goals of the new approach. The feasibility study would also determine if the project goals and other aspects are viable for the organization and the society on a whole or not. In addition to this, the technical personnel of the organization would also perform the feasibility study on the project so that the technically the project works for the advancement of the organization. In addition to this, the overall project scope and the aims and objectives of the project are also defined in this phase of the development of the software. The economic, external factors and the human resources are also important which are to be processed during this phase and the schedule is also developed during this phase.
In the planning and the requirement phase the adaptations for the new system and the development of the completely new system is developed in this phase. The users’ requirement, hardware and software requirements and the overall capacities of the project are developed in the planning phase of the development.
Work Breakdown Structure (WBS)
In the designing phase the costs of the system and the requirements of the users are identified and are worked up on. The designing of the front end part and the database concepts such as the ER diagram and the data model are developed in this phase. After the planning phase the system development and the implementation of the system starts. The developers perform the coding and the designing of the system. The back coding and the integration of the system is done during the implementation phase of the project. Additionally, the physical configurations and the access control features are also performed in the implementation phase.
After the implementation phase the testing phase of the project is started. As the project that is being discussed in this report is a IT oriented project hence, the testing phase would involve the procedures of the usability testing, the responsive design testing and the UI testing. After conducting the testing, the users would be providing valuable insights for the further development of the project and this would help the developers to improve the final product to great extent.
After the implementation phase the project sign off stage would be processed by the developer and during the sign off phase the documentation about the project and system manual would be submitted to the owners. The project team would also be dissolved during this phase.
The work breakdown structure for the project that is to be completed within the budget is provided below:
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
Teaching and Learning |
95 days |
Thu 18-10-18 |
Wed 27-02-19 |
|
1 |
Project Initiation |
4 days |
Thu 18-10-18 |
Tue 23-10-18 |
|
1.1 |
Meeting with the college authority |
1 day |
Thu 18-10-18 |
Thu 18-10-18 |
|
1.2 |
Meeting for budget allocation |
1 day |
Fri 19-10-18 |
Fri 19-10-18 |
2 |
1.3 |
Project team compilation |
2 days |
Mon 22-10-18 |
Tue 23-10-18 |
3 |
2 |
Analysis of the system |
3 days |
Wed 24-10-18 |
Fri 26-10-18 |
|
2.1 |
Feasibility Study |
1 day |
Wed 24-10-18 |
Wed 24-10-18 |
4 |
2.2 |
Decide on the aims and objectives of the project |
1 day |
Thu 25-10-18 |
Thu 25-10-18 |
6 |
2.3 |
Allocation of budget for the project |
1 day |
Fri 26-10-18 |
Fri 26-10-18 |
7,2 |
3 |
Planning of the system development |
4 days |
Mon 29-10-18 |
Thu 01-11-18 |
|
3.1 |
Development of project Schedule |
1 day |
Mon 29-10-18 |
Mon 29-10-18 |
8 |
3.2 |
identification of Hardware and Software |
1 day |
Tue 30-10-18 |
Tue 30-10-18 |
10,7 |
3.3 |
Procurement of Hardware and Software |
2 days |
Wed 31-10-18 |
Thu 01-11-18 |
11 |
4 |
System Design |
8 days |
Fri 02-11-18 |
Tue 13-11-18 |
|
4.1 |
Planning the design of the Undergraduate Program |
2 days |
Fri 02-11-18 |
Mon 05-11-18 |
12 |
4.2 |
Planning the design of the Postgraduate Program |
2 days |
Tue 06-11-18 |
Wed 07-11-18 |
14,11 |
4.3 |
Designing for system integration |
4 days |
Thu 08-11-18 |
Tue 13-11-18 |
15 |
5 |
Project Implementation |
52 days |
Wed 14-11-18 |
Thu 24-01-19 |
|
5.1 |
System Interface design |
5 days |
Wed 14-11-18 |
Tue 20-11-18 |
16 |
5.2 |
Designing Interface for the undergraduate program |
7 days |
Wed 21-11-18 |
Thu 29-11-18 |
18 |
5.3 |
Designing Interface for the undergraduate program |
7 days |
Fri 30-11-18 |
Mon 10-12-18 |
19,15 |
5.4 |
procurement of the Student details of the university |
2 days |
Tue 11-12-18 |
Wed 12-12-18 |
20 |
5.5 |
Designing the database for the system |
5 days |
Thu 13-12-18 |
Wed 19-12-18 |
21 |
5.6 |
Inserting the data into the database |
6 days |
Thu 20-12-18 |
Thu 27-12-18 |
22 |
5.7 |
Implementing functions in the database |
3 days |
Fri 28-12-18 |
Tue 01-01-19 |
23 |
5.8 |
System back end development |
10 days |
Wed 02-01-19 |
Tue 15-01-19 |
24 |
5.9 |
System integration |
7 days |
Wed 16-01-19 |
Thu 24-01-19 |
25,20 |
6 |
System Testing |
8 days |
Fri 25-01-19 |
Tue 05-02-19 |
|
6.1 |
GUI Testing |
2 days |
Fri 25-01-19 |
Mon 28-01-19 |
26 |
6.2 |
Usability Testing |
1 day |
Tue 29-01-19 |
Tue 29-01-19 |
28 |
6.3 |
Compatibility Testing |
2 days |
Wed 30-01-19 |
Thu 31-01-19 |
29 |
6.4 |
System performance Testing |
2 days |
Fri 01-02-19 |
Mon 04-02-19 |
30 |
6.5 |
Fetch System testing report |
1 day |
Tue 05-02-19 |
Tue 05-02-19 |
31,26 |
7 |
System Rebuild |
7 days |
Wed 06-02-19 |
Thu 14-02-19 |
|
7.1 |
Receive the feedback of the user |
1 day |
Wed 06-02-19 |
Wed 06-02-19 |
32 |
7.2 |
Analysis of the user reviews |
1 day |
Thu 07-02-19 |
Thu 07-02-19 |
34 |
7.3 |
Deployment of minor fixes in the system |
5 days |
Fri 08-02-19 |
Thu 14-02-19 |
35,31 |
8 |
System Deployment |
2 days |
Fri 15-02-19 |
Mon 18-02-19 |
|
8.1 |
Upload the system on the server |
1 day |
Fri 15-02-19 |
Fri 15-02-19 |
36 |
8.2 |
Hand over the Administration credentials |
1 day |
Mon 18-02-19 |
Mon 18-02-19 |
38 |
9 |
Project Maintain ace |
5 days |
Tue 19-02-19 |
Mon 25-02-19 |
|
9.1 |
Schedule the project maintenance |
2 days |
Tue 19-02-19 |
Wed 20-02-19 |
39 |
9.2 |
Allocate resource for maintenance |
2 days |
Thu 21-02-19 |
Fri 22-02-19 |
41 |
9.3 |
creating the system manual |
1 day |
Mon 25-02-19 |
Mon 25-02-19 |
42 |
10 |
project Sign-Off |
2 days |
Tue 26-02-19 |
Wed 27-02-19 |
|
10.1 |
Handing over the system manual and project documentation |
1 day |
Tue 26-02-19 |
Tue 26-02-19 |
43 |
10.2 |
Dissolve the project team |
1 day |
Wed 27-02-19 |
Wed 27-02-19 |
45,36 |
The calculations for the budget and cost for the implementation of the system is provided below:
Cost benefit analysis |
||||||
Year 0 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|
Value of benefits |
$0 |
$7,000 |
$7,000 |
$7,000 |
$7,000 |
$7,000 |
Development cost |
($20,000) |
$750 |
$800 |
$770 |
$750 |
$730 |
Annual Expenses |
$0 |
($2,000) |
($2,000) |
($2,000) |
($2,000) |
($2,000) |
Net benefit/costs |
$10,000 |
$0 |
$0 |
$0 |
$0 |
$0 |
Net cash flow |
($10,000) |
$5,750 |
$5,800 |
$5,770 |
$5,750 |
$5,730 |
Discount factors |
||||||
Discount rate |
6% |
|||||
Year Index |
0 |
1 |
2 |
3 |
4 |
5 |
Discount factor |
1 |
0.94 |
0.89 |
0.84 |
0.79 |
0.75 |
Discounted flows |
||||||
Cost |
($20,000) |
($1,887) |
($1,780) |
($1,679) |
($1,584) |
($1,495) |
Benefit |
$10,000 |
$6,604 |
$6,230 |
$5,877 |
$5,545 |
$5,231 |
Net |
($10,000) |
$4,717 |
$4,450 |
$4,198 |
$3,960 |
$3,736 |
Cumulative |
($10,000) |
($5,283) |
($833) |
$3,365 |
$7,326 |
$11,062 |
Net present value |
$11,062 |
|||||
ROI |
33% |
|||||
Payback Analysis |
||||||
Years |
Months |
|||||
1 |
14 |
|||||
Payback Period in Years |
2.30 |
Conclusion
For conclusion it can be said the project development would be done using the waterfall model and the budgeting and the schedule of the project is done according to the waterfall model. The schedule of the project indicates that the project can be completed in the 95 days and the payback period is calculated to be 2.3 years approximately. Hence, the report provides the entire details of the development of the software by the organization.
Emery, B. and Lu, Q.R., 2015. Transcriptional and epigenetic regulation of oligodendrocyte development and myelination in the central nervous system. Cold Spring Harbor perspectives in biology, p.a020461.
Frank, A.G., 2018. The development of underdevelopment. In Promise of development (pp. 111-123). Routledge.
Grey, S. and Patel, R., 2015. Food sovereignty as decolonization: Some contributions from Indigenous movements to food system and development politics. Agriculture and Human Values, 32(3), pp.431-444.
Kotlarsky, J., van den Hooff, B. and Houtman, L., 2015. Are we on the same page? Knowledge boundaries and transactive memory system development in cross-functional teams. Communication Research, 42(3), pp.319-344.
Liu, Y., Zhan, L., Zhang, Y., Markham, P.N., Zhou, D., Guo, J., Lei, Y., Kou, G., Yao, W., Chai, J. and Liu, Y., 2016. Wide-area-measurement system development at the distribution level: An FNET/GridEye example. IEEE Trans. Power Del, 31(2), pp.721-731.
Quesnel-Vallières, M., Irimia, M., Cordes, S.P. and Blencowe, B.J., 2015. Essential roles for the splicing regulator nSR100/SRRM4 during nervous system development. Genes & development, 29(7), pp.746-759.
Rong, A. and Lahdelma, R., 2016. Role of polygeneration in sustainable energy system development challenges and opportunities from optimization viewpoints. Renewable and Sustainable Energy Reviews, 53, pp.363-372.
Schafer, D.P. and Stevens, B., 2015. Microglia function in central nervous system development and plasticity. Cold Spring Harbor perspectives in biology, p.a020545.
Van Eijndhoven, J., Kamps, T., Kastelijn, M., Rutten, M. and Stravers, P., Vector Fabrics BV, 2015. Embedded system development. U.S. Patent 9,081,928.
Wiegmann, D.A. and Shappell, S.A., 2017. A human error approach to aviation accident analysis: The human factors analysis and classification system. Routledge.
Yip, M.H., Phaal, R. and Probert, D.R., 2014. Stakeholder engagement in early stage product-service system development for healthcare informatics. Engineering Management Journal, 26(3), pp.52-62.
Yuan, X., Roundy, J.K., Wood, E.F. and Sheffield, J., 2015. Seasonal forecasting of global hydrologic extremes: system development and evaluation over GEWEX basins. Bulletin of the American Meteorological Society, 96(11), pp.1895-1912.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2019). Case Study Of The High Quality Institute. Retrieved from https://myassignmenthelp.com/free-samples/case-study-of-the-high-quality-institute.
"Case Study Of The High Quality Institute." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/case-study-of-the-high-quality-institute.
My Assignment Help (2019) Case Study Of The High Quality Institute [Online]. Available from: https://myassignmenthelp.com/free-samples/case-study-of-the-high-quality-institute
[Accessed 18 December 2024].
My Assignment Help. 'Case Study Of The High Quality Institute' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/case-study-of-the-high-quality-institute> accessed 18 December 2024.
My Assignment Help. Case Study Of The High Quality Institute [Internet]. My Assignment Help. 2019 [cited 18 December 2024]. Available from: https://myassignmenthelp.com/free-samples/case-study-of-the-high-quality-institute.