Complete the following three parts:
In this part you need to compare and evaluate subcontract quotations for formworker and concretor work and determine which should be used on the Strathfield Apartment project.
You are to assume that you are the Project Manager for the multi storey unit development and your program requires you to let the subcontract for Concrete And Formwork for the project urgently.
You elect to use a Dincel reinforced concrete wall system instead of basement block walls shown for its speed advantage.
You have received the attached four (4) quotations from the purchasing officer for the works. Analyse and compare these quotations by comparing them with your original tender budget for this work and decide which is the most cost and time effective so that a sub contract can be raised.
All the subcontractors have successfully done work for your company previously and are deemed equally proficient as each other to effectively carry out the specified works.
Liquidated damages on the project are $4,500 per day. Builder's site O/H costs are $2,000 per day. Assume all activities are programmed on the critical path.
Use the following tender budgets for your comparison.
Estimator'S Tender Budget Information:
Concretor Package No.1
Supply, place and finish reinforced 32MPa concrete and associated formwork and falsework supports to basement floor slabs, ramps and dincel walling up to and including the level 1 floor slab. (Note: waste is included in $ rates but not in measured quantities)
Total Concretor trade budget $483,157
Note: Formwork and falsework cost above includes to S&P Dincel. Concrete includes a waste allowance of 5% on measured quantity from drawings. Reinforcement quantity of 150kgs/m3 concrete is the theoretical reinforcement quantity, and a rolling margin of +5% is to be expected if trucks loads are weighed.
It is estimated that 12 concrete pump setups will be required to complete the works.
A normal working day is deemed to be from = 7am to 3.20pm and includes 20 mins extra per day to accumulate a rostered day off once every 4 weeks. The work is expected to take 65 working days.
In this part you need to develop a range of documents and procedures for use managing subcontractors over the life of a building project similar to that detailed and used on the Strathfield Apartment project.
It is very important to select the best subcontractor when implementing a construction project because subcontractors play a very vital role in successful completion of these projects (Hartmann, et al., 2009); (Marzouk, et al., 2013). This task involves evaluating and comparing four quotations submitted by four different companies for formwork and concrete works. The purpose of this evaluation is to select the best subcontractor (in terms of cost and completion time) for the formwork and concrete works on the Strathfield Apartment project. The builder (Best Constructions Pty Ltd) has prepared an original tender budget for the works and will be the basis of the quotation evaluation.
The budget for the formwork and concrete works estimated by the builder is provided in Table 1 below
Table 1: Budget estimate by Constructions Pty Ltd
Item |
Quantity |
Unit |
Unit Price ($) |
Total Cost ($) |
Formwork and concrete costs |
1 |
PC |
484,388.20 |
483,157 |
Liquidated damages |
0 |
Days |
4,500 |
0 |
O/H costs |
65 |
Days |
2,000 |
130,000 |
Total |
|
|
|
613,157 |
Assumption: there are eight hours in a normal working day and the concrete work will require 12 concrete pump setups.
The budget for the formwork and concrete works estimated by the Ultimate Concrete Services Pty Ltd is provided in Table 2 below
Table 2: Budget estimate by Ultimate Concrete Services Pty Ltd
Item |
Quantity |
Unit |
Unit Price ($) |
Total Cost ($) |
Concrete and reinforcement works |
1 |
PC |
305,520 |
305,520 |
Formwork requirements |
1,994 |
M2 |
92 |
183,448 |
Additional concrete pumps |
4 |
No |
750 |
3,000 |
Labour cost |
560 |
Hours |
68 |
38,080 |
O/H costs |
70 |
|
2,000 |
140,000 |
Liquidated damages |
5 |
Days |
4,500 |
(-22,500) |
Total |
|
|
|
647,548 |
It is important to note that Ultimate Concrete Services Pty Ltd will complete the work five days late. Therefore the liquidated damages cost equivalent to $22,500 will be deducted from its total cost as shown in Table 2 above.
The budget estimate by Ultimate Concrete services Pty Ltd also excludes the following items that will have to be supplied by the builder: all hoisting facilities except those required for concrete placement; all lunch, toilet and change facilities; and curing concrete surfaces.
Assumption: there are eight hours in a normal working day, and a total of 12 concrete setups will be required for the concrete work.
The budget for the formwork and concrete works estimated by the Professional Formwork and Concreting Services Pty Ltd is provided in Table 3 below
Table 3: Budget estimate by Professional Formwork and Concreting Services Pty Ltd
Item |
Quantity |
Unit |
Unit Price ($) |
Total Cost ($) |
Concrete testing |
527 |
M3 |
8 |
4,216 |
Place and finish concrete slabs |
527 |
M3 |
48 |
25,296 |
Concrete pump setups |
12 |
No |
500 |
6,000 |
Termite control |
684 |
M2 |
6 |
4,104 |
50mm sand blinding |
684 |
M2 |
4.30 |
2,941.20 |
Place only membrane |
684 |
M2 |
7 |
4,788 |
S&P and strip formwork |
1,310 |
M2 |
110 |
144,100 |
Labour cost |
424 |
Hours |
70 |
29,680 |
O/H costs |
53 |
|
2,000 |
106,000 |
Liquidated damages |
0 |
Days |
4,500 |
0 |
Total |
|
|
|
327,125.20 |
Professional Formwork and Concreting Services Pty Ltd will complete the work earlier than the stipulated deadline hence there are no liquidated damages.
The budget estimate by Professional Formwork and Concreting Services Pty Ltd provided in Table 3 above excludes the following: supply of concrete, S&P steel reinforcement, curing of concrete, supply of membrane and workers’ shed accommodation.
Assumption: there are eight hours in a normal working day, and the company will use 12 concrete setups to complete the concrete work.
The budget for the formwork and concrete works estimated by the Quality Concreting Pty Ltd is provided in Table 4 below
Table 4: Budget estimate by Quality Concreting Pty Ltd
Item |
Quantity |
Unit |
Unit Price ($) |
Total Cost ($) |
Formwork |
1 |
PC |
115,800 |
115,800 |
S&P and finish concrete works and reinforcement |
1 |
PC |
305,400 |
305,400 |
Additional pump setups |
4 |
No |
750 |
3,000 |
Labour cost |
560 |
Hours |
75 |
42,000 |
O/H costs |
70 |
Days |
2,000 |
140,000 |
Liquidated damages |
5 |
Days |
4,500 |
(-22,500) |
Total |
|
|
|
583,700 |
Quality Concreting Pty Ltd will complete the work five days late. Therefore the liquidated damages cost equivalent to $22,500 will be deducted from its total cost as shown in Table 4 above.
The budget estimate by Quality Concreting Pty Ltd provided in Table 4 above excludes the following: concrete testing, supply of hoisting facilities, curing of concrete, sand blinding, termite control, removal of rubbish, and S&P ‘Fortecon’ slab underlay.
Assumption: there are eight hours in a normal working day, and the company will use 12 concrete setups to complete the concrete work.
The budget for the formwork and concrete works estimated by the P&W Concreting Services Pty Ltd is provided in Table 5 below
Table 5: Budget estimate by P&W Concreting Services Pty Ltd
Item |
Quantity |
Unit |
Unit Price ($) |
Total Cost ($) |
Suspended formwork |
1,310 |
M2 |
95 |
124,450 |
S&P steel reinforcement |
79.05 |
Tonnes |
2,200 |
173,910 |
S&P and finish 32MPa concrete |
527 |
M3 |
198 |
104,346 |
Labour cost |
576 |
Hours |
67 |
38,592 |
O/H costs |
72 |
Days |
2,000 |
144,000 |
Liquidated damages |
7 |
Days |
4,500 |
(-31,500) |
Total |
|
|
|
553,798 |
Weight of steel reinforcement = 527 m3 x 0.15 tonnes/m3 = 79.05 tonnes
P&W Concreting Services Pty Ltd will complete the work seven days late. Therefore the liquidated damages cost equivalent to $31,500 will be deducted from its total cost as shown in Table 5 above.
The budget estimate by P&W Concreting Services Pty Ltd provided in Table 5 above excludes the following: supply of membrane, curing of concrete, testing of concrete, supply of workers sheds, hoisting of materials, and removal of rubbish.
Professional Formwork and Concreting Services Pty Ltd has the lowest bid ($327,125.20) and will complete the work 12 days earlier than the stipulated deadline. However, the company has excluded very essential items in its budget estimate. Including these items will exceed the estimated budget by the builder. Therefore the company is not able to offer the required materials and services for the job hence not suitable for the formwork and concrete work package. P&W Concreting Services Pty Ltd has the second lowest bid ($553,798) and will complete the work seven days late than the stipulated deadline. The company has also excluded some items in its budget but the items can be provided by the builder from the other works being performed on the project. If the items are included in the budget, the company’s estimate still would not exceed the builder’s estimate.
The budget estimate for Ultimate Concrete Services Pty Ltd is $647,548 and the company will complete the work 5 days late than the stipulated deadline. The company has also excluded some items though they can be easily provided by the builder without incurring much cost. However, the company’s estimate already exceeds the builder’s estimate even before adding the excluded items. Hence the subcontractor should not be considered for the job.
The budget estimate for Quality Concreting Pty Ltd is $583,700 and the company will complete the work five days late than the stipulated deadline. The company has excluded some items that are essential and will have to be provided by the builder from external sources. This may lead to further delay and additional costs.
Therefore each of the four subcontractors have exclusions i.e. items that they have not included in their budget estimates. But considering the cost, time and the ability of the company to complete the required works adequately, the most suitable subcontractor for the formwork and concrete works package is P&W Concreting Services Pty Ltd.
Below is a set of questions that can be used to interview the lowest tenders in search for a suitable subcontractor to perform particular work in a construction project:
Pre Award Subcontractor Interview Template
Signed by:
Builder (or representative): Date:
Subcontractor (or representative: Date:
It is very important to evaluate a subcontractor comprehensively during selecting process (Ng & Skitmore, 2014). Some of the criteria to use for the selection process include the following:
Workforce: the company should have adequate skilled, semi-skilled and unskilled employees with the necessary academic qualifications and skills set to perform the work (Abbasianjahromi, et al., 2013).
Plant and equipment: the company should have the necessary plant/equipment to perform the work (Abbasianjahromi, et al., 2016). The plant/equipment may either be owned or leased.
Experience: the company’s previous works should be evaluated as it provides essential information about the company’s capability to perform the work at hand (Ulubeyi, et al., 2017). Companies with vast experienced in similar projects should be preferred.
Reputation: the reputation provides useful information about the company’s professionalism and the kind of relationship it builds with its partners and clients. A bad reputation should always be a red flag.
Certification: the company should have the necessary licenses and permits to operate business in the region as this shows that it has all the qualifications in that field (Abbasianjahromi, et al., 2018). This information can be requested from the company or obtained from relevant regulatory agencies.
Litigation cases: it is also important to check the number of solved and ongoing litigation cases that the company has had over the past years. This gives vital information about the possibility of conflicts and disputes (Akintan & Morledge, 2013). Companies with less litigation cases should be preferred.
Financial records: the company selected should have a stable financial record as this shows that it can meet some of the fundamental financial needs (Polat, 2016). The financial information can be obtained from the company’s financial reports or relevant financial institutions where the company makes its transactions.
Workload: it is also important to ensure that the company’s current workload does not affect its capability to perform the work.
Quality assurance: the company’s quality assurance and control systems should be evaluated to ensure that they guarantee high quality of the final products or services.
Safety: it is also recommended to select a company that has a comprehensive safety control and management plan to ensure safety and health of people on and around the site.
Innovativeness: innovation is very important today as it helps in reducing waste, costs, time and carbon footprint. As a result, it is important to look at some of the innovative concepts or systems that a company adopts in its operations.
Values and ethics: the company selected should also have an accepted code of ethics and b guided by values such as transparency, accountability, client satisfaction, sustainability, etc. This information can be obtained from the company’s websites, brochures, performance reports, etc.
Since the potential subcontractors are not currently on the company books, there is limited information about them. However, information about the company’s qualification, previous work history, credit checks, etc. can be gathered through the following approaches: requesting the subcontractor to share relevant documents such as registration or incorporation certificate, licenses, permits, project completion certificates, project handover certificates, company awards, recommendation letters and annual reports; seeking information from relevant government agencies; gathering information from company websites and social media networks; and requesting information from pertinent financial institutions.
The most suitable subcontractor can be selected from a group of subcontractors by using a matrix where scores are awarded to different criteria that are used to evaluate the shortlisted subcontractors. Below is a template that can be used to rank and select a new subcontractor. The best subcontractor is the one that has the highest total score.
Criteria |
Weight |
Score |
Remarks |
Workforce |
10 |
|
|
Plant/equipment |
10 |
|
|
Experience |
10 |
|
|
Reputation |
10 |
|
|
Certification |
10 |
|
|
Litigation cases |
10 |
|
|
Financial records |
10 |
|
|
Workload |
10 |
|
|
Quality assurance |
10 |
|
|
Safety |
10 |
|
|
Innovativeness |
10 |
|
|
Values and ethics |
10 |
|
|
Total |
120 |
|
|
The role of communication in successful implementation of projects cannot be overemphasized (Reyes-Martinez & Chileshe, 2011). The following are some of the communication methods that can be used by subcontractors on site to share information with other stakeholders:
Phone calls: this is the process where the subcontractor makes a phone call directly to whom he/she wants to communicate with. The process involves immediate responses.
Electronic: this is a commonly used formal process of communication between subcontractors and other stakeholders. It mainly involves sharing information, including documents, drawings, presentations, etc. through emails (Richards, 2018).
Teleconferencing and video conferencing: teleconferencing involves use of telephone conferencing system whereas video conferencing involves use of video conferencing system where those communicating see each other on a TV or computer screen.
Site meetings: this is where the subcontractor organizes for a meeting with other stakeholders to discuss issues arising or progress of the report. In this process, participants attend the meeting physically.
Print media: this involves printing the materials containing information to be communicated, such as progress report or site meeting resolutions, and sharing them with relevant stakeholders.
Letters: this is where the subcontractor writes a letter and sends it to other stakeholders. It may take more time for the subcontractor to receive responses when using letter depending on the delivery method.
Some of the necessary steps to take before conducting an interview about unsatisfactory work by a subcontractor are as follows: review the contract documents; evaluate the documents submitted by the subcontractor about her qualifications; identify areas where the subcontractor’s performance was poor; identify potential factors that may have contributed to the poor performance; establish potential laxities of the subcontractor; determine quality assurance; control and management systems that the subcontractor was using; use the gathered information to prepare a poor performance report; and invite the subcontractor to attend the planned interview.
Below is a template that can be used to conduct a subcontractor performance interview about unsatisfactory work:
Poor Subcontractor Performance Interview
Project name:
Project number:
Project location:
Subcontractor name:
Subcontract no:
Subcontract type:
Subcontract value:
Completion date:
Project progress (%):
Date:
The staffs to interview when investigating the poor performance of subcontractors include: representatives of the subcontractor including consultants, financial officer, site manager, safety manager, supervisor and foreman; and representatives of the builder including site engineer, quality manager and supervisor.
If a subcontractor performs poorly, it is very important to develop an action plan that will improve performance of the current and future contracts. Some of the activities that can be included in the action plan include: vet potential subcontractors more comprehensively so as to determine their actual competency of executing the contract; ensuring close supervision of ongoing work; asking the subcontractor to provide weekly progress report; dividing the contract into milestones and ensuring that each milestone is approved before proceeding to the next one; improve communication, collaboration and cooperation between the builder and subcontractor (Tan, et al., 2017); ensuring that the subcontractor adopts an efficient quality assurance and control system; and ensuring that the subcontractor is aware of severe penalties in case of poor performance.
One strategy of preventing poor performance from happening again is to develop a monitoring plan. The monitoring should basically involve a follow up aimed at ensuring that the measures included in the action plan are implemented effectively. Key performance indicators should be determined and evaluated against the works done by the subcontractor. This will ensure that all works are done in accordance with the specifications, codes and standards in the contract documents thus preventing poor performance.
Below is a template that can be used to record a meeting between a builder and subcontractor about unsatisfactory performance, together with examples of agreed solutions
Poor Performance Meeting Template
Project name:
Project number:
Project location:
Subcontractor name:
Subcontract number:
Subcontract type:
Subcontract value:
Completion date:
Project progress (%):
Venue:
Date:
List of attendees:
Absent with apology:
Absent without apology:
List of agenda items: contract conditions; performance requirements; factors that contributed to poor performance; why the subcontractor failed to prevent these causes; effectiveness of quality assurance and control systems used by the subcontractor; effects of the poor performance; persons responsible for the poor performance; and action plan to prevent poor performance in the future.
List of agreed solutions: increase supervision of work; provide weekly progress report; evaluate performance of each milestone before proceeding to the next one; enhance communication and collaboration of stakeholders; use more efficient and effective quality control systems; develop ad adopt an efficient risk management plan; and ensure that all works are done in accordance with the requirements in the contract documents.
Next meeting date:
Signed by:
Builder (or representative): Date:
Subcontractor (or representative): Date:
Others: Date:
Every work performed by the subcontractor should be evaluated to determine if it has been done in accordance with the contract requirements. The performance of the subcontractor should be evaluated by the builder’s representative such as project manager, site manager, job supervisor or quality manager. The items to be considered when performing overall performance of the subcontractor include: personnel (number and qualifications), understanding of contract conditions, workplace health and safety (WHS), adherence to applicable standards and codes, workmanship quality, communication level (Assbeihat, 2018), collaboration and cooperation, consultation level, cost, completion speed, waste control, payment claims, non-compliance remedies, number of conflicts/disputes, innovativeness, and sustainability targets.
The template below can be used in evaluating the overall performance of a subcontractor. The aim of the evaluation is usually to determine areas where the subcontractor failed, factors that may have led to the failure and how to improve the performance moving forward.
Overall Subcontractor Performance Evaluation
Project name:
Project number:
Project location:
Subcontractor name:
Subcontract number:
Subcontract type:
Subcontract value:
Completion date:
Project progress (%):
Date:
Evaluation item |
Weight |
Score |
Remarks |
Personnel (number and qualifications) |
10 |
|
|
Understanding of contract conditions |
10 |
|
|
WHS |
10 |
|
|
Adherence to applicable standards and codes |
10 |
|
|
Quality of workmanship |
10 |
|
|
Level of communication |
10 |
|
|
Level of collaboration and cooperation |
10 |
|
|
Level of consultation |
10 |
|
|
Cost |
10 |
|
|
Completion speed |
10 |
|
|
Waste control |
10 |
|
|
Payment claims |
10 |
|
|
Non-compliance remedies |
10 |
|
|
Number of conflicts or disputes |
10 |
|
|
Innovativeness |
10 |
|
|
Sustainability targets |
10 |
|
|
Signed:
Builder (or representative): Date:
The outcome from this evaluation should be shared with the subcontractor because it will be useful in ensuring that the overall performance of the subcontractor is improved in the future.
The following are some of the items that have to be explained during site induction of contractors before actual commencement of project works: site layout, rules of the site, restricted areas, welfare facilities, traffic control plan, parking arrangement, signing in/out processes, site attendance reporting, communication protocol, signs and symbols, working hours, hazardous materials/substances, safety and health hazards, environmental protection, accident reporting processes, emergency procedures, evacuation procedures, fire assembly point, personal protective equipment, key personnel, representatives, behavior and conduct standards, disaster management, waste management, quality assurance and control, risk factors, work permits, professional qualifications, working at height, lone working, coordination, method statements, weekly and monthly reports, disputes and conflicts, early/late completion, and penalties, among others. The following paperwork should also be completed before the start of actual work: general and special conditions of contract, form of agreement, site information, works information, activities schedules, drawings, bill of quantities, etc. (Rodriguez, 2018).
Abbasianjahromi, H., Rajaie, H. & Shakeri, E., 2013. A Framework for Subcontractor Selection in the Construction Industry. Journal of Civil Engineering and Management, 19(2), pp. 158-168.
Abbasianjahromi, H., Rajaie, H., Shakeri, E. & Kazemi, O., 2016. A new approach for subcontractor selection in the construction industry based on portfolio theory. Journal of Civil Engineering and Management, 22(3), pp. 346-356.
Abbasianjahromi, H., Sepehri, M. & Abbasi, O., 2018. A Decision-Making Framework for Subcontractor Selection in Construction Projects. Engineering Management Journal, 30(2), pp. 141-152.
Akintan, O. & Morledge, R., 2013. Improving the Collaboration between Main Contractors and Subcontractors within Traditional Construction Procurement. Journal of Construction Engineering, Volume 2013, pp. 1-11.
Assbeihat, J., 2018. Reasons Behind Subcontractor's Defaults In Construction Projects. International Journal of Civil Engineering and Technology, 9(4), pp. 327-338.
Hartmann, A., Ling, F. & Tan, J., 2009. Relative important of subcontractor selection criteria: evidence from Singapore. Journal of Construction Engineering Management, 135(9), pp. 826-832.
Marzouk, M., El Kherbawy, A. & Khalifa, M., 2013. Factors influencing sub-contractors selection in construction projects. HBRC Journal, 9(2), pp. 150-158.
Ng, S. & Skitmore, M., 2014. Developing a framework for subcontractor appraisal using a balanced scorecard. Journal of Civil Engineering and Management, 20(2), pp. 149-158.
Polat, G., 2016. Subcontractor selection using the integration of the AHP and PROMETHEE methods. Journal of Civil Engineering and Management, 22(8), pp. 1042-1054.
Reyes-Martinez, G. & Chileshe, N., 2011. Effectiveness of communication between contractors and sub-contractors: Practices, barriers and enablers. Adelaide, University of South Australia.
Richards, L., 2018. Methods of Communication Within a Business. [Online]
Available at: https://smallbusiness.chron.com/methods-communication-within-business-2931.html
[Accessed 15 January 2019].
Rodriguez, J., 2018. 10 Essential Contract Documents for Every Construction Project. [Online]
Available at: https://www.thebalancesmb.com/contract-documents-for-every-construction-project-844919
[Accessed 15 January 2019].
Tan, Y., Xue, B. & Cheung, Y., 2017. Relationships between Main Contractors and Subcontractors and Their Impacts on Main Contractor Competitiveness: An Empirical Study in Hong Kong. Journal of Construction Engineering and Management, 143(7), pp. 1-12.
Ulubeyi, S., Kazaz, A. & Arslan, V., 2017. Decision Criteria for Subcontractor Selection in International Construction Projects. Merkez, Turkey, Bulent Ecevit University.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2020). Select And Manage Building And Construction Contractors. Retrieved from https://myassignmenthelp.com/free-samples/cpccbc5005a-select-and-manage-building-and-construction-contractors.
"Select And Manage Building And Construction Contractors." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/cpccbc5005a-select-and-manage-building-and-construction-contractors.
My Assignment Help (2020) Select And Manage Building And Construction Contractors [Online]. Available from: https://myassignmenthelp.com/free-samples/cpccbc5005a-select-and-manage-building-and-construction-contractors
[Accessed 25 February 2021].
My Assignment Help. 'Select And Manage Building And Construction Contractors' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/cpccbc5005a-select-and-manage-building-and-construction-contractors> accessed 25 February 2021.
My Assignment Help. Select And Manage Building And Construction Contractors [Internet]. My Assignment Help. 2020 [cited 25 February 2021]. Available from: https://myassignmenthelp.com/free-samples/cpccbc5005a-select-and-manage-building-and-construction-contractors.
For years, MyAssignmenthelp.com has been operating as one of the cheap assignment help providers in the USA. We are one of the best college paper writing services that keep service price minimal. We do not let the affordability of our service to hamper the standard of our work. We have separate teams of experts to provide report writing help . At MyAssigenmnthelp.com, we believe in earning credibility, so students can pay for assignments only after getting satisfied solutions. Tough assignments bother you? Trust us with your project. You will not regret paying us to write assignments for you.
Answer Building Regulation Studies: Fire Regulations 1. This statement means that every building in Australia must have certain components and design elements/factors and be constructed using high quality materials and by following specific procedures so as to meet particular functional and performance requirements of the Building Code of Australia (BCA), particularly fire safety requirements. For example, ceiling heights of habitable rooms i...
Read MoreAnswer: Introduction: Over the recent years, a number of critical success factors have been identified by the researchers with an increased focus on various aspects of stakeholder management. Presently, environmental expectation are paid a high attention by many scholars from stakeholders' management perspective. In this context, the research topic for this study is "Critical Success factors for Managing Stakeholders in Australian Const...
Read MoreAnswer Enterprise Systems Introduction Enterprise resource planning systems have provided many systems with business functions such as the optimization and the integration in the processes of the business which have led to making plans which are improved and quality decisions. This has further smoothened the coordination between the units of the business which have resulted to efficiency being high, quick response time especially when the cu...
Read MoreAnswer Enterprise Systems Objectives Venture frameworks (ESs) are difficult to keep up since they implant a vast portion of authoritative information and assignments, which are frequently interwoven and very associated. The reason for this paper is to propose a technique for big business asset arranging (ERP) present execution change administration to help business examiners amid perfective support. Key institutional features are shown, for ...
Read MoreAnswer Enterprise Architecture Tutorial 1 What are some of the differences between enterprise architecture (EA) and a systems-level planning approach? Enterprise architecture focuses on designing virtual things, which include organizational capabilities whereas system planning focuses solely on developing physical, tangible things. EA follows a standardized approach towards the accomplishment of the architecture program. It prov...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
I\'m very satisfied with my results. Really wasn\'t expecting my result would get almost a full mark. Would come back for ur service again in the future. Thanks for the help guys
Australia
I must appreciate the work as it has met all the requirement criteria as described in the order. Hope to score good marks??
Australia
the experts did a great job as usual. I was very pleased with the outcome and will use again
Australia
I love this I got a perfect score on my essay. Will for sure be using this again
Australia