WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Cost |
Resource Names |
0 |
Big Data Analytics |
186 days |
Thu 4/26/18 |
Thu 1/10/19 |
|
$86,472.00 |
|
1 |
Analytic Package Identification |
7 days |
Thu 4/26/18 |
Fri 5/4/18 |
|
$3,136.00 |
|
1.1 |
Hire Consultant |
1 day |
Thu 4/26/18 |
Thu 4/26/18 |
|
$280.00 |
Project Manager |
1.2 |
Identify Various Packages |
2 days |
Fri 4/27/18 |
Mon 4/30/18 |
2 |
$960.00 |
Consultant, Project Manager |
1.3 |
Evaluate the Packages |
2 days |
Tue 5/1/18 |
Wed 5/2/18 |
3 |
$1,248.00 |
Consultant, Project Manager, System Engineer |
1.4 |
Compare Packages |
1 day |
Thu 5/3/18 |
Thu 5/3/18 |
4 |
$304.00 |
System Analyst, System Engineer |
1.5 |
Select an Analytical Package |
1 day |
Fri 5/4/18 |
Fri 5/4/18 |
5 |
$344.00 |
Consultant, System Engineer |
2 |
Project Team Recruitment |
14 days |
Mon 5/7/18 |
Thu 5/24/18 |
|
$5,120.00 |
|
2.1 |
Identify the Activities |
3 days |
Mon 5/7/18 |
Wed 5/9/18 |
6 |
$840.00 |
Project Manager |
2.2 |
Identify the Roles and Responsibilities for Each Task |
2 days |
Thu 5/10/18 |
Fri 5/11/18 |
8 |
$960.00 |
Consultant, Project Manager |
2.3 |
Advertise the Job Opening |
2 days |
Mon 5/14/18 |
Tue 5/15/18 |
9 |
$560.00 |
Project Manager |
2.4 |
Appoint a HR |
1 day |
Wed 5/16/18 |
Wed 5/16/18 |
9 |
$280.00 |
Project Manager |
2.5 |
Interview the Applicants |
4 days |
Thu 5/17/18 |
Tue 5/22/18 |
11,10 |
$1,920.00 |
Consultant, Project Manager |
2.6 |
Select Skilled and Professional Applicants |
2 days |
Wed 5/23/18 |
Thu 5/24/18 |
12 |
$560.00 |
Project Manager |
2.7 |
Identify 10 Metrics for Defining Project Success |
0 days |
Thu 5/24/18 |
Thu 5/24/18 |
13 |
$0.00 |
|
3 |
Data Source Identification |
26 days |
Fri 5/25/18 |
Fri 6/29/18 |
|
$12,040.00 |
|
3.1 |
Identify the Audiences of the System |
3 days |
Fri 5/25/18 |
Tue 5/29/18 |
13 |
$1,560.00 |
Business Analyst, Consultant, System Engineer |
3.2 |
Identify the User Requirements |
5 days |
Wed 5/30/18 |
Tue 6/5/18 |
16 |
$1,680.00 |
Business Analyst, System Analyst |
3.3 |
Identify the Business Requirements |
8 days |
Wed 6/6/18 |
Fri 6/15/18 |
16 |
$1,408.00 |
Business Analyst |
3.4 |
Identify the Data Associated with Each Requirement |
12 days |
Wed 6/6/18 |
Thu 6/21/18 |
17 |
$3,648.00 |
System Analyst, System Engineer |
3.5 |
Identify Who or Which Process Input that Data into the System |
6 days |
Fri 6/22/18 |
Fri 6/29/18 |
19 |
$3,744.00 |
Consultant, Project Manager, System Engineer |
4 |
Platform Trial |
38 days |
Mon 7/2/18 |
Wed 8/22/18 |
|
$11,136.00 |
|
4.1 |
Contact Platform Vendor |
13 days |
Mon 7/2/18 |
Wed 7/18/18 |
20 |
$2,600.00 |
Consultant |
4.2 |
Application for Trial |
1 day |
Thu 7/19/18 |
Thu 7/19/18 |
22 |
$280.00 |
Project Manager |
4.3 |
Trail if Application Approved |
24 days |
Fri 7/20/18 |
Wed 8/22/18 |
23 |
$8,256.00 |
Consultant, System Engineer |
5 |
Stakeholder Agreement |
14 days |
Thu 8/23/18 |
Tue 9/11/18 |
|
$6,720.00 |
|
5.1 |
Attend Meeting with Stakeholder |
6 days |
Thu 8/23/18 |
Thu 8/30/18 |
24 |
$2,880.00 |
Consultant, Project Manager |
5.2 |
Inform Them about the Product |
6 days |
Fri 8/31/18 |
Fri 9/7/18 |
26 |
$2,880.00 |
Consultant, Project Manager |
5.3 |
Share Reports |
1 day |
Mon 9/10/18 |
Mon 9/10/18 |
26 |
$480.00 |
Consultant, Project Manager |
5.4 |
Sign Agreements |
1 day |
Tue 9/11/18 |
Tue 9/11/18 |
27,28 |
$480.00 |
Consultant, Project Manager |
6 |
Negotiation with Vendor |
29 days |
Wed 9/12/18 |
Mon 10/22/18 |
|
$6,568.00 |
|
6.1 |
Contact Vendor |
1 day |
Mon 9/24/18 |
Mon 9/24/18 |
29 |
$280.00 |
Project Manager |
6.2 |
Share Requirements |
2 days |
Tue 9/25/18 |
Wed 9/26/18 |
31 |
$1,248.00 |
Consultant, Project Manager, System Engineer |
6.3 |
Negotiate Product Cost |
7 days |
Thu 9/27/18 |
Wed 10/17/18 |
32 |
$1,960.00 |
Project Manager |
6.4 |
Buy License |
3 days |
Thu 10/18/18 |
Mon 10/22/18 |
32 |
$840.00 |
Project Manager |
6.5 |
Discuss External Data Sources |
8 days |
Wed 9/12/18 |
Fri 9/21/18 |
29 |
$2,240.00 |
Project Manager |
6.6 |
Report on the project update to the Stakeholders |
0 days |
Fri 9/21/18 |
Fri 9/21/18 |
35 |
$0.00 |
|
7 |
Gain Access to Internal Data Source |
79 days |
Mon 9/24/18 |
Thu 1/10/19 |
|
$18,176.00 |
|
7.1 |
Implement a System with Graphical Interface |
40 days |
Mon 9/24/18 |
Thu 12/27/18 |
35 |
$12,096.00 |
System Analyst, System Designer, System Developer, System Engineer |
7.2 |
Connect the System with Main System |
2 days |
Fri 12/28/18 |
Mon 12/31/18 |
38 |
$640.00 |
IT Department |
7.3 |
Authorization Level Determination |
6 days |
Thu 1/3/19 |
Thu 1/10/19 |
38 |
$1,920.00 |
IT Department |
7.4 |
Enable Data Access |
2 days |
Tue 1/1/19 |
Wed 1/2/19 |
39 |
$640.00 |
IT Department |
7.5 |
Implement Security Measures |
9 days |
Mon 9/24/18 |
Thu 10/4/18 |
35 |
$2,880.00 |
IT Department |
7.6 |
Create an Agreement with the users of new system regarding data theft and security violations and inform them about consequences |
0 days |
Thu 10/4/18 |
Thu 10/4/18 |
42 |
$0.00 |
|
8 |
Implement Analytical Solutions |
25 days |
Fri 10/5/18 |
Thu 11/8/18 |
|
$9,256.00 |
|
8.1 |
Identify Various Solutions |
8 days |
Fri 10/5/18 |
Tue 10/16/18 |
42 |
$4,992.00 |
Consultant, Project Manager, System Engineer |
8.2 |
Evaluate the Solutions |
5 days |
Wed 10/17/18 |
Tue 10/23/18 |
45 |
$720.00 |
System Engineer |
8.3 |
Select the Solutions best for Business Profit |
1 day |
Wed 10/24/18 |
Wed 10/24/18 |
46 |
$464.00 |
IT Department, System Engineer |
8.4 |
Calculate all the Cost of the Project |
5 days |
Thu 10/25/18 |
Wed 10/31/18 |
47 |
$1,400.00 |
Project Manager |
8.5 |
Identify the Profit from the Project for Next Five Years |
4 days |
Thu 11/1/18 |
Tue 11/6/18 |
48 |
$1,120.00 |
Project Manager |
8.6 |
Measure ROI |
2 days |
Wed 11/7/18 |
Thu 11/8/18 |
49 |
$560.00 |
Project Manager |
8.7 |
Attending a Meeting with the Stakeholders to Finalize all the factors associated with the project |
0 days |
Thu 11/8/18 |
Thu 11/8/18 |
50 |
$0.00 |
|
9 |
Training |
40 days |
Fri 11/9/18 |
Thu 1/3/19 |
|
$5,040.00 |
|
9.1 |
Create a User Manual |
10 days |
Fri 11/9/18 |
Thu 11/22/18 |
50 |
$2,160.00 |
System Engineer, System Administrator |
9.2 |
Train User |
14 days |
Fri 11/23/18 |
Wed 12/12/18 |
53 |
$1,344.00 |
System Administrator |
9.3 |
Train IT Maintenance Staff Every day |
14 days |
Thu 12/13/18 |
Tue 1/1/19 |
53 |
$1,344.00 |
System Administrator |
9.4 |
Distribute Manual |
2 days |
Wed 1/2/19 |
Thu 1/3/19 |
53 |
$192.00 |
System Administrator |
9.5 |
Introduce a test that will ensure every end user and staff is ready to use the system |
0 days |
Thu 1/3/19 |
Thu 1/3/19 |
56 |
$0.00 |
|
10 |
Go Live |
29 days |
Fri 11/9/18 |
Wed 12/19/18 |
|
$9,280.00 |
|
10.1 |
Deploy System within Intelligent Information Inc Environment |
1 day |
Fri 11/9/18 |
Fri 11/9/18 |
50 |
$464.00 |
IT Department, System Engineer |
10.2 |
Post Implementation Activities |
28 days |
Mon 11/12/18 |
Wed 12/19/18 |
59 |
$8,816.00 |
IT Department, System Engineer |
10.3 |
Make arrangement for a launch checklist. Each activity and task must be listed. Establishment of all the due dates. |
0 days |
Wed 12/19/18 |
Wed 12/19/18 |
60 |
$0.00 |
|
Figure 1: Gantt Chart
(Source: Created by Author)
Milestone 1: By 24th May, identify 10 Metrics for Defining Project Success
Milestone 2: By 4th October, create an Agreement with the users of new system regarding data theft and security violations and inform them about consequences
Milestone 3: By 8th November, attend a Meeting with the Stakeholders to Finalize all the factors associated with the project
Milestone 4: By 21st September, create report on the project update to the Stakeholders
Milestone 5: By 3rd January 2019, introduce a test that will ensure every end user and staff is ready to use the system
Milestone 6: By 19th December, make arrangement for a launch checklist. Each activity and task must be listed. Establishment of all the due dates.
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project Manager |
Work |
|
P |
|
100% |
$35.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Consultant |
Work |
|
C |
|
100% |
$25.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Business Analyst |
Work |
|
B |
|
100% |
$22.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Analyst |
Work |
|
S |
|
100% |
$20.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Developer |
Work |
|
S |
|
100% |
$14.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Designer |
Work |
|
S |
|
100% |
$11.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Engineer |
Work |
|
S |
|
100% |
$18.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Administrator |
Work |
|
S |
|
100% |
$12.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
IT Department |
Work |
|
I |
|
100% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Task Name |
Cost |
Big Data Analytics |
$86,472.00 |
Analytic Package Identification |
$3,136.00 |
Hire Consultant |
$280.00 |
Identify Various Packages |
$960.00 |
Evaluate the Packages |
$1,248.00 |
Compare Packages |
$304.00 |
Select an Analytical Package |
$344.00 |
Project Team Recruitment |
$5,120.00 |
Identify the Activities |
$840.00 |
Identify the Roles and Responsibilities for Each Task |
$960.00 |
Advertise the Job Opening |
$560.00 |
Appoint a HR |
$280.00 |
Interview the Applicants |
$1,920.00 |
Select Skilled and Professional Applicants |
$560.00 |
Identify 10 Metrics for Defining Project Success |
$0.00 |
Data Source Identification |
$12,040.00 |
Identify the Audiences of the System |
$1,560.00 |
Identify the User Requirements |
$1,680.00 |
Identify the Business Requirements |
$1,408.00 |
Identify the Data Associated with Each Requirement |
$3,648.00 |
Identify Who or Which Process Input that Data into the System |
$3,744.00 |
Platform Trial |
$11,136.00 |
Contact Platform Vendor |
$2,600.00 |
Application for Trial |
$280.00 |
Trail if Application Approved |
$8,256.00 |
Stakeholder Agreement |
$6,720.00 |
Attend Meeting with Stakeholder |
$2,880.00 |
Inform Them about the Product |
$2,880.00 |
Share Reports |
$480.00 |
Sign Agreements |
$480.00 |
Negotiation with Vendor |
$6,568.00 |
Contact Vendor |
$280.00 |
Share Requirements |
$1,248.00 |
Negotiate Product Cost |
$1,960.00 |
Buy License |
$840.00 |
Discuss External Data Sources |
$2,240.00 |
Report on the project update to the Stakeholders |
$0.00 |
Gain Access to Internal Data Source |
$18,176.00 |
Implement a System with Graphical Interface |
$12,096.00 |
Connect the System with Main System |
$640.00 |
Authorization Level Determination |
$1,920.00 |
Enable Data Access |
$640.00 |
Implement Security Measures |
$2,880.00 |
Create an Agreement with the users of new system regarding data theft and security violations and inform them about consequences |
$0.00 |
Implement Analytical Solutions |
$9,256.00 |
Identify Various Solutions |
$4,992.00 |
Evaluate the Solutions |
$720.00 |
Select the Solutions best for Business Profit |
$464.00 |
Calculate all the Cost of the Project |
$1,400.00 |
Identify the Profit from the Project for Next Five Years |
$1,120.00 |
Measure ROI |
$560.00 |
Attending a Meeting with the Stakeholders to Finalize all the factors associated with the project |
$0.00 |
Training |
$5,040.00 |
Create a User Manual |
$2,160.00 |
Train User |
$1,344.00 |
Train IT Maintenance Staff Every day |
$1,344.00 |
Distribute Manual |
$192.00 |
Introduce a test that will ensure every end user and staff is ready to use the system |
$0.00 |
Go Live |
$9,280.00 |
Deploy System within Intelligent Information Inc Environment |
$464.00 |
Post Implementation Activities |
$8,816.00 |
Make arrangement for a launch checklist. Each activity and task must be listed. Establishment of all the due dates. |
$0.00 |
Task Name |
Project Manager and Consultant |
IT Department |
Project Team |
Analyst |
Sys Admin |
Hire Consultant |
R |
A |
|
|
|
Identify Various Packages |
R |
A |
|
|
|
Evaluate the Packages |
I |
A |
R |
|
|
Compare Packages |
I |
A |
R |
|
|
Select an Analytical Package |
I |
C |
R |
|
|
Identify the Activities |
R |
C |
|
|
|
Identify the Roles and Responsibilities for Each Task |
R |
C |
|
|
|
Advertise the Job Opening |
R |
|
|
|
|
Appoint a HR |
R |
|
|
|
|
Interview the Applicants |
R |
|
|
|
|
Select Skilled and Professional Applicants |
R |
|
|
|
|
Identify the Audiences of the System |
I |
A |
|
R |
|
Identify the User Requirements |
I |
|
|
R |
|
Identify the Business Requirements |
I |
|
|
R |
|
Identify the Data Associated with Each Requirement |
I |
A |
|
R |
|
Identify Who or Which Process Input that Data into the System |
I |
A |
|
R |
|
Contact Platform Vendor |
R |
C |
I |
I |
|
Application for Trial |
R |
A |
|
|
|
Trail if Application Approved |
A |
R |
|
|
|
Attend Meeting with Stakeholder |
R |
|
|
I |
|
Inform Them about the Product |
R |
|
|
|
|
Share Reports |
R |
I |
|
|
|
Sign Agreements |
R |
|
|
|
|
Contact Vendor |
R |
A |
I |
I |
|
Share Requirements |
R |
A |
|
C |
|
Negotiate Product Cost |
R |
C |
|
|
|
Buy License |
R |
C |
|
|
|
Discuss External Data Sources |
R |
A |
|
C |
|
Implement a System with Graphical Interface |
A |
C |
R |
I |
|
Connect the System with Main System |
A |
R |
I |
|
|
Authorization Level Determination |
A |
R |
I |
|
|
Enable Data Access |
A |
R |
I |
|
|
Implement Security Measures |
A |
R |
I |
|
|
Identify Various Solutions |
I |
A |
R |
|
|
Evaluate the Solutions |
I |
R |
C |
|
|
Select the Solutions best for Business Profit |
R |
|
|
C |
|
Calculate all the Cost of the Project |
R |
|
|
C |
|
Identify the Profit from the Project for Next Five Years |
R |
C |
|
|
|
Measure ROI |
R |
I |
|
|
|
Create a User Manual |
A |
I |
C |
|
R |
Train User |
A |
I |
C |
|
R |
Train IT Maintenance Staff Every day |
A |
I |
C |
|
R |
Distribute Manual |
A |
I |
C |
|
R |
Go Live |
|
|
|
|
|
Deploy System within Intelligent Information Inc Environment |
I |
R |
|
R |
|
Post Implementation Activities |
A |
R |
|
R |
|
Name |
Description |
Impact |
Likelihood |
Mitigation Technique |
Type |
Risk Response |
Responsible Person |
Defining data storage and quality |
Intelligent Information Inc is growing rapidly. The amount of data, the organization collects, processes and produces are increasing day by day (Najafabadi et al. 2015). In big data environment, it is not easy to predict the amount of data storage requires. |
High |
Medium |
Risk Transfer |
Negative |
The project manager and consultant will define storage requirements which can possible meet the future data requirements of the organization. The project manager will contact with a data warehouse service provider for creating the data warehouse of the Big Data Analytic project. The third party vendors who are well established in their domain will be employed within the project for designing and developing the data storage. |
Risk manager and Consultant |
Delay of deadline |
The projects experiences issues, challenges and risk. Due to these negative factors, the project progress is affected and progress delays (Marcelino et al. 2014). The project managers generally design the tight project schedule to meet the demands of the project owner. However, in the long run, this becomes issue for both the project manager and owner. Completing a complex and big project like the proposed one is a very difficult and next to impossible. |
High |
Medium |
Risk Reduction |
Negative |
The project manager will identify all the tasks, no matter how small it is, related the project. The project manager will set potential duration of completing the task. The project manager will contact with the team members and study best practices for setting the duration. The manager will also consider the possible issues with the activities. |
Project Manager and Project Sponsor |
Lack of skills of team members |
The project being a complex one, requires professional and skilled personnel within the team members. Each of the team member must be able to understand their role and responsibilities. |
High |
Low |
Risk Avoidance |
Negative |
There is no way the project manager can allow having a team member who has lack of skills. The project manager and the HR will first find the activities that are linked to the project (Turner 2016). Then the skills, knowledge and expertise required for each task will be identified. The team members will be recruited as per defined skills and knowledge. They will hire only those expertise who has experience of participating in at least two Data Analytics Project. |
Project Manager and HR |
More Data Quality |
The big data will be used for enhancing the productivity, working efficiency and obtaining important insight of the business (Wehn and Evers 2015). The big data take only the correct data as input. The data linking is done precisely so that the data quality can be improved significantly. |
Extreme |
High |
Risk Acceptance |
Positive |
The project manager will try to contact the best warehouse designers and developers for the project. The analytics will identify all the business requirements and then define system requirements. The system engineer and system analyst will identify all the data required for supporting the requirements. These data will be properly documented and send to the warehouse developers. |
Project Manager, Analyst, System Engineer |
Lack of Stakeholder Support |
Stakeholder support is one of the main criteria to complete a project successfully. The stakeholders sanction the project resources, required capital, extension of delivery date and many more. Generally speaking, the stakeholders are capable of shutting down a project. It is extremely important that project manager always communicate with the stakeholders to inform them about the project progress |
Extreme |
High |
Risk Avoidance |
Negative |
It is preferable that both the stakeholders and project manager use a combination system that will allow them to video chat and file sharing (Duffield and Whitty 2015.). This way the project manager can be efficiently communicating with the stakeholders without leaving the project site. The project manager will attend meeting with the stakeholders once every week to share all the information. This not only allows the project manager to gain stakeholder support but also making significant decisions for the sake of the project. |
Project Manager |
The technical issues |
The technical issues are an inevitable part of an ICT project. As the proposed project is very complex and requires high class technical resources and supports, the project may face various issues in different parts of the SDLC, mainly in the development part. The newly developed application, designed for collecting internal data source, can face issues like malfunctioning, poor authorization and many more. |
Medium |
Low |
Risk Reduction |
Negative |
The project manager, consultant and system engineer will put sincere focus on selecting the technical equipment like hardware and software. The project will use only the quality products that has good reviews. The system will be tested properly before using for data collection process. |
Project Manager and Team Member |
Increase of ROI |
The project manager measures the return of investment by calculating the cost of the project and the profit system will deliver to the organization over a certain period of time (Kerzner and Kerzner 2017). The project may provide profit than expected and result in more return from the project than measured. It is obviously benefit for the organization. |
Extreme |
Low |
Risk acceptance |
Positive |
The project manager will try to cut off the cost of the different resources to make more reduce the project cost. The project manager will look for alternate solutions to various issues so that project management budget can be reduced. All the issues and findings will be communicated with the stakeholders so that they can have all the updated information about the project. This way project manager will have the support of the stakeholders to take extreme decisions for reducing the cost of the project. |
Project Manager and Project Sponsor |
Figure 2: Probability/ Impact Matrix
(Source: Created by Author)
Alexandrov, A., Bergmann, R., Ewen, S., Freytag, J.C., Hueske, F., Heise, A., Kao, O., Leich, M., Leser, U., Markl, V. and Naumann, F., 2014. The stratosphere platform for big data analytics. The VLDB Journal, 23(6), pp.939-964.
Duffield, S. and Whitty, S.J., 2015. Developing a systemic lessons learned knowledge model for organisational learning through projects. International journal of project management, 33(2), pp.311-324.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Hu, H., Wen, Y., Chua, T.S. and Li, X., 2014. Toward scalable systems for big data analytics: A technology tutorial. IEEE access, 2, pp.652-687.
JOSEPH. PHILLIPS, P.M.P., CBAP, I. and PMP, C., 2018. PMP PROJECT MANAGEMENT PROFESSIONAL STUDY GUIDE. McGraw-Hill Education.
Kambatla, K., Kollias, G., Kumar, V. and Grama, A., 2014. Trends in big data analytics. Journal of Parallel and Distributed Computing, 74(7), pp.2561-2573.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Marcelino-Sadaba, S., Perez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.
Najafabadi, M.M., Villanustre, F., Khoshgoftaar, T.M., Seliya, N., Wald, R. and Muharemagic, E., 2015. Deep learning applications and challenges in big data analytics. Journal of Big Data, 2(1), p.1.
Raghupathi, W. and Raghupathi, V., 2014. Big data analytics in healthcare: promise and potential. Health information science and systems, 2(1), p.3.
Rajaraman, V., 2016. Big data analytics. Resonance, 21(8), pp.695-716.
Riggins, F.J. and Wamba, S.F., 2015, January. Research directions on the adoption, usage, and impact of the internet of things through the use of big data analytics. In System Sciences (HICSS), 2015 48th Hawaii International Conference on (pp. 1531-1540). IEEE.
Singh, D. and Reddy, C.K., 2015. A survey on platforms for big data analytics. Journal of Big Data, 2(1), p.8.
Tsai, C.W., Lai, C.F., Chao, H.C. and Vasilakos, A.V., 2015. Big data analytics: a survey. Journal of Big Data, 2(1), p.21.
Turner, R., 2016. Gower handbook of project management. Routledge.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Wehn, U. and Evers, J., 2015. The social innovation potential of ICT-enabled citizen observatories to increase eParticipation in local flood risk management. Technology in Society, 42, pp.187-198.
Zakir, J., Seymour, T. and Berg, K., 2015. BIG DATA ANALYTICS. Issues in Information Systems, 16(2).
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2019). Developing A Systemic Lessons Learned Knowledge Model - Gantt Chart. Retrieved from https://myassignmenthelp.com/free-samples/developing-a-systemic-lessons-learned-knowledge-model.
"Developing A Systemic Lessons Learned Knowledge Model - Gantt Chart." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/developing-a-systemic-lessons-learned-knowledge-model.
My Assignment Help (2019) Developing A Systemic Lessons Learned Knowledge Model - Gantt Chart [Online]. Available from: https://myassignmenthelp.com/free-samples/developing-a-systemic-lessons-learned-knowledge-model
[Accessed 18 December 2024].
My Assignment Help. 'Developing A Systemic Lessons Learned Knowledge Model - Gantt Chart' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/developing-a-systemic-lessons-learned-knowledge-model> accessed 18 December 2024.
My Assignment Help. Developing A Systemic Lessons Learned Knowledge Model - Gantt Chart [Internet]. My Assignment Help. 2019 [cited 18 December 2024]. Available from: https://myassignmenthelp.com/free-samples/developing-a-systemic-lessons-learned-knowledge-model.