Project Charter refers to a statement of objectives in a project. This statement also sets out detailed project goals, roles and responsibilities, identifies the main stakeholders, and the level of authority of a project manager. It acts as a guideline for future projects as well as an important material in the organization's knowledge management system. You have been asked to develop a Project Charter for an upcoming project by your company’s top management. Your Project Charter shall include but are not limited to the following:
• Project Background
• Problem Statement
• Project Objectives & Goals
• Project Schedule/Milestone
• Risks involved with the project
• Project Costing and Budget
• Stakeholder’s roles and responsibilities of the participants involved
• Informed and effective communication plan
The company “Yehia Sushail & Bros Co.” is one of the retail companies of Yemen. The company was established in the year 1969 by the distributor of products as well as commodities. It generally started as one of the small retail shop and now the business of the company is expanding and therefore numbers of branches have opened in different place which generally surrounds market cities as well as areas for appropriate distribution and marketing of products. In addition to this, it is identified that the company also expanded its investment in other fields including exchange of foreign money, real estate investment and more.
It is identified that as the company is expanding andnumber of branches of the company has opened in different places, it’s become quite difficult for the higher authorities to handle all the branches of the company properly at one time. They are not able to access the data properly and as a result they have to visit every branch in order to collect information. In order to resolve this problem, the higher authority of the organization wants to develop cloud based ERP so that an individual can easily access the data of different branches at one time irrespective of time and place. In addition to this, development of cloud based ERP helps in enhancing flexibility, scalability, support as well as assists in enhancing security.
The objectives of the project are as follows:
- To develop cloud based ERP system within the company Yehia Sushail& Bros Co
- To resolve the issues that the company is facing
- To handle the entire operation of the company effectively
The main goal of the company “Yehia Sushail & Bros Co” is to develop cloud based ERP system within the organization in order to resolve the issues that the higher authorities of the company facing in managing all the branches of the company effectively. In addition to this, they also wants to opt for cloud based ERP as it helps in enhancing flexibility as well as scalability of the business operation.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Development of Cloud based ERP system in Yehia Sushail & Bros Co. |
41 days |
Mon 01-01-18 |
Mon 26-02-18 |
||
Initiation phase |
14 days |
Mon 01-01-18 |
Thu 18-01-18 |
||
Developing business case |
4 days |
Mon 01-01-18 |
Thu 04-01-18 |
Project planner, Project manager |
|
Undertaking feasibility study |
4 days |
Fri 05-01-18 |
Wed 10-01-18 |
2 |
Financial manager |
Establishing project charter |
5 days |
Fri 05-01-18 |
Thu 11-01-18 |
2 |
Project planner |
Appointing team members of the project |
6 days |
Thu 11-01-18 |
Thu 18-01-18 |
3 |
Project planner, Project manager |
Planning phase |
13 days |
Thu 11-01-18 |
Mon 29-01-18 |
||
Creating project panning |
5 days |
Fri 12-01-18 |
Thu 18-01-18 |
4 |
Project planner, Supervisor |
Creating resource planning |
7 days |
Fri 12-01-18 |
Mon 22-01-18 |
4 |
Project planner,Financial manager, Human resource manager |
Creating financial plan |
6 days |
Fri 19-01-18 |
Fri 26-01-18 |
5 |
Project planner,Financial manager |
Creating quality plan |
5 days |
Fri 19-01-18 |
Thu 25-01-18 |
5 |
Supervisor,Financial manager, Risk analyst |
Creating risk plan |
7 days |
Thu 11-01-18 |
Fri 19-01-18 |
6 |
Risk analyst, Tester |
Creating acceptance plan |
6 days |
Thu 11-01-18 |
Thu 18-01-18 |
6 |
Project planner, Supervisor |
Creating communication plan |
5 days |
Fri 19-01-18 |
Thu 25-01-18 |
8 |
Project planner, Supervisor |
Creating procurement plan |
7 days |
Fri 19-01-18 |
Mon 29-01-18 |
8 |
Project planner, Supervisor,Financial manager |
Execution phase |
24 days |
Fri 19-01-18 |
Wed 21-02-18 |
||
Analyzing business needs |
15 days |
Tue 23-01-18 |
Mon 12-02-18 |
9 |
Supervisor, Database manager, Human resource manager |
Selection of cloud based ERP system |
12 days |
Mon 29-01-18 |
Tue 13-02-18 |
10 |
Supervisor, Technical engineer |
Work customization |
15 days |
Fri 26-01-18 |
Thu 15-02-18 |
11 |
Risk analyst, Technical engineer, Project planner |
Data migration |
16 days |
Mon 22-01-18 |
Mon 12-02-18 |
12 |
Database manager, Technical engineer, Tester |
Checking infrastructure |
17 days |
Mon 22-01-18 |
Tue 13-02-18 |
12 |
Supervisor, Risk analyst, Technical engineer, Tester |
Customization |
19 days |
Fri 19-01-18 |
Wed 14-02-18 |
13 |
Database manager, Project manager, Technical engineer |
Change management |
18 days |
Fri 19-01-18 |
Tue 13-02-18 |
13 |
Project planner, Supervisor, Database manager, Risk analyst, Technical engineer |
Technology and knowledge transfer |
17 days |
Fri 26-01-18 |
Mon 19-02-18 |
14 |
Supervisor, Database manager, Risk analyst, Technical engineer |
Testing project management |
15 days |
Fri 26-01-18 |
Thu 15-02-18 |
14 |
Risk analyst, Tester |
System integration testing |
16 days |
Tue 30-01-18 |
Tue 20-02-18 |
15 |
Supervisor, Database manager, Technical engineer |
User acceptance testing |
17 days |
Tue 30-01-18 |
Wed 21-02-18 |
15 |
Supervisor, Technical engineer |
Closing phase |
27 days |
Fri 19-01-18 |
Mon 26-02-18 |
||
Post project review |
3 days |
Fri 19-01-18 |
Tue 23-01-18 |
16 |
Project planner |
Stakeholder sign off |
3 days |
Thu 22-02-18 |
Mon 26-02-18 |
17 |
Project manager |
Post go-live support |
3 days |
Tue 13-02-18 |
Thu 15-02-18 |
18 |
Project planner |
Task Name |
End Date |
Milestone 1: Completion of initiation phase |
Wed 10-01-18 |
Milestone 2: Completion of planning phase |
Thu 18-01-18 |
Milestone 3: Completion of execution phase |
Mon 29-01-18 |
Milestone 4: Completion of closure phase |
Mon 12-02-18 |
Risks |
Description |
Impact |
Likelihood |
Mitigation measures |
Unauthorized access |
If proper authentication method is not used then unauthorized users can access the data from the database of the company which can create number of issues as well as challenges for the organization |
High |
High |
Proper authentication procedure must be utilized so that only authorized users can be able to access the data of the company. |
Hacking |
The important data as well as information from the cloud can be hacked by hackers therefore proper security must be provided so that the data as well as information of the organization remains secure from hacking. |
High |
High |
In order to resolve the challenges or issues that are associated with hacking, the organization needs to provide proper security so that hacking of data from the clod will be difficult and thus the information as well as data related with the company will be securely stored. |
Improper budget estimation |
If the budget of the project is not estimated properly then it will be quite difficult for the project manager to complete the entire project within the budget that is estimated. In addition to this, additional need of budget creates financial pressure on the company |
Medium |
High |
It is quite important to estimate the budget of the project properly. Proper estimation must be done by analyzing the market properly. |
Improper management |
If the project managers are not experienced then they are not able to manage the project effectively and as result the project will not be completed within the estimated budget as well as time. |
Medium |
Medium |
In order to complete the project successfully within estimated time and budget, proper management is quite necessary and in order to manage the project, it is quite important to hire experienced project manager. It is identified that experience project manager will be able to handle to project work quite effectively. |
Inaccurate allocation of resources |
If the resources of the project are not allocated properly between the various activities of the project then the project will face number of obstruction in its progress. Therefore proper as well as equal resource allocation is quite important in order to successfully complete the entire project within the estimated budget as well as time. |
Medium |
Medium |
It is quite important for the project manager to understand the needs as well as requirements of the project properly so that resources of the project will be allocated appropriately. |
Task Name |
Cost |
Development of Cloud based ERP system in YehiaSushail& Bros Co. |
?.?. 179,440.00 |
Initiation phase |
?.?. 8,200.00 |
Developing business case |
?.?. 2,400.00 |
Undertaking feasibility study |
?.?. 800.00 |
Establishing project charter |
?.?. 1,400.00 |
Appointing team members of the project |
?.?. 3,600.00 |
Planning phase |
?.?. 28,040.00 |
Creating project panning |
?.?. 2,600.00 |
Creating resource planning |
?.?. 5,040.00 |
Creating financial plan |
?.?. 2,880.00 |
Creating quality plan |
?.?. 3,400.00 |
Creating risk plan |
?.?. 3,360.00 |
Creating acceptance plan |
?.?. 3,120.00 |
Creating communication plan |
?.?. 2,600.00 |
Creating procurement plan |
?.?. 5,040.00 |
Execution phase |
?.?. 140,560.00 |
Analyzing business needs |
?.?. 11,400.00 |
Selection of cloud based ERP system |
?.?. 5,760.00 |
Work customization |
?.?. 11,400.00 |
Data migration |
?.?. 12,160.00 |
Checking infrastructure |
?.?. 16,320.00 |
Customization |
?.?. 15,960.00 |
Change management |
?.?. 23,040.00 |
Technology and knowledge transfer |
?.?. 17,000.00 |
Testing project management |
?.?. 7,200.00 |
System integration testing |
?.?. 12,160.00 |
User acceptance testing |
?.?. 8,160.00 |
Closing phase |
?.?. 2,640.00 |
Post project review |
?.?. 840.00 |
Stakeholder sign off |
?.?. 960.00 |
Post go-live support |
?.?. 840.00 |
Stakeholders |
Roles and responsibilities |
Project manager |
Project manager is a person who takes the entire responsibility of properly initiating, designing planning, executing, monitoring as well as closing the entire project. They are mainly responsible of making decisions and assists in controlling risks as well as minimizing uncertainty within the project. In addition to this, the project manager helps in organizing as well as motivating a project team so that they can easily stimulate the project team for reaching their full potential. |
Project planner |
A project planner is the person who generally works with project team in planning as well as tracking cost as well as time for the project. They mainly work with different proposal writers for estimating cost of the project. Moreover, they also engage with clients as well as project manager for establishing the cost of the project so that the project can be successfully completed within the estimated time. |
Database manager |
Database manager is the person who generally prepares as well as manages the information as well as data by studying requirements and plans. They also upgrade software as well as hardware by assessing the entire transaction. Additionally, they also engages in updating job knowledge by participating in various educational opportunities, maintaining personal networks as well as participates in various professional works. |
Supervisor |
A supervisor is the person who is mainly responsible of managing day to day work of the project. They generally help the project team in understand performance, goals as well as targets. They mainly involve in scheduling work hours and helps in training workers so that they can perform their roles properly for completing the project successfully. Additionally it is identified that supervisors have excellent grasp of the work as well as team in order to understand the project tasks as well as activities of the project manager. |
Human resource manager |
The human resource manager helps in guiding and managing the overall provision of the resource services, policies as well as programs of a company. They mainly engage in staffing, recruiting, managing resources, as well as assists in handling the performance of the company. |
Risk analyst |
Risk analyst are the persons who are mainly responsible of evaluating the risk in the project by forecasting potential losses as well as challenges and decides procedures or mitigation techniques that are helpful in resolving the issues as well as challenges of the project. They also engages in reviewing various risk factors including problems and also predict future trends from the current developments in the market in order to provide proper recommendation to the management for planning strategies for resolving project risks. |
Financial manager |
Financial managers are the people who are generally responsible of maintaining the financial health of the organization. They generally engage in producing financial reports, direct investment as well as develop strategies as well as plans for the long term goals of the organization. They prepare financial statements, business activities and monitor the finances of the entire project. In addition to this, they also analyze market trends to find new opportunities for expanding or acquiring other functions. |
Tester |
The tester engages in reviewing and contributing the test plans of the project in order to analyze, review as well as assess various requirements for designing different specifications. They also engages in understanding software requirements, deriving test scenarios, updating traceability, collecting data as well as executes test cases. In addition to this, they also monitor the testing environment in order tools for gathering performance metrics. |
Technical engineer |
Technical engineer is the person who mainly engages in providing technical support to the engineering team of the organization in various executive projects. They also engage in developing various types of preventive measures in recurring problems as well as issues. In addition to this, they also co-ordinate with various other technicians to develop various types of designs in order to develop the project successfully within the estimated budget as well as time. |
Description |
Type |
Target |
Delivery Method |
Delivery frequency |
Responsible |
Project status (Information about the status of the project must be informed to the project manager so that they can make sure that the project is on the right track |
Mandatory |
Project manager and Sponsors |
|
Monthly |
Team members |
Resource allocation (Information about allocation of resources must be properly discussed so that resources of the project are properly allocated |
Informational |
Team members |
Conference, email |
As required |
Project manager |
Project risk (the risks about the project must be discussed by the project manager so that they can easily find some steps to resolve the problems so that the progress of the project will not be obstructed.) |
Informational |
Project manager |
|
Monthly |
Team leaders |
Training requirement (the team leaders must discuss about the need of training within the organization so that they can be able to complete the project within the estimated budget and time. |
Informational |
Team leaders |
Email, conference |
Monthly |
Project managers |
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.
Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), 272-284.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd..
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Pemsel, S., & Wiewiora, A. (2013). Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Turner, R. (2016). Gower handbook of project management. Routledge.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2020). Yehia Sushail & Bros Co: Cloud-based ERP Development Essay.. Retrieved from https://myassignmenthelp.com/free-samples/empm5203-project-management-for-erp-system-in-yehia-sushail.
"Yehia Sushail & Bros Co: Cloud-based ERP Development Essay.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/empm5203-project-management-for-erp-system-in-yehia-sushail.
My Assignment Help (2020) Yehia Sushail & Bros Co: Cloud-based ERP Development Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/empm5203-project-management-for-erp-system-in-yehia-sushail
[Accessed 22 December 2024].
My Assignment Help. 'Yehia Sushail & Bros Co: Cloud-based ERP Development Essay.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/empm5203-project-management-for-erp-system-in-yehia-sushail> accessed 22 December 2024.
My Assignment Help. Yehia Sushail & Bros Co: Cloud-based ERP Development Essay. [Internet]. My Assignment Help. 2020 [cited 22 December 2024]. Available from: https://myassignmenthelp.com/free-samples/empm5203-project-management-for-erp-system-in-yehia-sushail.