Question:
Discuss about the Scope and Time Management Plans.
The project report is prepared for St. Dismas medical Center for the identification of the goals and objectives of the project. The project is developed for construction of a medical health center with all the modern treatment facility. The report consists of the scope stamen tent of the project and the work break down structure used for dividing the project into smaller manageable compounds and reduce the errors in the project. A schedule is created for the project for the estimation of the time line and the budget and it is followed for completion of the project successfully.
The project is prepared for St. Dismas Medical center for solving the current problem faced by the organization and help the organization to gain measurable profit. The main issues identified in the business case is the management of the admission rates and refurbishment of the current building infrastructure. The main goal of the company is the implementation of functional operational changes in the current business process for meeting the expected outcomes of the business.
The objectives identified for the development of the project are listed below:
- To renovate the current building of the office within the budget estimated
- To analyze the current requirement and the schedule for arrangement of meetings and make the requirement clear
- The identify the hardware and the software required for the development of the project
The project is developed by focusing on the different action that is required for the construction of the building. The project manager should monitor the progress of the project for completing it within the proposed budget and the time. A proper survey should be conducted for analysis of the market condition and the creating a list of resource required for the completion of the project. The services that should be provided and the technology that can be used for the project should be analyzed for reducing the errors in the project and reduce the effort off the development team. There are different assessment tools that can be used for accessing the requirement and meeting must be arranged with the medical representative for identification of the medical needs.
The work breakdown structure of the project is created for dividing the schedule into manageable component and assign roles and responsibility for the management of the task. The work break down structure helps the stakeholders to find the roles and responsibility they are assigned to the project and follow it for the development of the project.
For the development of the project schedule the main resources identified are the Chief Finance Officer (CFO), Marketing Vice President (VP), the construction project manager and Chief Legal Council (CLC). For increasing the accuracy of the project development the responsibility is needed to be assigned and the progress must be monitored for the completion of each of the activity in time.
Task Name |
Duration |
Start |
Construction project schedule |
377 days |
Mon 09-04-18 |
Project initiation |
76 days |
Mon 09-04-18 |
Furnishing & Construction |
3 days |
Mon 09-04-18 |
Facility in construction |
4 days |
Thu 12-04-18 |
Foundation and excavation (basement/1st floor slab) |
10 days |
Wed 18-04-18 |
Structure (steel/framing) |
4 days |
Wed 02-05-18 |
Interiors (drywall/ceiling/flooring/case goods) |
7 days |
Tue 08-05-18 |
units ready for occupancy preparation (light assisted) |
6 days |
Thu 17-05-18 |
First 45 units ready for residents |
7 days |
Fri 25-05-18 |
Remaining (light & heavy) 57 units ready for preparation of occupancy |
3 days |
Tue 05-06-18 |
Construction complete |
4 days |
Fri 08-06-18 |
residential planning |
5 days |
Thu 14-06-18 |
Building ready for residents |
8 days |
Thu 14-06-18 |
Requirements for Licensing and Legal authorization |
4 days |
Tue 26-06-18 |
Research licensing requirements for residential care facility |
7 days |
Mon 02-07-18 |
Uniform accessibility standard compliance (# handicap accessible beds) |
5 days |
Wed 11-07-18 |
Investigate law firm and outline services |
4 days |
Wed 18-07-18 |
Project planning |
97 days |
Tue 24-07-18 |
Preparation of project plan for getting license |
4 days |
Tue 24-07-18 |
File license — by opening date |
7 days |
Mon 30-07-18 |
(Access to country Rd.) Curb - cut approval from the county |
8 days |
Wed 08-08-18 |
Investigating the corporate structure for assisted in living |
5 days |
Wed 08-08-18 |
Determination of membership for Board of Trustee |
2 days |
Wed 15-08-18 |
Appointment of Board of Trustees |
3 days |
Fri 17-08-18 |
Preparation of draft Code for Regulation |
6 days |
Wed 22-08-18 |
Preparation of document and filing for governance structure |
3 days |
Thu 30-08-18 |
48 Arrangement of Draft service with St. Dismas enlisting the services provided |
4 days |
Tue 04-09-18 |
Lease issues |
7 days |
Mon 10-09-18 |
Research on requirements for Long Term Care insurance |
5 days |
Mon 10-09-18 |
Facility “rules” defined (i.e., smoking, fi rearms, pets, financial planning) |
5 days |
Mon 17-09-18 |
Spell out changes for residents in moving from “light” to “heavy” assisted |
8 days |
Mon 24-09-18 |
Preparation of Lease template |
7 days |
Thu 04-10-18 |
Checking compliance of all marketing materials |
2 days |
Mon 15-10-18 |
Planning for Operational Implementation |
7 days |
Wed 17-10-18 |
Management/ Organization structure |
4 days |
Fri 26-10-18 |
Recruitment & hiring of Executive Director |
6 days |
Fri 26-10-18 |
Analyzing Interior design issues (furnishings, etc.) |
3 days |
Mon 05-11-18 |
Determination of lease and furnished details of the units |
5 days |
Thu 08-11-18 |
Determination of interior budget |
8 days |
Thu 15-11-18 |
Determination of Carpet and wall finish |
4 days |
Tue 27-11-18 |
Furniture and room layout |
7 days |
Tue 27-11-18 |
Other planning development |
60 days |
Thu 06-12-18 |
Facility and equipment needs defined |
5 days |
Thu 06-12-18 |
Staffing determined |
7 days |
Thu 13-12-18 |
Office space for physicians |
6 days |
Mon 24-12-18 |
Determination of 66 Medical staffing needs & appointment of directors |
5 days |
Mon 24-12-18 |
Food service |
7 days |
Tue 01-01-19 |
Selection of menus |
4 days |
Thu 10-01-19 |
Determination of Waiting and service staffing needs |
8 days |
Wed 16-01-19 |
Analysis of additional equipment |
4 days |
Mon 28-01-19 |
Deployment of telecommunications services |
7 days |
Mon 28-01-19 |
Investigation on options of phone service |
4 days |
Wed 06-02-19 |
Certification/ Accreditation requirements |
4 days |
Tue 12-02-19 |
Investigation on the timing & requirements of the applicants |
8 days |
Mon 18-02-19 |
Development phase |
40 days |
Thu 28-02-19 |
Development of clinical and operational quality monitoring systems |
3 days |
Thu 28-02-19 |
Develop financial systems (billing, etc.) |
4 days |
Tue 05-03-19 |
Human resources |
7 days |
Mon 11-03-19 |
Work force management recommendations |
7 days |
Wed 20-03-19 |
Project plan for recruitment developed |
6 days |
Wed 20-03-19 |
Policies and procedures developed |
4 days |
Thu 28-03-19 |
Obtain ‘samples’ of assisted living policies and procedure from other institutions |
5 days |
Wed 03-04-19 |
Investigate assisted living laws proposed |
4 days |
Wed 10-04-19 |
other states/federal consideration |
7 days |
Tue 16-04-19 |
Legal regulation consideration |
61 days |
Thu 25-04-19 |
Technology & information systems |
4 days |
Thu 25-04-19 |
Develop plan for technology access for residents (TV, Cable, PC ’ s) |
7 days |
Wed 01-05-19 |
Investigate software/technology options |
8 days |
Fri 10-05-19 |
Marketing planning phase |
5 days |
Fri 10-05-19 |
Marketing |
2 days |
Wed 22-05-19 |
Emailing the community for the construction project |
7 days |
Fri 24-05-19 |
Arrangement of informal meetings |
6 days |
Fri 17-05-19 |
Volunteers of St. Dismas |
4 days |
Mon 27-05-19 |
Group of community |
3 days |
Fri 31-05-19 |
St. Dismas staff (all shifts) |
5 days |
Wed 05-06-19 |
Preparation of presentation for Speaker’s Bureau |
14 days |
Wed 12-06-19 |
Updating the community |
8 days |
Tue 02-07-19 |
Establishment of enquiry log |
4 days |
Fri 12-07-19 |
Groundbreaking ceremony — during National Hospital |
5 days |
Fri 12-07-19 |
Marketing plan developed and implementation |
31 days |
Fri 19-07-19 |
Establishment of contract with the PR firm |
7 days |
Fri 19-07-19 |
Development of the marketing plan |
4 days |
Tue 30-07-19 |
Determination of the name and sign for implementation of facility |
5 days |
Tue 30-07-19 |
Hiring of Marketing Director |
8 days |
Tue 06-08-19 |
Implementation of marketing plan |
7 days |
Fri 16-08-19 |
Implementation of marketing plan |
4 days |
Tue 27-08-19 |
Project closure phase |
12 days |
Mon 02-09-19 |
stakeholders signoff |
4 days |
Mon 02-09-19 |
Final project documentation |
5 days |
Fri 06-09-19 |
Post project maintenance planning |
3 days |
Fri 13-09-19 |
Conclusion
From the above report it can be concluded that the project management methodology is required to be followed by the project manager for the development of the project and delivering it on the proposed time and the budget. The requirement of the St. Dismal Medical Center project should be clearly understood for reducing the errors in the project. The construction of the new building for the accommodation of the patients and implementation of new technology for increasing the efficiency of the treatment procedure must be managed for the completion of the task. The finance manager should control the flow of the cash and estimate the investment for calculating the return of investment on the project.
Alexiou, S., 2017, April. How an impact plan can build on the success of your project-from proposal to legacy. In EGU General Assembly Conference Abstracts (Vol. 19, p. 14635).
Fellows, R.F. and Liu, A.M., 2015. Research methods for construction. John Wiley & Sons.
Parks, M., 2016. Project Proposal: The Effect of Semantics on Word Order.
Thamhain, H.J., 2014. Assessing the effectiveness of quantitative and qualitative methods for R&D project proposal evaluations. Engineering Management Journal, 26(3), pp.3-12.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Yet, B., Constantinou, A., Fenton, N., Neil, M., Luedeling, E. and Shepherd, K., 2016. A Bayesian network framework for project cost, benefit and risk analysis with an agricultural development case study. Expert Systems with Applications, 60, pp.141-155.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2019). Project Essay For St. Dismas Medical Center.. Retrieved from https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.
"Project Essay For St. Dismas Medical Center.." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.
My Assignment Help (2019) Project Essay For St. Dismas Medical Center. [Online]. Available from: https://myassignmenthelp.com/free-samples/scope-and-time-management-plans
[Accessed 24 November 2024].
My Assignment Help. 'Project Essay For St. Dismas Medical Center.' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/scope-and-time-management-plans> accessed 24 November 2024.
My Assignment Help. Project Essay For St. Dismas Medical Center. [Internet]. My Assignment Help. 2019 [cited 24 November 2024]. Available from: https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.