Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave
Project Goals and Objectives

Question:

Discuss about the Scope and Time Management Plans.

The project report is prepared for St. Dismas medical Center for the identification of the goals and objectives of the project. The project is developed for construction of a medical health center with all the modern treatment facility. The report consists of the scope stamen tent of the project and the work break down structure used for dividing the project into smaller manageable compounds and reduce the errors in the project. A schedule is created for the project for the estimation of the time line and the budget and it is followed for completion of the project successfully. 

The project is prepared for St. Dismas Medical center for solving the current problem faced by the organization and help the organization to gain measurable profit. The main issues identified in the business case is the management of the admission rates and refurbishment of the current building infrastructure. The main goal of the company is the implementation of functional operational changes in the current business process for meeting the expected outcomes of the business.

The objectives identified for the development of the project are listed below:

  • To renovate the current building of the office within the budget estimated
  • To analyze the current requirement and the schedule for arrangement of meetings and make the requirement clear
  • The identify the hardware and the software required for the development of the project

The project is developed by focusing on the different action that is required for the construction of the building. The project manager should monitor the progress of the project for completing it within the proposed budget and the time. A proper survey should be conducted for analysis of the market condition and the creating a list of resource required for the completion of the project. The services that should be provided and the technology that can be used for the project should be analyzed for reducing the errors in the project and reduce the effort off the development team. There are different assessment tools that can be used for accessing the requirement and meeting must be arranged with the medical representative for identification of the medical needs.

The work breakdown structure of the project is created for dividing the schedule into manageable component and assign roles and responsibility for the management of the task. The work break down structure helps the stakeholders to find the roles and responsibility they are assigned to the project and follow it for the development of the project.

For the development of the project schedule the main resources identified are the Chief Finance Officer (CFO), Marketing Vice President (VP), the construction project manager and Chief Legal Council (CLC). For increasing the accuracy of the project development the responsibility is needed to be assigned and the progress must be monitored for the completion of each of the activity in time. 

Task Name

Duration

Start

Construction project schedule

377 days

Mon 09-04-18

   Project initiation

76 days

Mon 09-04-18

      Furnishing & Construction

3 days

Mon 09-04-18

      Facility in construction

4 days

Thu 12-04-18

      Foundation and excavation (basement/1st floor slab)

10 days

Wed 18-04-18

       Structure (steel/framing)

4 days

Wed 02-05-18

      Interiors (drywall/ceiling/flooring/case goods)

7 days

Tue 08-05-18

       units ready for occupancy preparation (light assisted)

6 days

Thu 17-05-18

       First 45 units ready for residents

7 days

Fri 25-05-18

      Remaining (light & heavy) 57 units ready for preparation of occupancy

3 days

Tue 05-06-18

      Construction complete

4 days

Fri 08-06-18

      residential planning

5 days

Thu 14-06-18

      Building ready for residents

8 days

Thu 14-06-18

       Requirements for Licensing and Legal authorization

4 days

Tue 26-06-18

      Research licensing requirements for residential care facility

7 days

Mon 02-07-18

      Uniform accessibility standard compliance (# handicap accessible beds)

5 days

Wed 11-07-18

      Investigate law firm and outline services

4 days

Wed 18-07-18

   Project planning

97 days

Tue 24-07-18

      Preparation of project plan for getting license

4 days

Tue 24-07-18

      File license — by opening date

7 days

Mon 30-07-18

      (Access to country Rd.) Curb - cut approval from the county

8 days

Wed 08-08-18

      Investigating the corporate structure for assisted in living

5 days

Wed 08-08-18

      Determination of membership for Board of Trustee

2 days

Wed 15-08-18

      Appointment of Board of Trustees

3 days

Fri 17-08-18

      Preparation of draft Code for Regulation

6 days

Wed 22-08-18

      Preparation of document and filing for governance structure

3 days

Thu 30-08-18

      48 Arrangement of Draft service with St. Dismas enlisting the services provided

4 days

Tue 04-09-18

      Lease issues

7 days

Mon 10-09-18

      Research on requirements for Long Term Care insurance

5 days

Mon 10-09-18

      Facility “rules” defined (i.e., smoking, fi rearms, pets, financial planning)

5 days

Mon 17-09-18

      Spell out changes for residents in moving from “light” to “heavy” assisted

8 days

Mon 24-09-18

      Preparation of Lease template

7 days

Thu 04-10-18

      Checking compliance of all marketing materials

2 days

Mon 15-10-18

      Planning for Operational Implementation

7 days

Wed 17-10-18

      Management/ Organization structure

4 days

Fri 26-10-18

      Recruitment & hiring of Executive Director

6 days

Fri 26-10-18

      Analyzing Interior design issues (furnishings, etc.)

3 days

Mon 05-11-18

      Determination of lease and furnished details of the units

5 days

Thu 08-11-18

      Determination of interior budget

8 days

Thu 15-11-18

      Determination of Carpet and wall finish

4 days

Tue 27-11-18

      Furniture and room layout

7 days

Tue 27-11-18

   Other planning development

60 days

Thu 06-12-18

      Facility and equipment needs defined

5 days

Thu 06-12-18

      Staffing determined

7 days

Thu 13-12-18

      Office space for physicians

6 days

Mon 24-12-18

      Determination of 66 Medical staffing needs & appointment of directors

5 days

Mon 24-12-18

      Food service

7 days

Tue 01-01-19

      Selection of menus

4 days

Thu 10-01-19

      Determination of Waiting and service staffing needs

8 days

Wed 16-01-19

      Analysis of additional equipment

4 days

Mon 28-01-19

      Deployment of telecommunications services

7 days

Mon 28-01-19

       Investigation on options of phone service

4 days

Wed 06-02-19

      Certification/ Accreditation requirements

4 days

Tue 12-02-19

      Investigation on the timing & requirements of the applicants

8 days

Mon 18-02-19

   Development phase

40 days

Thu 28-02-19

      Development of clinical and operational quality monitoring systems

3 days

Thu 28-02-19

      Develop financial systems (billing, etc.)

4 days

Tue 05-03-19

      Human resources

7 days

Mon 11-03-19

      Work force management recommendations

7 days

Wed 20-03-19

      Project plan for recruitment developed

6 days

Wed 20-03-19

      Policies and procedures developed

4 days

Thu 28-03-19

      Obtain ‘samples’ of assisted living policies and procedure from other institutions

5 days

Wed 03-04-19

      Investigate assisted living laws proposed

4 days

Wed 10-04-19

      other states/federal consideration

7 days

Tue 16-04-19

   Legal regulation consideration

61 days

Thu 25-04-19

      Technology & information systems

4 days

Thu 25-04-19

      Develop plan for technology access for residents (TV, Cable, PC ’ s)

7 days

Wed 01-05-19

      Investigate software/technology options

8 days

Fri 10-05-19

      Marketing planning phase

5 days

Fri 10-05-19

      Marketing

2 days

Wed 22-05-19

      Emailing the community for the construction project

7 days

Fri 24-05-19

      Arrangement of informal meetings

6 days

Fri 17-05-19

       Volunteers of St. Dismas

4 days

Mon 27-05-19

      Group of community

3 days

Fri 31-05-19

      St. Dismas staff (all shifts)

5 days

Wed 05-06-19

      Preparation of presentation for Speaker’s Bureau

14 days

Wed 12-06-19

      Updating the community

8 days

Tue 02-07-19

      Establishment of enquiry log

4 days

Fri 12-07-19

      Groundbreaking ceremony — during National Hospital

5 days

Fri 12-07-19

   Marketing plan developed and implementation

31 days

Fri 19-07-19

      Establishment of contract with the PR firm

7 days

Fri 19-07-19

      Development of the marketing plan

4 days

Tue 30-07-19

      Determination of the name and sign for implementation of facility

5 days

Tue 30-07-19

       Hiring of Marketing Director

8 days

Tue 06-08-19

      Implementation of marketing plan

7 days

Fri 16-08-19

      Implementation of marketing plan

4 days

Tue 27-08-19

   Project closure phase

12 days

Mon 02-09-19

      stakeholders signoff

4 days

Mon 02-09-19

      Final project documentation

5 days

Fri 06-09-19

      Post project maintenance planning

3 days

Fri 13-09-19

Conclusion

From the above report it can be concluded that the project management methodology is required to be followed by the project manager for the development of the project and delivering it on the proposed time and the budget. The requirement of the St. Dismal Medical Center project should be clearly understood for reducing the errors in the project. The construction of the new building for the accommodation of the patients and implementation of new technology for increasing the efficiency of the treatment procedure must be managed for the completion of the task. The finance manager should control the flow of the cash and estimate the investment for calculating the return of investment on the project.

Alexiou, S., 2017, April. How an impact plan can build on the success of your project-from proposal to legacy. In EGU General Assembly Conference Abstracts (Vol. 19, p. 14635).

Fellows, R.F. and Liu, A.M., 2015. Research methods for construction. John Wiley & Sons.

Parks, M., 2016. Project Proposal: The Effect of Semantics on Word Order.

Thamhain, H.J., 2014. Assessing the effectiveness of quantitative and qualitative methods for R&D project proposal evaluations. Engineering Management Journal, 26(3), pp.3-12.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Yet, B., Constantinou, A., Fenton, N., Neil, M., Luedeling, E. and Shepherd, K., 2016. A Bayesian network framework for project cost, benefit and risk analysis with an agricultural development case study. Expert Systems with Applications, 60, pp.141-155.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2019). Project Essay For St. Dismas Medical Center.. Retrieved from https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.

"Project Essay For St. Dismas Medical Center.." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.

My Assignment Help (2019) Project Essay For St. Dismas Medical Center. [Online]. Available from: https://myassignmenthelp.com/free-samples/scope-and-time-management-plans
[Accessed 27 July 2024].

My Assignment Help. 'Project Essay For St. Dismas Medical Center.' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/scope-and-time-management-plans> accessed 27 July 2024.

My Assignment Help. Project Essay For St. Dismas Medical Center. [Internet]. My Assignment Help. 2019 [cited 27 July 2024]. Available from: https://myassignmenthelp.com/free-samples/scope-and-time-management-plans.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close