Discuss about the Systems Approach To Planning Scheduling And Controlling.
Before the start of a project, a standard is set that must be fulfilled at the end of the project. This particular standard is called measurable organization value or MOV. The MOV for a project is generally defined by a number of aspects that are described below focussing on this particular project for the development of online stud farm management system.
Desired Area of Impact: Since Globex is focusing to develop the system in order to satisfy the needs of the customer, this project can be called as customer centric and hence, the desired area of impact for the project is customer. Globex wants to exploit the customers’ needs for enhancing the needs of the business for the company.
In addition to the desired area of impact, there are also some values that are to be fulfilled by the project. These values are able to define the entire quality of the project are explained as follows.
Better: The proposed management system is definitely a better option over the existing systems that are handled manually in the stud farms.
Faster: The manual systems at the stud farms are slow and not very efficient. The new proposed management system is thousand times faster and very efficient.
Cheaper: The new proposed system will have one time purchase cost and small maintenance costs whereas the manual system requires monthly expenses on wages as well as system maintenance.
Do More: In addition to providing the clients with their business needs, Globex will be able to get a strong hold on the software distribution and development market.
After these attributes are defined, the outcome of the project will be judged by some project metrics that are certain sets of values or standards associated with the project. The project metrics are as follows.
Quality: The developed system must be of the best quality without any major issues, bugs or interface problems. The user should be able to read the contents and functions of the system easily so that they can use or manage the same. Without the presence of quality, Globex will not be able to develop their business and marketing strategy with the online management system.
Service: Another major metric for the project is the service provided by the system. The system must be able to fulfil the requirements of the stud farm managers and additionally, they should be able to use with low maintenance and upgrade costs.
Desired Area of Impact
The timeframe for achieving the MOV is set at around 10 months within which, the project will be completed and commercialization will be done.
The MOV of the project proposed by Globex is a high quality online stud farm management system that will provide the stud farm managers will required services and features without additional maintenance and upgrade costs once the one time cost for the system is paid.
The scope of the project including the out of scope items have been defined as follows.
- Contract with Virtucon for the development of the system is within the scope of the project.
- Identification of issues faced by the stud farm managers is within the scope of the project.
- Development of the new online stud farm management system is within the scope of the project.
- Development of system marketing strategy is out of scope of the project.
- Plans for future upgrades and mods are out of scope of this project.
The work breakdown structure of the project is shown as follows.
Based on the work breakdown structure, the schedule for the project is determined and shown in the following table.
Task Name |
Duration |
Start |
Finish |
Development of Online Stud Farm Management System |
114 days |
Tue 29-05-18 |
Fri 02-11-18 |
Project Planning and Preparation |
25 days |
Tue 29-05-18 |
Mon 02-07-18 |
Discussion and Consultation between Globex and Virtucon |
4 days |
Tue 29-05-18 |
Fri 01-06-18 |
Identification of the Business Solution |
2 days |
Mon 04-06-18 |
Tue 05-06-18 |
Install a Demo Version of Proposed System |
5 days |
Wed 06-06-18 |
Tue 12-06-18 |
Try on the Demo Version |
5 days |
Wed 13-06-18 |
Tue 19-06-18 |
Approve System Design |
1 day |
Wed 20-06-18 |
Wed 20-06-18 |
Sign Contract for the Development of the Stud Farm Management System |
2 days |
Thu 21-06-18 |
Fri 22-06-18 |
Develop Project Plan |
5 days |
Mon 25-06-18 |
Fri 29-06-18 |
Approve Project Plan |
1 day |
Mon 02-07-18 |
Mon 02-07-18 |
Project Initiation |
7 days |
Tue 03-07-18 |
Wed 11-07-18 |
Allocation Funds for the Project |
1 day |
Tue 03-07-18 |
Tue 03-07-18 |
Create a List of Requirements |
3 days |
Wed 04-07-18 |
Fri 06-07-18 |
Final Review Management System Design |
2 days |
Mon 09-07-18 |
Tue 10-07-18 |
Estimate an Overall Schedule for Project |
1 day |
Wed 11-07-18 |
Wed 11-07-18 |
Project Execution |
63 days |
Thu 12-07-18 |
Mon 08-10-18 |
Procure System Softwares and Software Platform |
2 days |
Thu 12-07-18 |
Fri 13-07-18 |
Procure Hardware Upgrades |
2 days |
Thu 12-07-18 |
Fri 13-07-18 |
Upgrade Current Hardware |
10 days |
Mon 16-07-18 |
Fri 27-07-18 |
Start Development of Online Stud Farm Management System |
1 day |
Mon 16-07-18 |
Mon 16-07-18 |
Develop the System Architecture |
25 days |
Tue 17-07-18 |
Mon 20-08-18 |
Develop Proposed Features |
15 days |
Tue 21-08-18 |
Mon 10-09-18 |
Add GUI |
10 days |
Tue 11-09-18 |
Mon 24-09-18 |
Test System for Bugs and Errors |
6 days |
Tue 25-09-18 |
Tue 02-10-18 |
Complete the Development of the System |
4 days |
Wed 03-10-18 |
Mon 08-10-18 |
Training |
10 days |
Tue 09-10-18 |
Mon 22-10-18 |
Train Current Employees at Globex |
5 days |
Tue 09-10-18 |
Mon 15-10-18 |
Develop Marketing Plan for the Management System |
2 days |
Tue 16-10-18 |
Wed 17-10-18 |
Provide Future Upgrade Information |
2 days |
Thu 18-10-18 |
Fri 19-10-18 |
System Handover |
1 day |
Mon 22-10-18 |
Mon 22-10-18 |
Project Closing |
9 days |
Tue 23-10-18 |
Fri 02-11-18 |
Post Project Review |
2 days |
Tue 23-10-18 |
Wed 24-10-18 |
Project Documentation |
5 days |
Thu 25-10-18 |
Wed 31-10-18 |
Stakeholder Sign Off |
1 day |
Thu 01-11-18 |
Thu 01-11-18 |
Closing of the Project |
1 day |
Fri 02-11-18 |
Fri 02-11-18 |
For the development of the budget plan for the project, the following resources are considered along with their standard usage rates.
Resource Name |
Type |
Initials |
Max. Units |
Std. Rate |
Project Manager |
Work |
P |
100% |
$175.00/hr |
Manager of Marketing and Finance |
Work |
M |
100% |
$125.00/hr |
IT Technical Manager |
Work |
I |
100% |
$125.00/hr |
Trainer |
Work |
T |
100% |
$50.00/hr |
System Integration Expert |
Work |
S |
100% |
$75.00/hr |
System Developer |
Work |
S |
100% |
$75.00/hr |
Chief IT Officer |
Work |
C |
100% |
$125.00/hr |
Data Management and Control Officer |
Work |
D |
100% |
$125.00/hr |
Project Supervisor |
Work |
P |
100% |
$125.00/hr |
Hardware Upgrades |
Material |
H |
$30,000.00 |
|
Development Software |
Material |
D |
$15,000.00 |
These resources are allocated within the project and the overall budget for the project is determined using bottom up estimation method as follows.
Task Name |
Resource Names |
Cost |
Development of Online Stud Farm Management System |
$125,000.00 [TOTAL BUDGET] |
|
Project Planning and Preparation |
$38,000.00 |
|
Discussion and Consultation between Globex and Virtucon |
Project Manager |
$5,600.00 |
Identification of the Business Solution |
Project Manager, IT Technical Manager |
$4,800.00 |
Install a Demo Version of Proposed System |
Chief IT Officer, IT Technical Manager |
$10,000.00 |
Try on the Demo Version |
Chief IT Officer |
$5,000.00 |
Approve System Design |
Project Manager |
$1,400.00 |
Sign Contract for the Development of the Stud Farm Management System |
Project Supervisor, Project Manager |
$4,800.00 |
Develop Project Plan |
IT Technical Manager |
$5,000.00 |
Approve Project Plan |
Project Manager |
$1,400.00 |
Project Initiation |
$7,000.00 |
|
Allocation Funds for the Project |
Project Supervisor |
$1,000.00 |
Create a List of Requirements |
Manager of Marketing and Finance |
$3,000.00 |
Final Review Management System Design |
Manager of Marketing and Finance |
$2,000.00 |
Estimate an Overall Schedule for Project |
IT Technical Manager |
$1,000.00 |
Project Execution |
$59,000.00 |
|
Procure System Softwares and Software Platform |
Chief IT Officer |
$2,000.00 |
Procure Hardware Upgrades |
Chief IT Officer |
$2,000.00 |
Upgrade Current Hardware |
System Integration Expert |
$6,000.00 |
Start Development of Online Stud Farm Management System |
System Integration Expert |
$600.00 |
Develop the System Architecture |
System Integration Expert |
$15,000.00 |
Develop Proposed Features |
Data Management and Control Officer |
$15,000.00 |
Add GUI |
System Developer |
$6,000.00 |
Test System for Bugs and Errors |
System Developer |
$3,600.00 |
Complete the Development of the System |
System Developer, System Integration Expert, Chief IT Officer |
$8,800.00 |
Training |
$4,000.00 |
|
Train Current Employees at Globex |
Trainer |
$2,000.00 |
Develop Marketing Plan for the Management System |
Trainer |
$800.00 |
Provide Future Upgrade Information |
Trainer |
$800.00 |
System Handover |
Trainer |
$400.00 |
Project Closing |
$17,000.00 |
|
Post Project Review |
Chief IT Officer |
$2,000.00 |
Project Documentation |
Project Manager |
$7,000.00 |
Stakeholder Sign Off |
Project Supervisor, Manager of Marketing and Finance, Data Management and Control Officer, System Developer, System Integration Expert, Chief IT Officer, IT Technical Manager, Trainer |
$6,600.00 |
Closing of the Project |
Project Manager |
$1,400.00 |
Before analysing the project risks, the assumptions made during execution of the project are described as follows.
The proposed system will be accepted by stud farm managers.
The development costs and investments can be recovered within 6 to 10 months through the profits.
The project will be completed within 5 months time frame.
The risks of the project are identified using risk register matrix as follows.
Risk |
Chance of Occurrence |
Effect on Project |
Management Strategy |
Financial risk |
Very High |
High |
Estimate appropriate budget, do not overspend |
Scope risk |
High |
Very High |
Define project scope and exclude out of scope items |
No technical support |
High |
High |
The hardware should be upgraded and updated software platform should be used |
Bugs and glitches in the system |
High |
Very High |
Debug and system testing |
Lack of business |
Medium |
High |
Promote the uses and features of the developed system |
The project team follows one philosophy: team work. The entire team believes if the team members coordinate with each other, they will be able to overcome any challenges and complete all their project duties successfully.
The project quality will be determined based on the pre set measurable organization value (MOV) and the project metrics that have also been defined earlier. To analyse the quality of the project, the project supervisor must ensure all the requirements and standards for the project have been made.
Heagney (2016) explains the importance of project closure within his work. According to him, any project, without a closure phase and appropriate closing plan, will remain incomplete and will have high chances of failure. He emphasized on the development of suitable project closure plan before making final decisions regarding the outcome of the project.
According to Walker (2015), project evaluation must be done before it is officially authorized and signed off. This is to ensure all the requirements of the project have been met and all deliverables have been completed successfully. Another important requirement of the project evaluation is to determine whether the budget and the time limits have been fulfilled or not.
Schwalbe (2015) have discussed the basic requirements of the project evaluation and closure. According to him, the project manager needs to review the project documentation to understand what has been done throughout the course of the project. Next, he should review whether the requirements and deliverables of the project have been fulfilled or not. Finally, he should check off a closure checklist to ensure the requirements and outcomes of the project have been authorized by him.
Item |
Check |
Deadline for Project is Met |
|
No Overspending Done during Project |
|
System Requirements have been met |
|
All system errors and bugs have been addressed |
|
Signature |
The project evaluation will be done by the project manager. He will first study the documentation of the project and then review the developed system by himself. Furthermore, he will review the item checklist and mark them as completed before signing off from the project.
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2019). Systems Approach To Planning, Scheduling, And Controlling In Project Management Essay.. Retrieved from https://myassignmenthelp.com/free-samples/systems-approach-to-planning-scheduling-and-controlling.
"Systems Approach To Planning, Scheduling, And Controlling In Project Management Essay.." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/systems-approach-to-planning-scheduling-and-controlling.
My Assignment Help (2019) Systems Approach To Planning, Scheduling, And Controlling In Project Management Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/systems-approach-to-planning-scheduling-and-controlling
[Accessed 23 December 2024].
My Assignment Help. 'Systems Approach To Planning, Scheduling, And Controlling In Project Management Essay.' (My Assignment Help, 2019) <https://myassignmenthelp.com/free-samples/systems-approach-to-planning-scheduling-and-controlling> accessed 23 December 2024.
My Assignment Help. Systems Approach To Planning, Scheduling, And Controlling In Project Management Essay. [Internet]. My Assignment Help. 2019 [cited 23 December 2024]. Available from: https://myassignmenthelp.com/free-samples/systems-approach-to-planning-scheduling-and-controlling.