Discuss About The Construction And Manufacturing Copyright?
In the present planning and completing a project within calculated time and budget has become a tough challenge. It is becoming harder for the engineers to complete their projects as per the calculated time. As per the operations, there are few obstacles while planning and scheduling the construction of the Grand mosque. Hereby, this report has been prepared to discuss the problems that are creating the challenge to complete the project on calculated time and budget. Thereby, as per the complete analysis about the same, there are a few proposals which can help the team to complete the project in an exact way
This report has been prepared to give the details about the scenario and the issues, which have been come up, while complete the task as per the planned task. However, with the complete analysis of the issues, there are some ways, which may help the team has also been discussed over.
As per the schedule and planning, the project needs to get completed within 9 days. However, on the last day of working the team has reached a 1.17m depth of excavation as planned. Therefore, an unexpected hard rock layer has been found by the team which has now created a challenge for the project.
Our consultant was then present at the site and he has advised that the team has to reach 1.5m depth as per the diagram.
The planned calculations for Activity B (Excavation) were;
Activity B |
Soil type |
Quantity |
Rate per Day |
Working days |
Rent per Day |
Total Cost |
|
Sand |
2500 |
200 |
9 |
200 |
2500 |
Table .1
The calculated working day was 9 within which the Excavation should be completed. Now the team has already completed 77 % of the work as per the schedule this activity.
Now as the Hard Rock layer has been found so now it is important to bring rock Breaker. This will not only increase the budget but also will exceed the time period of the project (Rees, 2003).
Now it is important to hire a breaker machine on rent to complete the task and the charges of excavation is 100 m3/ day
Soil type |
Quantity |
Rate per Day |
Working days |
Rent per Day |
Total Cost |
Sand |
1900 |
200 |
6 |
200 |
1500 |
Hard |
600 |
100 |
6 |
250 |
2200 |
|
|
Total |
12 |
Total |
3700 |
Table.2
Hence, the schedule will exceed and the modified one will take 12 working days instead of 9 and this will make the project 9 days behind the planned period.
However, not merely the duration but this will also affect the cost and budget of the project (Nagarajan, 2004). The modified cost for the activity B will become 3700+ indirect costs for 3 days in spite of 2500, this will lead the project over budget.
If we compare the previous excavation cost and time and modify cost and time it is creating a huge difference in the plan.
Thereafter, it has been assumed that the costs to exceed surface mining costs. Now it has become important to review that presumption to analyze the core elements of costs in every case and to compare the costs for the same (Chitkara, 2013).
There are few reasons that are nursing alleged cost effectiveness based on hard rock industry.
They contain labor intensity, equipment, higher energy efficiency and some operations like ground control, supplies etc.
Manpower need to be increased with arise the problem in order to complete the project on time (Dykstra, 2011). This will create over budget issues Indirect cost and direct both.
Equipment cost will also increase the rent of breaker will also include in the expenses. The increased days of working will definitely increase indirect costs for the project (Clough, 2015). The rent of the Breaker and if tried to hire more labor then also it will increase the cost as extra labor will be over budget as per the planned budget.
The processes employed in budgeting is contained to an understanding of cost control and cost estimation.
The analysis has shown us various factors that are affecting the esteemed planned.
Henceforth, the modification has become mandatory to find out any kind of solution for this.
So here are some of the ideas that may help to deal with the current scenario.
Particular |
1st week |
2nd week |
3rd week |
4th week |
Problem Identification |
|
|
|
|
Preparing the Literature Review |
|
|
|
|
Analysis of the gathered data |
|
|
|
|
Research gap |
|
|
|
|
Framing of the aims and objectives of the research |
|
|
|
|
Primary data collection |
|
|
|
|
Scrutiny of data |
|
|
|
|
Explanation and interpretation |
|
|
|
|
Finding valid conclusion |
|
|
|
|
Submission |
|
|
|
|
Figure .1
In order to bring out the appropriate solution, it was important to research accurately. The above-prepared chart has detailed the process of submission. As per the reviewed network and activities sequences, the solution that has been observed is overlap (Dou, 2016). The team can overlap 5 days between activity G and H in spite of working in a sequence. The description has been given below with the help of the table which will help understand the entire activity.
Activity |
Description |
Immediate Predecessors |
Time Duration (Days) |
A |
Excavation |
A |
9 |
B |
Install rough Plumbing |
B |
21 |
C |
Cleaning and Securing of the site |
- |
3 |
D |
Reinforced concrete for plinth Beams works AND Filling |
C |
25 |
E |
Install Rough electrical wiring |
D |
7 |
F |
Outside plaster |
E |
10 |
G |
Wall Tiles For Toilets & Imam House Kitchen |
F |
15 |
H |
Floor Ceramic Tiles |
F |
11 |
I |
Waterproof and Roof Sloop concrete |
G |
8 |
J |
Inside plaster |
I, J |
5 |
K |
Inside painting |
G |
4 |
L |
Outside Painting |
H |
10 |
M |
External Works |
M, K |
25 |
N |
Reinforced concrete for ground floor Columns And Slab |
L |
45 |
O |
Doors and Windows |
N |
21 |
P |
Install Plumbing Fixtures |
O, Q |
9 |
Q |
Marking, Reinforced concrete works |
O, Q |
6 |
R |
SRC solid blocks work for super structure works |
L |
10 |
S |
Install Electric Fixyures |
I,J |
8 |
T |
SRC Solid blocks work for periphery outside the building under the plinth beam |
K |
7 |
U |
Handing Over of completed work Leave in a fit condition for occupation: |
P,R,S |
5 |
Table .3
Overlapping activity G and H can save the extra 3 days as well as will help the project to complete it as per the schedule but will add another critical path and this can increase the risk.
Then the modification will create 2 critical paths and there the team has to work with the new technique to reduce the risk.
Consisting of two critical paths will increase project risk but the help of this solution can be found for the problem of the team.
|
|
Original Planned |
Modified |
||
Activity Code |
Immediate Predecessors |
Duration Days |
Total Direct Cost |
Duration Days |
Total Direct Cost |
A |
A |
9 |
1500 |
12 |
1500 |
B |
B |
21 |
6950 |
21 |
6000 |
C |
- |
3 |
500 |
3 |
500 |
D |
C |
25 |
1700 |
25 |
2000 |
E |
D |
7 |
650 |
7 |
650 |
F |
E |
10 |
2500 |
10 |
2500 |
G |
F |
15 |
3000 |
15 |
3000 |
H |
F |
11 |
1800 |
11 |
2000 |
I |
G |
8 |
900 |
8 |
900 |
J |
I,J |
5 |
600 |
5 |
600 |
K |
G |
4 |
550 |
4 |
550 |
L |
H |
10 |
2000 |
10 |
2000 |
M |
M,K |
25 |
4040 |
25 |
4040 |
N |
L |
45 |
10,000 |
45 |
10,000 |
O |
N |
21 |
5050 |
21 |
5050 |
P |
O,Q |
9 |
3500 |
9 |
3500 |
Q |
O,Q |
6 |
750 |
6 |
750 |
R |
L |
10 |
2500 |
10 |
2500 |
S |
I,J |
8 |
1200 |
8 |
1200 |
T |
K |
7 |
900 |
5 |
900 |
U |
P,R,S |
5 |
800 |
4 |
800 |
|
|
Total |
51390 |
Total |
50940 |
Table .4
With the above classifications, it has been clearly analyzed that it is possible to maintain the budget as well as the duration of the project. The modification brings out another critical path with which new calculation has been generated and that may help the team (Jha, 2011).
The cost of RCC foundation including labor = 80 O.R/m3, 38 x 80 = 3040 O.R.
Imported filling including machine + labor charge = 1.5 O.R / m3, 750x1.5=1125
As per this calculation, the solution which can be used to maintain our budget is using the selected excavated material after use screen
Estimated selected excavated material after use screen + labor charge = 0.5 O.R/m3, 750x0.5=375
This will help us to save 750 O.R. the project will be under budget
|
Working Days |
Direct Cost |
Indirect Cost/Day |
Sum Indirect Cost |
Total Cost |
Planned Baseline |
160 |
51390 |
100 |
16000 |
67390 |
Modified Baseline |
160 |
50940 |
100 |
16000 |
66940 |
Table .5
With this modified baseline it is possible to control the budget and the time for the project. The construction is possible with the help of modification as per the analysis of the complete problem.
It is important to maintain the budget and time so if excavated materials are getting used and overlapping the G and H activity it will reduce the project risk (Munier, 2012). As per the modified base line, our direct cost will become 50940 that are even less than the previously planned baseline.
The entire problem of over budgeting and increase of planned duration while excavation because of the finding of Hard Rock layer while reaching 1.17 m deep has made the project has made challenging one. In order to bring the appropriate solution, it was important to analyze and modify the entire calculation which has generated two critical paths. Two Critical paths may generate a bit of risk in the project.
Although with the complete analysis the solution that has been understood is the overlapping of few business-law as well as the using the selected excavated materials instead of imported one may help reduce the risk of the project. Overlapping of two activities that are activity G and H has not only helped to maintain the duration of the budget but has also helped to maintain the budget. As shown in the table that the total cost of modified baseline is 66940 which obviously less than the previously planned base line.
Carmichael, D (2000) Contracts and International Project Management. CRC Press. copyright
Chitkara, K (2013) Construction Project Management. Tata McGraw-Hill Education. Copyright
Clough, R (2015) Construction Project Management. John Willey & Sons. Copyright
Dou, R (2016) Proceedings of the 22nd International Conference on Industrial..Vol2. Springer. Copyright
Dykstra, A (2011) Construction Project Management. Kirshner Publishing Company
Jha, K (2011) Construction Project Management: Theory and Practice. SAGE Publication
Munier, N (2012) Project Management for Environmental, Construction and Manufacturing. psychology. Copyright
Nagarajan, K (2004) Project Management. New Age International. Copyright
Ramakrishna, K (2010) Essentials of Project Management. PHI Learning Pvt Ltd. Copyright
Rees, G (2003) Civil Engineering Project Management Fourth Edition. Elsevier. Copyright
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2018). Construction And Manufacturing Copyright . Retrieved from https://myassignmenthelp.com/free-samples/construction-and-manufacturing-copyright.
"Construction And Manufacturing Copyright ." My Assignment Help, 2018, https://myassignmenthelp.com/free-samples/construction-and-manufacturing-copyright.
My Assignment Help (2018) Construction And Manufacturing Copyright [Online]. Available from: https://myassignmenthelp.com/free-samples/construction-and-manufacturing-copyright
[Accessed 20 January 2021].
My Assignment Help. 'Construction And Manufacturing Copyright ' (My Assignment Help, 2018) <https://myassignmenthelp.com/free-samples/construction-and-manufacturing-copyright> accessed 20 January 2021.
My Assignment Help. Construction And Manufacturing Copyright [Internet]. My Assignment Help. 2018 [cited 20 January 2021]. Available from: https://myassignmenthelp.com/free-samples/construction-and-manufacturing-copyright.
MyAssignmenthelp.com is a leading name in providing PhD dissertation writing help in Australia. Our services cover a wide range of subjects including economics and marketing dissertation help. Students can easily avail our services since we provide cheap dissertation writing services. But we never compromise with the quality while providing dissertation help services . Moreover, students are also allowed to get free access to dissertation samples and use them as a future reference.
Answer: Introduction: This report is going to discuss about the methodology that is described by Terry Cooke-Davies in the book Aspect of Complexity. The main objective of this report is to discuss about the parametric estimation in non-engineering fields (Brockwell & Schlemm, 2013). Parametric estimate is calculated by calculating the time and cost required per unit. The approaches that are estimated with the parametric model will ...
Read MoreAnswer 1. The major social responsibility issue associated with Producto International (PI) is the production and distribution of unsafe and unhealthy products. The scenario reveals that Betel, which is one of the products produced and distributed by PI, has negative health consequences. For example, the case reveals that Myron was learning more about the betel nut, he came across the different reports that implicate betel to oral cancer and o...
Read MoreAnswer Professional practice in teaching sector Introduction: The report emphasises on the major features of teaching methods and learning in further education and skills sectors. Further education (FE) involves any course or study that is different from secondary education and it is not a part of higher studies (Gleeson et al. 2015). It is a course, degree or qualification that is offered in universities or other academic institutes. Th...
Read MoreAnswer: Part 1: The Protagonist According to the personality test, my personality trait is a protagonist with greater alignments of assertiveness and judging. Although there are other individual traits like extraversion, intuition, and feeling, they contribute less to the personality type. Ideally, people who are considered protagonists have different characteristics. First, protagonists have a sense of curiosity either natural or insti...
Read MoreAnswer: Introduction: The evidence is stated as the type of exhibitor material, which is represented prior to the court's jurisdiction or else prior to any different panel authorization in order to hear as well as determine a subject matter. The method of showing facts generally plays a significant role in order to determine a concerned matter. In spite of the importance that is attached to it, various bodies consisting the children hav...
Read MoreJust share requirement and get customized Solution.
Orders
Overall Rating
Experts
Our writers make sure that all orders are submitted, prior to the deadline.
Using reliable plagiarism detection software, Turnitin.com.We only provide customized 100 percent original papers.
Feel free to contact our assignment writing services any time via phone, email or live chat. If you are unable to calculate word count online, ask our customer executives.
Our writers can provide you professional writing assistance on any subject at any level.
Our best price guarantee ensures that the features we offer cannot be matched by any of the competitors.
Get all your documents checked for plagiarism or duplicacy with us.
Get different kinds of essays typed in minutes with clicks.
Calculate your semester grades and cumulative GPa with our GPA Calculator.
Balance any chemical equation in minutes just by entering the formula.
Calculate the number of words and number of pages of all your academic documents.
Our Mission Client Satisfaction
Im certain very pleased with the work done.All my requirements were very in detail meet. Thank you
Australia
You wont believe who just got 93% on the first assignment i asked you guys to do for me. Keep up the good work guys. I'm definitely going to tell my friends
Australia
The outcome was very good and satisfactory.I am planning to submit more assignments in near future.
Australia
Work delivered as requested, ahead of the deadline. Fully referenced, could not have asked for more. Thanks guys & gals!
Australia