Part B – Scope and Time Management Plans
In this subject, you will be creating key components of a Project Management Plan using the information found in your selected Case Study. The case study (or a selection of) will be provided by your learning facilitator at the commencement of the subject.
In modules 1, 2 and 3, you will work individually or in a group of 2-3 students on a given/approved Case Study. For Assessment 1 Part B, you are responsible for submitting the following components of your project scope and time management plans that contain:
- Project goals and objectives
- Project scope statement
- Work Breakdown Structure (WBS)
- Project schedule
For the project scope statement and WBS, you can use the templates found in this module’s Learning Resources or a format of your own. For the project schedule, you are responsible for submitting a schedule and a network diagram using the critical path method (CPM). Your schedule can be created using scheduling software e.g. ProjectLibre or Microsoft Project. Your network diagram can be hand-drawn and scanned or created using drawing tools e.g. in Microsoft Word or PowerPoint.
Your written project goals, project objectives and scope statement should consist of 800 words/student.
Output:
Complete and submit your Scope and Time Management Plan individually or in a group of 2 to 3 students by the end of Module 3. If your submission is in group, only one group member to submit the assessment. Each group member is required to submit a contribution form.
1.0 Project Goals and Objectives
Introduction
This project is based on the renovation of the St. Dismas Assisted Living Facility as well as addition of new residential area and implementation of medical information management system. The project will be conducted in several phases and a significant amount of investment is required to get the project done within time.
In this report, the project goals, objectives and scope are identified and project duration has been determined.
1.0 Project Goals and Objectives
The primary goals of the project include the complete renovation of the hospital building, addition and implementation of better hospital facilities and development of a new management system for better and faster operations. Due to the age of the building, there have been several areas where walls have got eroded and need urgent repair (Harrison & Lock, 2017). The existing facilities have not been upgraded as well as hence require urgent upgrade as well as replacement. Finally, IT is finally going to be an integral part of the hospital operations with the development of the new management system. Hence, the objectives of the project are derived as follows.
- To survey the entire building and mark the areas that need repair and renovation
- To survey existing facilities and equipments for determining changes
- To survey the requirements and features for the management system
- To procure materials for building renovation
- To repair the marked areas and renovate the entire building
- To replace old facilities and replace them with new ones
- To upgrade the medical equipments and facilities
- To develop an online medical process management system
2.0 Project Scope Statement
The scope of the project includes the following.
- The scope includes the renovation of the entire hospital building.
- The scope includes changes and upgrades in various departments in the hospital.
- The scope includes the development of a medical management system that will increase the processing of various hospital operations like registering a patient, processing of hospital bill payment, searching for existing patient’s medical records and others (Laudon & Laudon, 2016).
The overall scope of the project also includes fulfilling the following milestones / activities within an estimated duration as shown in the following table.
Task Name |
Duration |
Start |
Finish |
St. Dismas Assisted Living Facility Project |
4420 days |
Wed 2/14/18 |
Tue 1/23/35 |
Initiation phase |
793 days |
Wed 2/14/18 |
Fri 2/26/21 |
Construction & Furnishing |
369 days |
Wed 2/14/18 |
Mon 7/15/19 |
Facility construction |
329 days |
Tue 7/16/19 |
Fri 10/16/20 |
Phase 1 - Foundation & excavation (basement/1st fl oor slab) |
95 days |
Mon 10/19/20 |
Fri 2/26/21 |
Phase 2 - Structure (steel/framing) |
113 days |
Tue 4/23/19 |
Thu 9/26/19 |
Phase 3 - Enclosure (masonry/windows/roof) |
134 days |
Tue 7/16/19 |
Fri 1/17/20 |
Phase 4 - Interiors (drywall/ceiling/fl ooring/case goods) |
234 days |
Tue 7/16/19 |
Fri 6/5/20 |
First 45 (light assisted) units ready to prepare for occupancy |
0 days |
Fri 8/23/19 |
Fri 8/23/19 |
First 45 units ready for residents |
8 days |
Mon 1/20/20 |
Wed 1/29/20 |
Remaining 57 units (light & heavy) ready to prepare for occupancy |
0 days |
Thu 9/26/19 |
Thu 9/26/19 |
Construction complete |
0 days |
Fri 8/23/19 |
Fri 8/23/19 |
Building ready for residents |
8 days |
Thu 1/30/20 |
Mon 2/10/20 |
Planning phase |
654 days |
Tue 2/11/20 |
Fri 8/12/22 |
Legal and Licensing Requirements |
154 days |
Tue 2/11/20 |
Fri 9/11/20 |
Research licensing requirements for residential |
38 days |
Mon 9/14/20 |
Wed 11/4/20 |
Uniform accessibility standard compliance |
10 days |
Thu 11/5/20 |
Wed 11/18/20 |
Investigate law fi rm and outline services |
20 days |
Thu 11/19/20 |
Wed 12/16/20 |
Prepare project plan for license |
10 days |
Thu 11/19/20 |
Wed 12/2/20 |
File license — by opening date |
0 days |
Wed 12/16/20 |
Wed 12/16/20 |
Curb - cut approval from county (access to |
53 days |
Thu 12/3/20 |
Mon 2/15/21 |
Investigate corporate structure for assisted living |
115 days |
Thu 12/17/20 |
Wed 5/26/21 |
Determine Board of Trustee membership |
15 days |
Tue 2/16/21 |
Mon 3/8/21 |
Appoint Board of Trustees |
20 days |
Thu 5/27/21 |
Wed 6/23/21 |
Prepare draft Code of Regulation |
20 days |
Tue 3/9/21 |
Mon 4/5/21 |
Prepare draft Code of Regulation |
20 days |
Thu 6/24/21 |
Wed 7/21/21 |
Prepare document and fi ling of governance structure |
60 days |
Tue 4/6/21 |
Mon 6/28/21 |
Draft service agreement with St. Dismas for services provided |
20 days |
Thu 7/22/21 |
Wed 8/18/21 |
Lease issues |
110 days |
Tue 6/29/21 |
Mon 11/29/21 |
Research Long Term Care insurance |
60 days |
Thu 8/19/21 |
Wed 11/10/21 |
Facility “rules” defined |
20 days |
Tue 11/30/21 |
Mon 12/27/21 |
Spell out changes for residents in moving |
30 days |
Tue 11/30/21 |
Mon 1/10/22 |
Lease template prepared |
30 days |
Tue 12/28/21 |
Mon 2/7/22 |
Review all marketing materials for compliance |
154 days |
Tue 1/11/22 |
Fri 8/12/22 |
Execution phase |
2757 days |
Mon 8/15/22 |
Tue 3/8/33 |
Operational Implementation Plan |
1 day |
Mon 8/15/22 |
Mon 8/15/22 |
Management/Organization structure |
87 days |
Tue 8/16/22 |
Wed 12/14/22 |
Recruit & hire Executive Director |
17.4 wks |
Thu 12/15/22 |
Fri 4/14/23 |
Interior design issues decided (furnishings, etc.) |
20 days |
Mon 4/17/23 |
Fri 5/12/23 |
Determine what was provided with lease and what was furnished in some units |
2 wks |
Mon 5/15/23 |
Fri 5/26/23 |
Determine budget for interior |
10 days |
Mon 5/29/23 |
Fri 6/9/23 |
Carpet and wall finish determined |
2 wks |
Mon 5/29/23 |
Fri 6/9/23 |
Furniture and room layout |
2 wks |
Mon 5/29/23 |
Fri 6/9/23 |
Facility and equipment needs defi ned |
4 wks |
Mon 6/12/23 |
Fri 7/7/23 |
Staffing determined |
2 wks |
Mon 7/10/23 |
Fri 7/21/23 |
Offi ce space for physicians |
4 wks |
Mon 7/24/23 |
Fri 8/18/23 |
Medical staffi ng needs determined & Director appointed |
4 wks |
Mon 8/21/23 |
Fri 9/15/23 |
Food service |
45 days |
Mon 9/18/23 |
Fri 11/17/23 |
Menus selected |
8 wks |
Mon 11/20/23 |
Fri 1/12/24 |
Waiting and service staffi ng needs determined |
4 wks |
Mon 1/15/24 |
Fri 2/9/24 |
Additional equipment needs |
4 wks |
Mon 1/15/24 |
Fri 2/9/24 |
Telecommunications services |
45 days |
Mon 2/12/24 |
Fri 4/12/24 |
Investigate phone service options |
45 days |
Mon 4/15/24 |
Fri 6/14/24 |
Certifi cation/Accreditation requirements |
42 days |
Mon 6/17/24 |
Tue 8/13/24 |
Investigate requirements & timing of applicants |
0 days |
Tue 8/13/24 |
Tue 8/13/24 |
Develop clinical and operational quality |
0 wks |
Tue 8/13/24 |
Tue 8/13/24 |
Develop financial systems (billing, etc.) |
6 wks |
Wed 8/14/24 |
Tue 9/24/24 |
Human resources |
79 wks |
Wed 9/25/24 |
Tue 3/31/26 |
Work force management recommendations |
6 wks |
Wed 4/1/26 |
Tue 5/12/26 |
Project plan for recruitment developed |
2 wks |
Wed 4/1/26 |
Tue 4/14/26 |
Policies and procedures developed |
60 days |
Wed 5/13/26 |
Tue 8/4/26 |
Obtain ‘samples’ of assisted living policies & procedures from other institutions |
4 wks |
Wed 4/15/26 |
Tue 5/12/26 |
Investigate assisted living laws proposed in other stages |
12 wks |
Wed 8/5/26 |
Tue 10/27/26 |
Technology & information systems |
344 wks |
Wed 5/13/26 |
Tue 12/14/32 |
Develop plan for technology access for residents (TV, Cable, PC ’ s) |
3 wks |
Wed 10/28/26 |
Tue 11/17/26 |
Investigate software/technology options for residents |
12 wks |
Wed 12/15/32 |
Tue 3/8/33 |
Completion of the construction nad furnishing pahse |
490 days |
Wed 3/9/33 |
Tue 1/23/35 |
Marketing |
270 days |
Wed 3/9/33 |
Tue 3/21/34 |
Community mailing about construction project |
0 days |
Tue 3/21/34 |
Tue 3/21/34 |
Initial informational meetings |
16 days |
Wed 3/22/34 |
Wed 4/12/34 |
St. Dismas volunteers |
1 day |
Thu 4/13/34 |
Thu 4/13/34 |
Community groups |
4 days |
Fri 4/14/34 |
Wed 4/19/34 |
St. Dismas staff (all shifts) |
3 days |
Thu 4/20/34 |
Mon 4/24/34 |
Presentation prepared for Speaker ’ s Bureau |
0 days |
Tue 3/21/34 |
Tue 3/21/34 |
Provide updates to community |
0 days |
Mon 4/24/34 |
Mon 4/24/34 |
Inquiry log established |
0 days |
Tue 3/21/34 |
Tue 3/21/34 |
Groundbreaking ceremony — during National Hospital Week |
0 days |
Mon 4/24/34 |
Mon 4/24/34 |
Marketing plan developed and implemented |
180 days |
Wed 3/22/34 |
Tue 11/28/34 |
PR firm contracted |
4 wks |
Tue 4/25/34 |
Mon 5/22/34 |
Marketing plan developed |
8 wks |
Wed 11/29/34 |
Tue 1/23/35 |
Determine name and signage for facility |
0 days |
Mon 5/22/34 |
Mon 5/22/34 |
Hire Marketing Director |
4 wks |
Tue 5/23/34 |
Mon 6/19/34 |
Marketing plan ready to implement |
0 days |
Mon 5/22/34 |
Mon 5/22/34 |
Implementation of marketing plan—5 months before facility ready,then ongoing |
20 days |
Tue 6/20/34 |
Mon 7/17/34 |
3.0 Work Breakdown Structure
The work breakdown structure for the project is shown in the following diagram.
Figure 1: Project Work Breakdown Structure
(Source: Created by Author)
2.0 Project Scope Statement
4.0 Project Schedule
The estimated schedule for the project is calculated and shown in the Gantt chart as follows.
Figure 2: Gantt Chart of the Project
(Source: Created by Author)
Figure 3: Network Diagram for the Project
(Source: Created by Author)
Conclusion
This report has been developed in order to determine scope, deliverables and schedule for the St. Dismas Assisted Living Facility Project. This project includes repair work for the entire hospital building, addition of residential zones for the patients, implementation of medical information management system and others.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2020). Scope And Time Management Essay For St. Dismas Assisted Living Facility Project.. Retrieved from https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/work-breakdown-structure.html.
"Scope And Time Management Essay For St. Dismas Assisted Living Facility Project.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/work-breakdown-structure.html.
My Assignment Help (2020) Scope And Time Management Essay For St. Dismas Assisted Living Facility Project. [Online]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/work-breakdown-structure.html
[Accessed 22 November 2024].
My Assignment Help. 'Scope And Time Management Essay For St. Dismas Assisted Living Facility Project.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/work-breakdown-structure.html> accessed 22 November 2024.
My Assignment Help. Scope And Time Management Essay For St. Dismas Assisted Living Facility Project. [Internet]. My Assignment Help. 2020 [cited 22 November 2024]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/work-breakdown-structure.html.