Describe about the Project Plan for a Company Retreat to Another Country.
Company Background
The selected organization (company) is Aetos Engineering that deals with design and engineering in aircrafts. It is a business organization that has extensive business system in the native country and is now looking to retreat to some other country as part of the business strategy. The company has been very successful in the native country and now wants to retreat to another country in order to get access to global market. The company has chosen to retreat to Australia first and if the move is successful, they will consider retreating to other countries. However, before retreating to some other country, some project planning is necessary so that the system can be installed in time before the start of business in the new country. As per the requirement of the company, a project plan has been prepared.
The project is based on the preparation and design of a system plan that the company needs to retreat to another country. In order to complete the retreat successfully, the company needs a proper project planning that must be followed step by step. The tasks of the project are as follows.
- Selection of a suitable country for retreat (in this case, the country selected is Australia)
- Analysis of the existing market and competitions in Australia
- Total budget estimation and cost benefit analysis for the purpose of retreat
- Stakeholder analysis for estimating the total number of people to be involved in the project
- Analysis of the existing law, government policies and business guidelines in the Australia
- Risk analysis and mitigation
The 6-point checklist is as follows.
Project Scope |
Verification |
Project Objective |
Done √ |
Deliverables |
Done √ |
Milestones |
Done √ |
Technical Requirements |
Done √ |
Limitations and Exclusions |
Done √ |
Customer Review |
Done √ |
The primary objective of this project is preparation and designing of a system for the company that will help in the retreat to the chosen country. The company, Aetos Engineering deals with engineering of aircraft designs and wants to retreat to Australia in order to gain access to the global market and global popularity. The brief explanation of the objectives of this project is provided below:
- To choose a suitable country for relocation
- To analyze the existing conditions of the country – political, judicial, social and commercial
- To analyze the risks accompanying the project
- To install necessary hardware systems in the retreat office
- To design and implement a suitable data warehouse for storage and operation of business data
- To connect the data warehouse with the native business headquarters
- To initiate the new system in the selected country
The deliverables of the project are as follows.
- Selection of a suitable site / country for retreat
- Complete analysis report on the market conditions in the selected country
- Complete risk analysis report
- New office building for the retreat
- New hardware systems for business operations
- New data warehouse for storage and management of business data
- Established connection between the retreat office and the main headquarters
The estimated project milestones calculated from the initiation of the project are as follows.
A list of countries of retreat prepared – 10 days
Market and other factors analyses – 2 months
Risk analysis – 1 month
Selection of the country for retreat – 5 days
Cost estimation – 15 days
Resource allocation and funding – 1 month
Infrastructure planning, setting up of retreat office – 1 year
Hardware implementation – 3 months
Software and data warehouse implementation – 1 month
Establishment of connection between the offices of the two countries – 15 days
System initiation – 1 month
Following are the technical requirements for the project.
- The business must comply with the legal policies and guidelines of the country in which the retreat is planned.
- The installed hardware systems must be upgraded to latest technology in order to manage the business efficiently.
- The data warehouse system must be up to date and must support business operations and data management.
- The company must comply with business guidelines and the retreat must provide significant cost benefits in order to ensure success of the project.
Limitations
The following are the project limitations.
Description of the Project
Although an external analysis is conducted on the selected country, the exact conditions cannot be known accurately before actually initiating services in the country.
This project plan only deals with the discussion of scope and estimation of resources. Actual project plan should be prepared with more information and estimations.
The resource details are only rough estimations. More modifications are required with changing scopes and design of the system.
No stakeholder plan is provided in this part of project plan.
The data provided in this project plan will change with changes in project plan and the dynamic market of the new country.
The exclusions of the project are as follows.
× The share market condition and the company’s entry in the share market of the selected country are excluded from this project plan.
× The outsourcing and employment policies for initiation of services in the new country are excluded from this project plan.
× Only a brief idea of estimated resources has been provided, resource management plan has been excluded from the project plan.
× New business policies have been excluded from the plan.
× The selection of hardware and software vendors and their implementation steps have also been excluded.
Customer review is an important part of any business as the production and innovation is dependent on customer satisfaction. Now, for retreating to another country, international customers come into play. Before the project, an analysis of the social background of the company is to be conducted in addition to market analysis for understanding the demands of products and customer commercial trend. After initiation of business, the company should start a customer review system in order to know what the customers like and dislike about their products or services. The company should revise its policies and business products in accordance with the customer reviews in order to enhance the existing business system of the company. This will ensure the success of the business retreat of the company to another country.
Project/Selection Criteria |
Cost |
Scope |
Time |
||||
Weight: |
8 |
7 |
6 |
Total |
|||
Company Relocation |
8 |
6 |
8 |
||||
(8*8=) 64 |
(7*6=) 42 |
(6*8=) 48 |
(64+42+48=) 154 |
||||
Analysis of the Foreign Market |
5 |
6 |
4 |
||||
(8*5=) 40 |
(7*6=) 42 |
(6*4=) 24 |
(40+42+24=) 106 |
||||
Architecture Development |
9 |
6 |
8 |
||||
(8*9=) 72 |
(7*6=) 42 |
(6*8=) 48 |
(72+42+48=) 162 |
||||
Resource Investment |
10 |
7 |
10 |
||||
(8*10=) 80 |
(7*7=) 49 |
(6*10=) 60 |
(80+49+60=) 189 |
This project priority matrix has been used to represent the primary four areas that are required for the project. These four parts are market analysis, investment, infrastructure and relocation projects. There should be at least three success criteria for the project having different weightages. The three main success criteria are “cost, scope and time”. The weightage for the success criteria should be as follows.
Project Cost – 8
Project Scope – 7
Project Time – 6
The effects of the chosen success criteria will depend on the priorities estimated in the project and the project has to be executed accordingly.
Task No |
Task Name |
No of Days |
1 |
Project: Company Retreat to Another Country |
1005 days |
1.1 |
Project Initiation Phase |
100 days |
1.1.1 |
Requirement Analysis |
30 days |
1.1.2 |
Feasibility Testing |
30 days |
1.1.3 |
Selection of Country |
10 days |
1.1.4 |
Estimation of Costs and Expenses |
30 days |
1.2 |
Project Planning Phase |
150 days |
1.2.1 |
Preparation of Project Plan |
30 days |
1.2.2 |
Scheduling of Project Duties |
15 days |
1.2.3 |
Allocation of Resources |
30 days |
1.2.4 |
Preparation of Communication Plan |
15 days |
1.2.5 |
Land Selection in the Retreat Country |
60 days |
1.3 |
Execution phase |
430 days |
1.3.1 |
Development of Abroad Branch |
180 days |
1.3.1.1 |
Architecture Planning and Design |
60 days |
1.3.1.2 |
Resource Collection |
30 days |
1.3.1.3 |
Location Blueprint Preparation |
30 days |
1.3.1.4 |
Development of Communication System |
30 days |
1.3.1.5 |
Development of a new Business System |
30 days |
1.3.2 |
Implementation Phase |
250 days |
1.3.2.1 |
Implementation of the Resources |
60 days |
1.3.2.2 |
Development of Business Plan |
60 days |
1.3.2.3 |
Implementation of Software and Data Warehouse |
90 days |
1.3.2.4 |
Market Analysis System Development |
30 days |
1.3.2.5 |
Connection of the Data Warehouse with Central Headquarters |
10 days |
1.4 |
Closing Phase |
150 days |
1.4.1 |
Creation of Communication Link between New Branch and Headquarters |
10 days |
1.4.2 |
Employee Training and Recruitment |
90 days |
1.4.3 |
Business Data Warehouse Maintenance |
50 days |
Figure: WBS of the Project
(Source: Created by Author)
Figure: Gantt Chart
(Source: Created by Author)
Cost Estimation Table
Project Activity |
Estimated Cost |
Location Survey and Selection |
$20,000 |
Land Purchase |
$100,000 |
Architecture Development |
$100,000 |
Implementation of Necessary Hardware |
$50,000 |
Implementation of Software |
$50,000 |
Communication Set Up |
$10,000 |
Training of Recruits |
$20,000 |
Project Name |
Monthly Timeline |
|||||
Month 1 |
Month 2 |
Month 3 |
Month 4 |
Month 5 |
Notes: |
|
Location Analysis |
-$10,000 |
-$10,000 |
|
|
|
Selection of location for retreat |
Resource Investment |
|
|
$100,000 |
$100,000 |
$150,000 |
Investment on project fund |
Architecture Development |
|
|
-$50,000 |
-$150,000 |
-$150,000 |
Development of building, hardwares and softwares |
Business Initiation |
|
|
|
|
-$50,000 |
Initiation of Business |
System Testing |
|
|
|
-$5,000 |
-$2,500 |
Testing of market, hardware and software |
Project Start Up |
|
|
|
|
$200,000 |
Total Capital |
Recruitment and Training |
|
|
|
-$10,000 |
|
Training and recruitment of new employees |
Payment of Wages |
|
|
|
|
-$25,000 |
Wage payments |
Profit (Estimated) |
|
|
|
|
$50,000 |
Profit from the 1st month of the business |
Month 1 |
Month 2 |
Month 3 |
Month 4 |
Month 5 |
|
|
Totals: |
-$10,000 |
-$10,000 |
$50,000 |
-$65,000 |
$172,500 |
Total balance of each month |
Cumulative Total: |
-$10,000 |
-$20,000 |
$30,000 |
-$35,000 |
$137,500 |
Available balance after each month |
Burke, R. (2013). Project management: planning and control techniques.New Jersey, USA.
Fitzsimmons, J., & Fitzsimmons, M. (2013). Service management: Operations, strategy, information technology. McGraw-Hill Higher Education.
Greenberg, B. N., & Jetton, S. M. (2013). U.S. Patent No. 8,352,341. Washington, DC: U.S. Patent and Trademark Office.
Grefen, P., Pernici, B., & Sánchez, G. (Eds.). (2012). Database support for workflow management: the WIDE project (Vol. 491). Springer Science & Business Media.
Heagney, J. (2012). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, R. (2016). Gower handbook of project management. Routledge.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2018). Project Plan For A Company Retreat To Another Country - Aetos Engineering Essay.. Retrieved from https://myassignmenthelp.com/free-samples/project-plan-for-a-company-retreat-to-another-country.
"Project Plan For A Company Retreat To Another Country - Aetos Engineering Essay.." My Assignment Help, 2018, https://myassignmenthelp.com/free-samples/project-plan-for-a-company-retreat-to-another-country.
My Assignment Help (2018) Project Plan For A Company Retreat To Another Country - Aetos Engineering Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/project-plan-for-a-company-retreat-to-another-country
[Accessed 27 November 2024].
My Assignment Help. 'Project Plan For A Company Retreat To Another Country - Aetos Engineering Essay.' (My Assignment Help, 2018) <https://myassignmenthelp.com/free-samples/project-plan-for-a-company-retreat-to-another-country> accessed 27 November 2024.
My Assignment Help. Project Plan For A Company Retreat To Another Country - Aetos Engineering Essay. [Internet]. My Assignment Help. 2018 [cited 27 November 2024]. Available from: https://myassignmenthelp.com/free-samples/project-plan-for-a-company-retreat-to-another-country.