Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

Overall goal of the team is to deliver and online system for stud farm management in least possible expense on time which is capable of meeting requirements of the stakeholders from the system.  With my previous experience I am looking forward to utilize my understanding of HTML and Java platform to offer effective development of online system.

  • Team members should respect contribution of each other
  • They should not discriminate on the basis of designation and nationality.
  • They should not procrastinate and must contribute equally.
  • Team members are expected to work with honesty
  • They are expected to follow the code of integrity
  • They are expected to contribute in the project with their highest potential
Team Values
  • Choose the area of impact you have ranked as no 1.
  • For that area of impact
  • With reference to your project, identify one or two of the following types of value:
    • Better - is improving quality important to your client?
    • Faster - does your client want to increase efficiency?
    • Cheaper - is cutting costs important?
    • Do more - does your client want to continue its growth?

For the online Stud Farm project strategy is in rank 1, for their area of impact and with the project reference it is found that two different types of values such as better and faster are considered for this. At the project initiation phase, the business analyst considers certain marketing and managerial strategies. The chosen values for the business strategies are as follows:

Better: The strategies considered for this online booking system is needed to be better than the existing one. With a better strategy the online Stud Farm will be able to grab more consumers from wide geographical location and retain their existing customers.

Faster:  The online booking system is expected to be faster than the traditional spreadsheet booking system. With a faster approach they can book for more numbers of consumers with a little time period.

  • Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.

Stakeholders

Target and expectation

Project manager

Target and expectations of the project manager are not that much different from each other. Collectively it can be said that, the target should reach the project expectation. The project manager is expecting to deliver an online booking system to the consumers.

Government

The expectation of the government is to retain the consumers and to prevent them to travel outside country for the animal breeding.  The business outcome is indirectly related to the governmental tax.

Suppliers

In order to develop the online booking system for the Stud Farm they should deal with three suppliers- network supplier, hardware and software suppliers.

  • Determine the timeframe for achieving the MOV - ask yourselves, when do we want to achieve this target metric?
    Based on the project background and project details it has been found that the company will need not more than 10 months to successfully accomplish the online booking system.  After considering the complexity of the project it is divided into small activities. Individual timeframe is again designed for each of the activity. The planned budget and the actual budget for the project may vary but still overall it is expected that the project will be accomplished in $95,700.
  • Part Two: (10 Marks)
    Scope (minimal 10 items) – 10 Marks
  • Requirements are gathered and documented
  • Design and Development of the online booking system for Stud Farm
  • Test and Implementation of the design and outlined prototype
  • Reports are implemented after analysing the project details and project requirements
  • Support the system through warranty period of 24 months or around 2 years
  • The service will be open for the consumers for 24X7 hours
  • In case  of online booking no third party or mediator are present thus it is absolutely commission free
  • It gives secured and good customer service
  • The workload from the project team members will be reduced completely
  • All the customers will be able to deliver a secured online payment option to the consumers.

No post project maintenance plan is developed for the online Stud Farm management system

The role of the business analyst and how the project will be promoted is out of scope

Project assumption is a set of belief that is assumed to be true for the coming future outcome of the system. Based on the knowledge, experience and available information the project assumptions are designed by the project team members and project manager.  It is assumed that the project will get all necessary resources (physical and human) for the successful implementation of the project. The stakeholders will attend all the meetings are motivate the team members so that they can reach the project objectives very easily.

In order to develop the online stud farm management system triple project constraints has been chosen. It is ideate that for successful implementation of the online booking system the total budget that is estimated is $95,700 and the total time within which the project is expected to be completed is 10 months.

The scope management plan developed for the Online Stud Farm include initiation, scope planning, scope definition, scope verification and scope change control. The scope initiation plan deals with product and service description, strategic plan, project selection criteria.  10 different scope statements are considered for this particular project and based on those the project constraints should be developed. The tools and techniques considered for developing the scope of the project are Work Breakdown Structure and corrective actions.

  • People (and their roles), plus any extra personnel that is required for the project – Project screenshot.

Figure 1: Resources for the Online Stud Farm project

(Source: Created by author)

  • Technology - any hardware, network and software needs to support the team and your client.

Hardware

Server,  processor, sound card, hard drives, memory

Software

Server side scripting language, software license, cache memory, database

Network

Ethernet, bandwidth and network  to design the online system

  • Facilities - where will most of the teamwork be situated?

According to the facilities of the online project it has been found that, onsite will most of the teamwork be situated.

  • Other - for example, travel, training etc.

Travel Requirements

· Ticket

· Return ticket

· Unexpired Passport

· Unexpired Visa

Training Requirements

· Technical training

· Cultural training

· Non-technical training

Stakeholders

Using MS Project, develop a schedule using a high level Work Breakdown Structure (WBS). It should include:

  • Milestones for each phase and deliverable (4 marks)

      Milestone 1: completion of project initiation phase

0 days

Fri 8/10/18

Fri 8/10/18

7

Project manager

$0.00

      Milestone 2: completion of project planning phase

0 days

Wed 1/2/19

Wed 1/2/19

17

Project manager

$0.00

      Milestone 3: completion of project design phase

0 days

Mon 5/20/19

Mon 5/20/19

26

Project manager

$0.00

      Milestone 4: completion of project testing phase

0 days

Wed 6/26/19

Wed 6/26/19

31

Project manager

$0.00

      Milestone 5: completion of project closure phase

0 days

Fri 7/5/19

Fri 7/5/19

35

Project manager,team leader

$0.00

  • Activities / Tasks(4 marks)

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

Schedule for the Online Stud Farm management system

300 days

Mon 5/14/18

Fri 7/5/19

$95,648.00

   Project initiation phase

81 days

Mon 5/14/18

Mon 9/3/18

$28,584.00

      Current manual system of the OSFMS

20 days

Mon 5/14/18

Fri 6/8/18

operation manager

$4,800.00

      Budget preparation

12 days

Mon 6/11/18

Tue 6/26/18

2

finance manager

$3,360.00

      Requirement specification

15 days

Wed 6/27/18

Tue 7/17/18

3

network need

$4,200.00

      Resource specification

15 days

Wed 6/27/18

Tue 7/17/18

3

application programming manager

$3,600.00

      Resource gathering

16 days

Wed 7/18/18

Wed 8/8/18

4

system analyst

$3,840.00

      Project sponsors signing

18 days

Wed 7/18/18

Fri 8/10/18

5

sponsors

$5,040.00

      Project team development

18 days

Thu 8/9/18

Mon 9/3/18

5,6

system developer

$3,744.00

      Milestone 1: completion of project initiation phase

0 days

Fri 8/10/18

Fri 8/10/18

7

Project manager

$0.00

   Project planning phase

103 days

Mon 8/13/18

Wed 1/2/19

$31,000.00

      Communication management plan

12 days

Mon 8/13/18

Tue 8/28/18

9

HR manager

$2,688.00

      Risk management plan

15 days

Wed 8/29/18

Tue 9/18/18

11

business analyst

$3,600.00

      Contingency and procurement management planning

20 days

Wed 9/19/18

Tue 10/16/18

12

operation manager

$4,800.00

      Valuable insights and analytics identification

21 days

Wed 9/19/18

Wed 10/17/18

12

system analyst

$5,040.00

      Hardware requirement specification

22 days

Thu 10/18/18

Fri 11/16/18

13,14

hardware need

$5,632.00

      Software requirement specification

12 days

Mon 11/19/18

Tue 12/4/18

15

software need

$3,360.00

      Network requirement specification

21 days

Wed 12/5/18

Wed 1/2/19

16

network need

$5,880.00

      Milestone 2: completion of project planning phase

0 days

Wed 1/2/19

Wed 1/2/19

17

Project manager

$0.00

   Design and development phase

98 days

Thu 1/3/19

Mon 5/20/19

$27,216.00

      Online project prototype outlining

20 days

Thu 1/3/19

Wed 1/30/19

18

Project manager

$6,400.00

      Prototype designing

20 days

Thu 1/3/19

Wed 1/30/19

18

system designer

$4,000.00

      Interface modeling

12 days

Thu 1/31/19

Fri 2/15/19

20,21

application programming manager

$2,880.00

      Coding

12 days

Mon 2/18/19

Tue 3/5/19

22

system developer

$2,496.00

      SLA guidelines installation

12 days

Wed 3/6/19

Thu 3/21/19

23

application programming manager

$2,880.00

      Mobile interface design

20 days

Fri 3/22/19

Thu 4/18/19

24

system developer

$4,160.00

      GUI incorporation

22 days

Fri 4/19/19

Mon 5/20/19

25

system designer

$4,400.00

      Milestone 3: completion of project design phase

0 days

Mon 5/20/19

Mon 5/20/19

26

Project manager

$0.00

   Testing phase

27 days

Tue 5/21/19

Wed 6/26/19

$6,048.00

      Unit testing

10 days

Tue 5/21/19

Mon 6/3/19

27

system tester

$2,240.00

      Integrated testing

8 days

Tue 6/4/19

Thu 6/13/19

29

system tester

$1,792.00

      Acceptance testing

9 days

Fri 6/14/19

Wed 6/26/19

30

system tester

$2,016.00

      Milestone 4: completion of project testing phase

0 days

Wed 6/26/19

Wed 6/26/19

31

Project manager

$0.00

   Closure phase

7 days

Thu 6/27/19

Fri 7/5/19

$2,800.00

      Project Stakeholder signoff

4 days

Thu 6/27/19

Tue 7/2/19

32

business analyst,team leader

$2,080.00

      Final submission of the project document

3 days

Wed 7/3/19

Fri 7/5/19

34

system analyst

$720.00

      Milestone 5: completion of project closure phase

0 days

Fri 7/5/19

Fri 7/5/19

35

Project manager,team leader

$0.00

  • Resource Assignments(4 marks)

Task Name

Resource Names

Schedule for the Online Stud Farm management system

   Project initiation phase

      Current manual system of the OSFMS

operation manager

      Budget preparation

finance manager

      Requirement specification

network need

      Resource specification

application programming manager

      Resource gathering

system analyst

      Project sponsors signing

sponsors

      Project team development

system developer

      Milestone 1: completion of project initiation phase

Project manager

   Project planning phase

      Communication management plan

HR manager

      Risk management plan

business analyst

      Contingency and procurement management planning

operation manager

      Valuable insights and analytics identification

system analyst

      Hardware requirement specification

hardware need

      Software requirement specification

software need

      Network requirement specification

network need

      Milestone 2: completion of project planning phase

Project manager

   Design and development phase

      Online project prototype outlining

Project manager

      Prototype designing

system designer

      Interface modeling

application programming manager

      Coding

system developer

      SLA guidelines installation

application programming manager

      Mobile interface design

system developer

      GUI incorporation

system designer

      Milestone 3: completion of project design phase

Project manager

   Testing phase

      Unit testing

system tester

      Integrated testing

system tester

      Acceptance testing

system tester

      Milestone 4: completion of project testing phase

Project manager

   Closure phase

      Project Stakeholder signoff

business analyst, team leader

      Final submission of the project document

system analyst

      Milestone 5: completion of project closure phase

Project manager, team leader

  • Estimates for Each Activity / Task (3 Marks)

Figure 2: Gantt chart for the Online Stud Farm project

(Source: Created by author)

  • Assumptions - Document any assumptions you have made about the project (5 Marks)

The assumptions for this particular project are as follows:

  • The resources identified for the online Stud Farm are accurately utilized during the development of the project
  • The project manager is very much motivating and a perfect leader
  • The project manager has the ability to keep the project team members engaged to their job roles
  • The hardware, software and network suppliers have supplied necessary   products
  • List at least 5
  • Using the Risk Identification Framework as a basis, identify five risks to the project –
  • Analyse these risks, assign a risk to an appropriate member, and describe a strategy for the management of each specific risk. (10 Marks)
  • List at least 5

Risk ID

Description

Probability

Impact

Rate

Assigned To

Response Strategy

Threat or Opportunity

5

Distributed project team members

80%

5

High

Operation manager

Time to time meeting and video conference should be arranged and all the project team members should attend that meetings accordingly.  

It will minimize the intra and inter organizational conflict and increase team collaboration.

10

Lack of technical skill

90%

5

High

Project manager and team leader

At the project initiate phase, proper technical training should be organized by the project manager.

It will increase the skills and knowledge of the project team members

12

Improper communication

90%

5

High

HR manager

Open communication should be followed by the project team members.

Will develop innovative and creative ideas accordingly.

6

Inadequate resource

70%

3

Medium

Operation manager

Proper resources should be identified and collected from the successful implementation of the project.

Will help to complete the project  within the estimated budget

8

Improper time management

50%

1

Medium

Project developer

Proper time should be arranged based o project complexity and project background

Will help to gain competitive advantages

  • A short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client. – 3 Marks

The philosophy of the project development team is to deliver a user friendly online booking system for the consumers.

  • Develop and describe the following that your project team could implement to ensure quality;
    • A set of verification activities ( - 6 Marks)

Verification Activity

When?

Testing based on project

Design phase

Design review

Testing phase

Prototype review

Testing phase

Specific test phase review

Testing phase

Cost review

Testing phase

Testing phase

  • A set of validation activities (-6 Marks)

Validation Activity

When?

System testing

Testing phase

Implementation of project test case

Testing phase

Process development testing

Testing phase

Unit testing

Testing phase

Integrated testing

Testing phase

Acceptance testing

Testing phase

  1. To prepare for this task, you will be required to provide an annotated bibliography. – 3 marks

Pilepic, L., Simunic, M., & Car, T. (2015). Online hotel's sales strategies with emphasis on web booking. Journal of Technology Research, 6, 1.

This journal reflects the role of hotels dependency on the online intermediaries and their chosen distribution channel portfolios. The differences between the traditional sales channel and the role of social media network in the business growth are elaborated in these journals in terms of mixed marginal channel. The mixed management strategies are also developed and illustrated in this journal.

Heinemann, A., & Gebicka, A. (2016). Can Computers Form Cartels? About the Need for European Institutions to Revise the Concertation Doctrine in the Information Age. Journal of European Competition Law & Practice, 7(7), 431-441.

 This journal deals with the restrictive practices in computerized world. The way through which the online booking platform increases, the overall business efficiency and helps to gain high range profit revenue are also illustrated in this journal.

Haas, J. E. (2016). The influence of proportion positive online reviews and the disclosure of travel companion information on general trust in online reviews, perceived risk, booking intention, and WOM-intention (Master's thesis, University of Twente).

The essence of this particular journal is focused on influence of online booking system over the traditional booking. It is found that most of the consumers are currently dependent upon online booking due to its user friendliness.

  1. Develop a closure checklist that the project team will use to ensure that the project has been closed properly. – 3 marks Refer also to chapter 12
  • The testing of the developed online booking system is tested accurately
  • The documents are properly reviewed and approved by the project manager
  • The requirement traceability matrix is checked by the project manager
  • The issues and project risks are closed
  • The project document is hand overed
  • Both the on-job, technical and non technical trainings are completed
  1. Develop a project evaluation –outline and discuss how your project’s MOV will be evaluated. – 3 Marks chapter 12

Many measurable projects organizational values are estimated for the project such as customer, strategy, finance, social and operation. It is expected that with the successful implementation of these factors the project will deliver a secured user friendly online booking system to the consumers.

References

Bilgihan, A., Nusair, K., Okumus, F., & Cobanoglu, C. (2015). Applying flow theory to booking experiences: An integrated model in an online service context. Information & Management, 52(6), 668-678.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.

Eskerod, P., Huemann, M., & Savage, G. (2015). Project stakeholder management—past and present. Project Management Journal, 46(6), 6-14.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Haas, J. E. (2016). The influence of proportion positive online reviews and the disclosure of travel companion information on general trust in online reviews, perceived risk, booking intention, and WOM-intention (Master's thesis, University of Twente).

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.

Heinemann, A., & Gebicka, A. (2016). Can Computers Form Cartels? About the Need for European Institutions to Revise the Concertation Doctrine in the Information Age. Journal of European Competition Law & Practice, 7(7), 431-441.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Pilepic, L., Simunic, M., & Car, T. (2015). Online hotel's sales strategies with emphasis on web booking. Journal of Technology Research, 6, 1.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). Online Stud Farm Management System - Strategy, Stakeholders, And Scope Essay.. Retrieved from https://myassignmenthelp.com/free-samples/itc505-ict-project-management/acquires-knowledge-regarding-several.html.

"Online Stud Farm Management System - Strategy, Stakeholders, And Scope Essay.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/itc505-ict-project-management/acquires-knowledge-regarding-several.html.

My Assignment Help (2020) Online Stud Farm Management System - Strategy, Stakeholders, And Scope Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/acquires-knowledge-regarding-several.html
[Accessed 22 December 2024].

My Assignment Help. 'Online Stud Farm Management System - Strategy, Stakeholders, And Scope Essay.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/itc505-ict-project-management/acquires-knowledge-regarding-several.html> accessed 22 December 2024.

My Assignment Help. Online Stud Farm Management System - Strategy, Stakeholders, And Scope Essay. [Internet]. My Assignment Help. 2020 [cited 22 December 2024]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management/acquires-knowledge-regarding-several.html.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
close