Discuss about the System Implementation Project Plan for Strategic Marketing.
The project charted document has been made for the project of TOSIG's CRM implementation for customer information system. The completion of all project activities would result in forming the achievement of the final deliverable for the project. The project has comprised of analysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project. The analysis of the risk factors had tended for forming the development of the effective mitigation strategies.
Project Title: ‘TOSIG's CRM implementation for customer information system’
The development of the project documents, design deployment, system development, system deployment, and final test results are included in the scope of the TOSIG's CRM implementation for customer information system project. The project planning has included the use of the effective project management for the execution of project activities and attainment of final project deliverable.
The organization of TOSIG requires the implementation of the effective CRM suysyem for the management of the information of the various customers. The TOSIG provides insurance to various customers for buildings, fencing, stock yards, storage silos and machinery, and even crops. They had been following their simple information processing and the 150 agents would have to manage the information. However, it would require the use of CRM system for improving the management of information for the customers.
The project of TOSIG's CRM implementation for customer information system is developed for the aligning effective project activities. The completion of all these phases would result in forming the achievement of the final deliverable for the project. The completed project would be divided into 6 phases. The analysis and document phase would include the activities of requirement analysis, accumulation of resources, charter documentation, documents submission, signing of the documents, and analysis and documentation phase completion. The ui and system design would include the activities of platform selection, outline of ui and system is developed, development of UI design, development of system design, feasibility analysis, and design phase completion. The development of system would include the activities of database creation, development of UI, development of functions, development of programs, integration of the system, and system development completion. The deployment of system would include the activities of planning of the system development, implementing the system, integrating the system, training the staff, and deployment phase completed. The test of system would include the activities of alpha test, white box testing, simulation testing, UI operatibility testing, and test phase completed. The documentation for project would include the activities of final reports are made, submission of reports, signing of the documents, and closure of project.
Project Phases
The project of TOSIG's CRM implementation for customer information system is developed for the aligning the six phases of Analysis and Document Phase, UI and system design, Development of System, Deployment of System, Test of System, and Documentation for project. The completion of all these phases would result in forming the achievement of the final deliverable for the project. The milestones of the project is shown in the following project schedule by highlighting it,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
TOSIG's CRM implementation for customer information system |
100 days |
Mon 7/16/18 |
Fri 11/30/18 |
1 |
Analysis and Document Phase |
11 days |
Mon 7/16/18 |
Mon 7/30/18 |
1.1 |
Requirement Analysis |
2 days |
Mon 7/16/18 |
Tue 7/17/18 |
1.2 |
Accumulation of Resources |
4 days |
Wed 7/18/18 |
Mon 7/23/18 |
1.3 |
Charter Documentation |
3 days |
Tue 7/24/18 |
Thu 7/26/18 |
1.4 |
Documents Submission |
1 day |
Fri 7/27/18 |
Fri 7/27/18 |
1.5 |
Signing of the documents |
1 day |
Mon 7/30/18 |
Mon 7/30/18 |
M1 |
Analysis and Documentation Phase Completion |
0 days |
Mon 7/30/18 |
Mon 7/30/18 |
2 |
UI and system design |
20 days |
Tue 7/31/18 |
Mon 8/27/18 |
2.1 |
Platform Selection |
2 days |
Tue 7/31/18 |
Wed 8/1/18 |
2.2 |
Outline of UI and system is developed |
4 days |
Thu 8/2/18 |
Tue 8/7/18 |
2.3 |
Development of UI design |
5 days |
Wed 8/8/18 |
Tue 8/14/18 |
2.4 |
Development of System design |
5 days |
Wed 8/15/18 |
Tue 8/21/18 |
2.5 |
Feasibility Analysis |
4 days |
Wed 8/22/18 |
Mon 8/27/18 |
M2 |
Design Phase Completion |
0 days |
Mon 8/27/18 |
Mon 8/27/18 |
3 |
Development of System |
35 days |
Tue 8/28/18 |
Mon 10/15/18 |
3.1 |
Database Creation |
5 days |
Tue 8/28/18 |
Mon 9/3/18 |
3.2 |
Development of UI |
8 days |
Tue 9/4/18 |
Thu 9/13/18 |
3.3 |
Development of functions |
6 days |
Fri 9/14/18 |
Fri 9/21/18 |
3.4 |
Development of Programs |
10 days |
Mon 9/24/18 |
Fri 10/5/18 |
3.5 |
Integration of the system |
6 days |
Mon 10/8/18 |
Mon 10/15/18 |
M3 |
System Development Completion |
0 days |
Mon 10/15/18 |
Mon 10/15/18 |
4 |
Deployment of System |
16 days |
Tue 10/16/18 |
Tue 11/6/18 |
4.1 |
Planning of the system development |
3 days |
Tue 10/16/18 |
Thu 10/18/18 |
4.2 |
Implementing the system |
2 days |
Fri 10/19/18 |
Mon 10/22/18 |
4.3 |
Integrating the system |
4 days |
Tue 10/23/18 |
Fri 10/26/18 |
4.4 |
Training the staff |
7 days |
Mon 10/29/18 |
Tue 11/6/18 |
M4 |
Deployment Phase Completed |
0 days |
Tue 11/6/18 |
Tue 11/6/18 |
5 |
Test of System |
12 days |
Wed 11/7/18 |
Thu 11/22/18 |
5.1 |
Alpha Test |
3 days |
Wed 11/7/18 |
Fri 11/9/18 |
5.2 |
White Box Testing |
3 days |
Mon 11/12/18 |
Wed 11/14/18 |
5.3 |
Simulation Testing |
3 days |
Thu 11/15/18 |
Mon 11/19/18 |
5.4 |
UI Operatibility Testing |
3 days |
Tue 11/20/18 |
Thu 11/22/18 |
M5 |
Test Phase Completed |
0 days |
Thu 11/22/18 |
Thu 11/22/18 |
6 |
Documentation for project |
6 days |
Fri 11/23/18 |
Fri 11/30/18 |
6.1 |
Final Reports are made |
4 days |
Fri 11/23/18 |
Wed 11/28/18 |
6.2 |
Submission of reports |
1 day |
Thu 11/29/18 |
Thu 11/29/18 |
6.3 |
Signing of the documents |
1 day |
Fri 11/30/18 |
Fri 11/30/18 |
M6 |
Closure of Project |
0 days |
Fri 11/30/18 |
Fri 11/30/18 |
Table 1: Project Milestones in Project Schedule
The acceptance criteria for the completion of each of the milestones of analysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project. These milestones must meet some specific criteria for achievement of the final project deliverable. The acceptance criteria for the milestones are,
Criteria for analysis and documentation phase completion: The analysis and documentation phase completion would be dependent on the project manager signing the documents and approving the initiation of the project.
Criteria for design phase completion: The design phase completion would be dependent on the implication of the effective simulation of the design developed for the
Criteria for system development completion: The functions of TOSIG must be compatible with the CRM system developed for the implication of the improved operation development.
Criteria for deployment phase completed: The implementation of the CRM system would be based on the effective integration of the activities favoring the organization’s activities.
Criteria for test phase completed: The test phase would be based on the implication of the activities forming the analysis of the quality and achievement of the expected test results.
Criteria for closure of project: The final reports would be deployed for the effective alignment of the operations and documentation process that can be utilized for future projects.
The project of TOSIG's CRM implementation for customer information system is an IT based project and the completion of the project would have to face several issues and problems. The analysis of the risk factors had tended for forming the development of the effective mitigation strategies. The following table would show the various risk factors for the project,
Risk Factor |
Risk Classification |
Risk Mitigation Strategy |
Equipments Failure |
Technical |
Reduce |
Shortage of the Resources |
Financial |
Avoid |
Overtime of the activities |
Operational |
Accept |
Design Flaws |
Technical |
Transfer |
Loss of data |
Accidental |
Mitigate |
The project of TOSIG's CRM implementation for customer information system would align with the use of the effective IT management principles and operations. The assumptions of the project are,
- Resources required for the completion of the project would be available and can be aligned with the implication of the effective alignment of the operations
- Project would be completed in the estimated time and resources accumulated in the project
- The team members would not face any quarrel or conflict among each other
The estimated budget, calculated time, and the expected quality of the system operations are the constraints of the project of TOSIG's CRM implementation for customer information system.
Type |
Stakeholders |
Role |
Governance |
Sponsor, Client, Steering Committee, |
Making decisions in the project |
Managerial |
Project Manager and Contractor |
Management of the project activities |
Operational |
Complete project team, suppliers, and some external workers |
Carrying out all the activities of the project |
Conclusion
The project charted had been developed in the project and it had been helpful for conveying information to other stakeholders. The project of TOSIG's CRM implementation for customer information system was developed for the aligning the six phases of Analysis and Document Phase, UI and system design, Development of System, Deployment of System, Test of System, and Documentation for project. The completion of all these phases had resulted in forming the achievement of the final deliverable for the project. The charted had highlighted the acceptance criteria required for the completion of each of the milestones of analysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project. The analysis of the risk factors had tended for forming the development of the effective mitigation strategies.
Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.
Chen, Y.S., Wu, C., Chu, H.H., Lin, C.K. and Chuang, H.M., 2018. Analysis of performance measures in cloud-based ubiquitous SaaS CRM project systems. The Journal of Supercomputing, 74(3), pp.1132-1156.
Eichorn, F.L., 2018. Internal customer relationship management (IntCRM) a framework for achieving customer relationship management from the inside out. Management, 2, p.1.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Jaber, F. and Simkin, L., 2017. Unpicking antecedents of CRM adoption: a two-stage model. Journal of Strategic Marketing, 25(5-6), pp.475-494.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education India.
Orenga-Roglá, S. and Chalmeta, R., 2016. Social customer relationship management: taking advantage of Web 2.0 and Big Data technologies. SpringerPlus, 5(1), p.1462.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
To export a reference to this article please select a referencing stye below:
My Assignment Help. (2019). TOSIG's CRM Implementation For Customer Information System Essay.. Retrieved from https://myassignmenthelp.com/free-samples/system-implementation-project-plan-strategic-marketing.
"TOSIG's CRM Implementation For Customer Information System Essay.." My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/system-implementation-project-plan-strategic-marketing.
My Assignment Help (2019) TOSIG's CRM Implementation For Customer Information System Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/system-implementation-project-plan-strategic-marketing
[Accessed 22 November 2024].