Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

The purpose of the project is to practice some of the aspects of project planning and control in the context of uncertainty. The project is to be done individually.

1)Based on the results of previous assignment on this module, your prior work experience or personal preferences pick a subject area for a project (see list of proposed subject areas below).

2)As a representative of an organisation commissioning the above project:

a)Define a reasonably achievable scope and deliverables – use your judgement to set the time constraints, assume money is “no object”.

b)Construct a Request For Proposal (RFP) that is to be sent out to potential contract bidders. Refer to the lecture slides for the standard/required components of the document.

3)As a contractor who has just won the tender for the above project create a Project Charter to be used by the project team. This should at least include the following elements:

a)Work Breakdown Structure (WBS)

b)Estimate of time and resources needed (staff, materials, etc.)

c)Network / Critical Path analysis and Gantt Diagram

d)Budget

e)Quality Assurance plan

f)Risk Management plan

Objective of the Project

This project is based on the development and implementation of a new strategic path for Netflix. Netflix is an online video streaming company that provides services to over 150 countries around the world. Initially, the company started out with video rentals service where the customers were provided with online copies of DVDs on rental basis. However, the company slowly adopted movie streaming services that could be viewed if the users subscribed to the services by paying a certain amount of money. With further development in the customer base and significant increase in popularity, Netflix also started streaming TV series that they produced in their own production house.

In spite of the popularity of Netflix around the world, users are slowly becoming concerned about the extremely high subscription prices. Furthermore, availability of free download websites like torrents provide better alternative to the users rather than paying high amount of subscription money to Netflix every month. Hence, Netflix needs new business strategy to solve these problems and maintain the current hold in video streaming market. In this report, a project charter has provided that aims to address the project plan requirements for deployment of new business strategy of Netflix.

This project is based on the development and implementation of a new strategic plan for Netflix in order to address the issues currently arising in their existing business strategies and policies. It has been found that in spite of massive popularity of Netflix all over the world as well as increasing number of subscriptions every year, there is also growing concern due to the high subscription prices that the users have to pay. From an analysis, it has been found that the increase in the number of customers for 2017 has been much less than the previous year. This is mainly because there are other alternatives like pirated movie websites, torrents and other sites where the users can download the TV series or movies for free or at minimal costs whereas at Netflix website / app, they have to pay very high subscription fees each month. On the other hand, Netflix being only a video streaming business has to recover a huge amount of expenses encountered during the production of the originals (TV series and movies). Netflix has also developed its own production house where the Netflix Originals movies and series are filmed. These costs have to be recovered through streaming revenue and the subscription money paid by the customers.

Scope of the Project

The project scope includes the following.

  • Analysis of the current marketing and business strategy of Netflix is within the scope of the project.
  • Analysis of the current business issues faced by Netflix is within the scope of the project.
  • Identification of possible solutions for addressing the issues for Netflix is within the scope of the project.
  • Recommendation of the most feasible solution for Netflix is within the scope of the project.

Accordingly, the objectives of the project are as follows.

  • To deliver a detailed report on the current system, business strategies and issues faced by Netflix
  • To prepare a project plan on the implementation of the newly proposed business strategy
  • To deliver a project model that can be used for approach towards project execution
  • To use budget and resources for successfully executing the project

The list of stakeholders and their duties for this project is prepared in the following table.

Name

Designation

Role

Reed Hastings

CEO / Project Manager

To approve, manage, control and supervise the project

Jonathan Hendricks

Finance Manager

To manage and allocate project funds

David Thompson

Business Strategies Manager

To manage and control project as per company’s business strategies and alignment

James Hudson

Systems Manager

To manage hardware and software operations and implementations

Matias Hernandez

Procurement Manager

To procure necessary resources required for the purpose of the project

Eddie Charlton

Consultancy Manager

To consult with various agencies for implementation of new systems like ERP, SAP, etc.

The work breakdown structure for the project is shown in the following diagram.

Figure 1: Work Breakdown Structure of the Project

(Source: Created by Author)

The estimated project schedule and the duties of the stakeholders in the project are shown in the following table.

Task Name

Duration

Start

Finish

Resource Names

Development and Implementation of New Business System for Netflix

300 days

Mon 02-04-18

Fri 24-05-19

   Survey, Discussion, Analysis

66 days

Mon 02-04-18

Mon 02-07-18

      Initial Survey

15 days

Mon 02-04-18

Fri 20-04-18

Business Strategies Manager, Project Manager, Systems Manager

      Collection of Survey Data

15 days

Mon 23-04-18

Fri 11-05-18

Business Strategies Manager, Project Manager, Systems Manager

      Analysis of Survey Data

30 days

Mon 14-05-18

Fri 22-06-18

Business Strategies Manager, Project Manager, Systems Manager

      Board Meeting

2 days

Mon 25-06-18

Tue 26-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Identification of Issues

2 days

Wed 27-06-18

Thu 28-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Identification of the Grievances of the Customers

1 day

Fri 29-06-18

Fri 29-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Identification of Possible Solutions

1 day

Fri 29-06-18

Fri 29-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Checking Business Feasibility of the Solutions

1 day

Fri 29-06-18

Fri 29-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Reaching a Final Conclusion

1 day

Fri 29-06-18

Fri 29-06-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      Decide a Solution for Implementation

1 day

Mon 02-07-18

Mon 02-07-18

Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager

      End of First Meeting

0 days

Mon 02-07-18

Mon 02-07-18

   Second Meeting and Approval

9 days

Tue 03-07-18

Fri 13-07-18

      Second Board Meeting

1 day

Tue 03-07-18

Tue 03-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Discussion Regarding the Chosen Plan

1 day

Wed 04-07-18

Wed 04-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Estimation of Overall Budget for Project

1 day

Thu 05-07-18

Thu 05-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Estimation of Overall Timeline for Project

1 day

Fri 06-07-18

Fri 06-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Discussion Regarding Project Feasibility

1 day

Mon 09-07-18

Mon 09-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Preparation of Project Proposal

4 days

Tue 10-07-18

Fri 13-07-18

Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager

      Project Approval

0 days

Fri 13-07-18

Fri 13-07-18

   Planning for the Project

29 days

Mon 16-07-18

Thu 23-08-18

      Development of Project Charter

4 days

Mon 16-07-18

Thu 19-07-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Preparation of Accurate Project Timeline

2 days

Fri 20-07-18

Mon 23-07-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Preparation of Accurate Project Budget

2 days

Tue 24-07-18

Wed 25-07-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Estimation of Resources Required for the Project

1 day

Thu 26-07-18

Thu 26-07-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Develop and Approve Project Scope

1 day

Fri 27-07-18

Fri 27-07-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Meet with Business Solutions Consultancy

5 days

Mon 30-07-18

Fri 03-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Prepare a Deployment Plan

3 days

Mon 06-08-18

Wed 08-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Analyze Risks Associated with Project

5 days

Thu 09-08-18

Wed 15-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Prepare Addressing Plan for the Risks

2 days

Thu 16-08-18

Fri 17-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Final Feasibility Tests

3 days

Mon 20-08-18

Wed 22-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Project Ready for Initiation

1 day

Thu 23-08-18

Thu 23-08-18

Business Strategies Manager, Consultancy Manager, Systems Manager

      Go Ahead from CEO

0 days

Thu 23-08-18

Thu 23-08-18

   Initiation of the Project

30 days

Fri 24-08-18

Thu 04-10-18

      Appointment of Project Stakeholders

5 days

Fri 24-08-18

Thu 30-08-18

Project Manager

      Deployment of Project Team

2 days

Fri 31-08-18

Mon 03-09-18

Project Team Leader

      Allocate Duties to Each Team Member and Stakeholder

1 day

Tue 04-09-18

Tue 04-09-18

Project Team Leader

      Hand Over Project Schedule to the Stakeholders

1 day

Wed 05-09-18

Wed 05-09-18

Project Manager

      Procurement of Project Funds

5 days

Thu 06-09-18

Wed 12-09-18

Procurement Manager

      Provide the Funds to the Finance Manager's Account

1 day

Thu 13-09-18

Thu 13-09-18

Procurement Manager

      Recruit System Development Team

3 days

Fri 14-09-18

Tue 18-09-18

Systems Manager

      Team Meeting

1 day

Wed 19-09-18

Wed 19-09-18

Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team

      Discuss Project Roadmap

1 day

Thu 20-09-18

Thu 20-09-18

Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team

      Selection of Personal Roles and Responsibilities in Project

1 day

Fri 21-09-18

Fri 21-09-18

Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team

      Allocation of Budget to the Teams

2 days

Mon 24-09-18

Tue 25-09-18

Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team

      Contact Vendor for Resources

1 day

Wed 26-09-18

Wed 26-09-18

Procurement Manager

      Procurement of the Resources

5 days

Thu 27-09-18

Wed 03-10-18

Procurement Manager

      Allocation of Resources

1 day

Thu 04-10-18

Thu 04-10-18

Project Team Leader

      Teams Ready to Go Ahead

0 days

Thu 04-10-18

Thu 04-10-18

   Project Execution

156 days

Fri 05-10-18

Fri 10-05-19

      Analysis of Existing System by System Developer

5 days

Fri 05-10-18

Thu 11-10-18

System Development Team

      Subscription to AWS

5 days

Fri 12-10-18

Thu 18-10-18

System Development Team

      Connecting the Existing Business Server with AWS

4 days

Fri 19-10-18

Wed 24-10-18

System Development Team

      Test the System with AWS

5 days

Thu 25-10-18

Wed 31-10-18

System Development Team, Testing Team

      Upgrade Hardware

4 days

Thu 01-11-18

Tue 06-11-18

System Development Team, Updated Hardware[1]

      Upgrade Software

5 days

Wed 07-11-18

Tue 13-11-18

System Development Team, Software[1]

      Develop Business ERP Solution

30 days

Wed 14-11-18

Tue 25-12-18

System Development Team

      Create UI for the ERP software

10 days

Wed 26-12-18

Tue 08-01-19

System Development Team

      Add Features to the Software

15 days

Wed 09-01-19

Tue 29-01-19

System Development Team

      Test the Software Demo Version

10 days

Wed 30-01-19

Tue 12-02-19

System Development Team, Testing Team

      Make Internal Changes and Upgrades

15 days

Wed 13-02-19

Tue 05-03-19

System Development Team

      Debugging

7 days

Wed 06-03-19

Thu 14-03-19

System Development Team

      Deploy Strong System Firewall

6 days

Fri 15-03-19

Fri 22-03-19

System Development Team

      Test the system

10 days

Mon 25-03-19

Fri 05-04-19

System Development Team, Testing Team

      Create New Exclusive Netflix Business Portal

15 days

Mon 08-04-19

Fri 26-04-19

System Development Team

      Final Testing and Changes

10 days

Mon 29-04-19

Fri 10-05-19

System Development Team, Testing Team

      Handover to Project Authority

0 days

Fri 10-05-19

Fri 10-05-19

   Closing and Sign Off

10 days

Mon 13-05-19

Fri 24-05-19

      Post Project Appraisal and Review

4 days

Mon 13-05-19

Thu 16-05-19

Project Manager

      Prepare Project Report

5 days

Fri 17-05-19

Thu 23-05-19

Project Team Leader

      Signoff from Stakeholders and Project Manager

1 day

Fri 24-05-19

Fri 24-05-19

Business Strategies Manager, Consultancy Manager, Finance Manager, Procurement Manager, Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team

      Closing of the Project

0 days

Fri 24-05-19

Fri 24-05-19

The resources required for the project including their standard costs and charges are shown in the following table.

Resource Name

Type

Max. Units

Std. Rate

Ovt. Rate

Project Manager

Work

100%

$400.00/hr

$0.00/hr

Finance Manager

Work

100%

$250.00/hr

$0.00/hr

Business Strategies Manager

Work

100%

$325.00/hr

$0.00/hr

Systems Manager

Work

100%

$325.00/hr

$0.00/hr

Procurement Manager

Work

100%

$225.00/hr

$0.00/hr

Consultancy Manager

Work

100%

$250.00/hr

$0.00/hr

Project Team Leader

Work

100%

$175.00/hr

$0.00/hr

System Development Team

Work

100%

$350.00/hr

$0.00/hr

Testing Team

Work

100%

$275.00/hr

$0.00/hr

Updated Hardware

Material

$150,000.00

Software

Material

$125,000.00

The Gantt chart of the project is shown in the following diagram.

Figure 2: Gantt Chart of the Project

(Source: Created by Author)

The critical path analysis is shown in the following diagram.

Figure 3: Critical Path Analysis of the Project

(Source: Created by Author)

The overall estimated budget for the project is shown in the following table.

Resource

Estimated Budget

Human Resource (From Gantt Chart)

$ 1,587,400

Hardware Costs

$ 150,000

Software Costs

$ 125,000

Development Costs

$ 200,000

Testing Costs

$ 125,000

Business Implementation Costs

$ 165,000

TOTAL

$ 2,352,400

Quality assurance plan is required in every project in order to ensure the project meets the best quality standards. Furthermore, for this large scale and high budget project for Netflix, quality assurance plan must be prepared before the project is executed.

The list of policies and requirements to be following during quality assurance is as follows.

  • The procured hardware must be of the most updated versions so that they need not be changed for the next 5 years.
  • The software used for development of ERP must be up to date and of the original authentic version.
  • The business portal should have all the necessary functions as required within one easily understandable dashboard.
  • The AWS must be connected to the central database of the company so that all the necessary information and data can be migrated to the cloud.
  • The newly deployed system and business strategy must be able to reduce operational and other costs significantly.

The possible risks associated with the project as well as suitable management plans are shown in the following table.

Risk Details

Chance of Occurrence

Impact on Project

Management Plan

Budget Overshoot, caused due to scope creep or excessive overspend during the project

High

Very High

Prepare accurate budget plan during planning, try to remain within the limits of the allocated budget to complete the works in the project

Failed Implementation, due to lack of quality resources, fraud consultancy and others

Medium

Extreme

Check background details of the consultancy before hiring, conduct quality check on the resources before purchase

Cyber Attack, due to lack of system firewall, external attackers, malwares and others may enter into and harm the company database

Very High

Extreme

Use strong system firewalls, cyber security softwares, system cleaners and others to minimize chances of cyber attacks

 

Conclusion

In this report, a detailed project plan has been provided for the new strategic development of Netflix. As per the analysis of the existing issues and problems faced by Netflix, deployment of an ERP system as well as migration of the entire database into cloud have been suggested as part of the recommendation for the project. Following the scope and objectives of the project, an estimated budget has been developed along with a rough schedule. Furthermore, stakeholder analysis, quality assurance and risk management plans have also been provided. However, it should be noted that this is only a rough initial plan that needs to be further developed with more accurate estimations before it can be used as the plan of the actual project.

References

Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.

Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.

Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L.P., 2014. Critical chain project management. Artech House.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.

Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.

Turner, R., 2016. Gower handbook of project management. Routledge.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Project Stakeholder Analysis

The resources required for the project including their standard costs and charges are shown in the following table.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). Project Planning And Control In The Context Of Uncertainty Is Crucial For Effective Essay.. Retrieved from https://myassignmenthelp.com/free-samples/bb7019-strategic-project-management-and-practice.

"Project Planning And Control In The Context Of Uncertainty Is Crucial For Effective Essay.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/bb7019-strategic-project-management-and-practice.

My Assignment Help (2020) Project Planning And Control In The Context Of Uncertainty Is Crucial For Effective Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/bb7019-strategic-project-management-and-practice
[Accessed 02 May 2024].

My Assignment Help. 'Project Planning And Control In The Context Of Uncertainty Is Crucial For Effective Essay.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/bb7019-strategic-project-management-and-practice> accessed 02 May 2024.

My Assignment Help. Project Planning And Control In The Context Of Uncertainty Is Crucial For Effective Essay. [Internet]. My Assignment Help. 2020 [cited 02 May 2024]. Available from: https://myassignmenthelp.com/free-samples/bb7019-strategic-project-management-and-practice.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close