Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

Etimate the cost of a variation to provide the front fence as detailed on the plan. As the work is minor in extent, there is no need to measure in trade order but the tasks should be sequenced as they would occur in the construction process. Your builder’s bill should be prepared in P10 format.

You can assume the site has been surveyed and identified with survey pegs to allow an easy set-out for the construction of the fence. Your builder’s bill should include the costing of the tasks identified and include a builder’s margin and GST. You should also nominate an appropriate ‘extension of time’ for the contract period to be extended if you believe it is warranted.

When preparing your bill of quantities you can allow the following monetary sums:

  • Face bricks $700.00 per thousand – supply and delivery.        
  • Sandstone capping $200.00 per metre (270 wide and 50mm thick) allow 20mm                             border (overhang) at each edge.
  • Metal panels $100.00 per metre supply and delivery

Helpful notes:

  • Remove and tip all excavated material – you will need to make some assumptions for this task
  • Provide adequate safety and security during the construction process
  • Remove all rubbish on completion of the works
  • Ignore all previous indicators of the cost of this exercise. They have not been correctly estimated, nor do they include the pricing information provided above.

Reflecting on your answer for Part A, please answer the following questions:

  1. Explain the basis of your calculation of the labour component of installing the metal panels
  2. As this is a variation, will all the labour components be priced at the same rate as the work in the main project which has been tendered on? Explain your answer.
  3. Charge out rates for directly employed labour can be higher than sub-contract rates. Have you utilised any directly employed labour in your costing? If so, nominate the component and explain how you costed the rate. Note: at the very least there should be a cost for supervision of the work.
  4. Is there any danger in the work associated with procuring and fixing the sandstone capping? Elaborate on your answer and explain how you will cover any risks identified.

 

  1. Briefly discuss the benefit of estimating the cost of a task by separately costing the materials, labour and plant required.
  2. List the considerations that would affect your decision on whether to tender on a project or not.
  3. When estimating the cost of excavation, what are the factors which determine the size of plant needed to complete the task?
  4. What does the builder’s margin include?
  5. Why do engineering drawings take precedence over architectural drawings when estimating and constructing a project?
  6. Why are many components of the construction process sub-contracted out to other parties?
  7. Discuss the issues with obtaining quotations from specialist trades or companies with whom you have no previous association and no direct knowledge of.
  8. List the on-costs associated with directly employed labour.
  9. List five (5) conditions of a contract which may produce a cost on the project and therefore should be included in your bill of quantities.
Discuss how you would calculate the labour cost to complete a task when you have no knowledge of the time involved to carry out the work.

Part A

Trade…………………………..                                                 Reference…………………….

 

 

Unit

QTY

   Total

  $

1.0

1.1

 

 

 

 

1.2

 

 

 

1.3

 

1.4

 

 

 

 

1.5

PRELIMINARIES

Carry out the data checks of the  that are required to be done on the availed data and the information which is relevant to the project mostly regarding the existing conditions, site and all the tasks that are to be undertaken

To generate with 2 copies of the main drawing, a soft copy which should be stored in an open drive and a hard copy labelled the details of the project design and the specifications of the client.

Protecting all the existing finishes in the areas that are to be affected by the construction and carefully taking note of the impacts that the construction process structures which are existing Invalid source specified..

 Clearing and clearance of the areas where the face is to be constructed before the construction starts and when it will be completed.

 

2.0

CONSTRUCTION WORKS

Supply of equipment, tools, labours, professional, machinery, materials supervision and all that is required in the construction of front face.

Note: Refer drawing for details – Project 1 attached

2.1

Demolishing of the old existing structures on site , clearing of flora and garbage from the

2.2

Excavating the ground for the purpose of the laying the foundation the soli which are excavated some is discarded while the other is stored to be used in backfilling

 

2.3

Construction of Brick Fence footage of 600 mm thick x 150 mm (W) on-site concrete British Reinforced Concrete A7 sides formwork and concrete G25 and others to complete.

 

2.4

Construction of Brick Fence infill metal panels for installation between columns. Size of the metal panel:-

a)      50 mm (L) x 75 mm (W) x 1200 mm (H) Invalid source specified.

 

2.5

Construct 150 mm thick x 300 mm (W) x 300 mm (L) concrete columns cast on site G25 as footage and British Reinforced Concrete A7 sides’ formwork and for the brick fence.

 

2.6

Supply and install 225 mm (L) x 112.5 mm (W) x 75 mm (H) Face bricks

$700 per thousand supply & delivery

 

2.7

Supply and constructing of 2500 mm (W) x 2400 mm (H) steel garage door

One no

$300 per piece

 

Supply and install 300 mm (L) x 300 mm (W) x 20 mm (H) sandstone capping

20 no

$200 per meter at each edge

 

2.8

Close turf affected area to include Backfilling side of ground beam spread level.

All the affected areas should be filled back and levelled.

LS

2.9

Site cleaning and clearance after the construction of the front face.

That involves replanting the trees which were destroyed.

LS

3.0

Total Cost for all the  Items 1.0-2.9

4.0

 

ADDITIONAL REQUIREMENTS

Items that are meant to meet the specification of the project but were not included in the part of the technical specifications they include.

LS

LS

LS

LS

 

Total Cost for Item 4.0

  1. Labour required for the instalment of the metal panels is based on the length of the face to be installed. The labour charges which were calculated were done based on the perimeter of the front fence which was to be constructed.
  2. The labour of the project will be priced at the same rate. If the project was tendered and adjusted on the original document the process of construction would be slowed down resulting to delays. There was the deployment of skilled and unskilled labour from the subcontractors, and the main contractor was to be in charge of the subcontractors.
  3. The construction of the project was to be halted due to the delays of supply of the sandstone capping. The sandstone capping was manufactured by precast hence there was the risk of delays to supply to the site. The project was to halt till the sandstone capping were yet to be delivered. This risk can be solved by ensuring that the suppliers are informed on the urgency under which the materials should be delivered to the site. Also to reduce the risks it is important to ensure close supervision of the process of delivery of the materials to the site.
  1. The benefit of estimating the cost of a task.
  • There are many benefits which are associated with the cost estimation before the construction of the project as discussed below.
  • The quantity and quality of the materials which are required for the task to be carried out can be full and accurately determined before the construction of the project starts. That gives the client a better idea of how much resources are required for the project to be completed.
  • The flexibility of the task improves. Determining the number of materials, labour and other resources which will be required for the task to be completed always there is a room which is left for adjustments. The adjustments which will be required to be implemented during the construction stage would have been catered for thus improving the flexibility of the task.
  • The delays are reduced. Estimating the cost of the project before construction allows one to know the estimated amount of material, labour, and other resources which will be required during the construction period. The client or contractor assembles all the resources which are required before construction the different parties who also will be involved in the construction are assigned their task, and their deadlines are set of which they work to beat in that way the delays are reduced.
  • The administration of the task is fastened. The project manager or the client knows what exactly is to be done in the project and what is needed. The project manager can come up with the schedules on how the different tasks can be completed before the construction of the project starts.
  • The overall quality of the task improves because it allows the client or project manager to plan in advance on how to bring on board various experts into the implementation of the project.
  • It makes it easier to control (cost) finance of the project. Each of the subcontractor during the agreement is allocated the amount of money which will enable him/her to accomplish the work which is allocated to them. It is then the responsibility of the subcontractor to ensure that the finance and the resources which were allocated to him/her have been managed well to accomplish the intended task.
  • It enables the main contractor come up with system for proper labour allocation and equipment maintenance. Once the agreement has been reached between the main contractor and the subcontractors each of the subcontractor knows the exact amount of labour required to enable him/her to accomplish the task which was assigned to him/her. The subcontractor is responsible to maintain the equipment which are used by the subcontractors instead each of the subcontractors is responsible for his/her equipment maintenance. That reduces the work of the main contractor in maintaining the equipment.
  1. Considerations which decision making on whether to tender on a project or not.
  • The availability of labour, materials, and equipment which are required for the project to be completed have a great impact on whether one is to tender the project or not.
  • The available time for the project to be implemented. Time plays a very important role in decision making on whether to tender or not. In most cases, clients tend to tender their projects when they have insufficient time.
  • The size and purpose of the project. Most people tend to tender big projects which they cannot manage to execute on their own. Small projects in mostly are carried out by the owners as they are easy to implement.
  • The budget of the project. This is the fundamental factor which determines if one is to tender or not. The decision of tendering has arrived if one has enough resources to tender out.
  • The type of the project. The input towards the project is greatly influenced by the type of the project. The public and commercial projects will tend to require more materials, labour and other resources which forces one to tend the project out. Most of the small private projects are in most cases administered by the clients because they require very little input which the client can manage on his/her own without necessary tendering out.
  • The available resources greatly depend on the size of the plant to be acquired to accomplish the excavation process on site. In cases where the client or the contractor has enough resources, he or she can be able to acquire a large and powerful plant to carry out the excavation process.
  1. Factors influencing the size of the plant required to complete the task.
  • The type and size of the project.
  • Massive projects are known to require deep extractions, unlike the small projects. Deep extractions require large machines to do the excavations. Some of the projects which have basements will require more excavations than the projects which do not have excavations due to that they will require large and power machinery to enable them to accomplish the depth and size of the excavation.
  • The depth and size of the excavation.
  • The size of the hole to be excavated has a great impact on the size of the machinery and equipment which will be required to carry out the task. Large excavations in most cases require large and powerful types of machinery unlike the small excavations.
  • The volume of the waste soil that has to be excavated.
  • The size and ability of the machinery which are required to do the excavations greatly depend on the amount of soil that has to be excavated. Large machines are required to remove large amounts of soils such as in the cases where the foundation of the project requires removal of all the black cotton soils before laying the foundation.
  • Type of soil to be excavated.
  • The characteristics of the soil to be excavated has a great impact on the size of the plant required to complete the excavation task. Some soils characteristics are known to complicate the excavations process thus requiring the large plant to do the excavations.
  1. The builder’s margin contents include
  • Setout
  • Progressive cleaning
  • Temporary services
  • Insurances
  • Council inspection
  • Supervision
  • Rubbish removal
  • Access
  • Safety equipment
  • Site fencing
  1. Reasons why engineering drawings take precedence over architectural drawings when estimating and constructing a project.
  • The engineering drawings can be used in the verification of the bill of quantities which have been generated whereby the architectural drawings cannot be used in the verification process.
  • The ideas in the engineering drawings are logically presented which makes them be consistent. The consistence in the engineering drawings allows the various cost estimators to complete various parts of the quantity survey, or be continued later.
  • Engineering drawings tend to be the same globally that makes it easier in coming up with a system through which the engineering drawings can be used in the estimation of the cost of the project. The architectural drawing lacks that aspect of uniformity which makes it very difficult in estimating the cost of the project.
  • The engineering drawings allow an engineer to be involved in generating a structure or system that will assist in researching and developing alternative methods that will result in cost optimization, unlike the architectural drawings.
  • The engineering drawings are internationally accepted to be used in the cost and duration estimation of different construction standard. On the other hand, the architectural drawings are not internationally acceptable in the cost estimation process.
  1. The purpose of sub-contracting projects during the construction process.
  • Improves the Product’s Quality

Subcontracting brings in much expertise from different fields into the construction of the project. Involving the project team of members who are specialized in different fields boosts the final product which is the project being constructed.

  • To Increase Productivity

Subcontracts are well laid out, and each of the subcontractors knows what is exactly is expected of them thus working to achieve the best within that subcontract thus increasing the productivity of the overall project team.

  • To reduce delays.

During the agreements of subcontracting both of the parties who are involved agree on the duration which the task should be done. There are very clearly start and the deadline for the project. All the subcontractors work to ensure that they meet the deadlines thus reducing the delays.

  • The quantity and quality of the materials which are required for the task to be carried out can be full and accurately determined before the construction of the project starts. That gives the client a better idea of how much resources are required for the project to be completed, and during the subcontracting, each of the subcontractors knows the exact amount of materials he or she requires.
  • To ease the control of finances

During the process of subcontracts all the subcontractors are required to present their proposed bill of quantities, and from there the cheapest of them with quality is selected and then financed according to what was on the bill of quantities in that way the finances of the project are controlled and well managed.

  • To eliminate sub-used labour and equipment maintenance.
  • Each of the subcontractors knows exactly the number of employees he/she requires to complete the intended task. Each subcontractor knows how to deal with his/. Her own labour which and equipment which in turn reduces the sub-using different labour at different phases of the project.
  • To allow the main contractor acquire new connections with other contractors while developing the skills which he/she might be lacking in the company. At the same time, the main contractor may decide to sub contract due to lack of resources such as machinery and skilled labour.
  • To give an opportunity for other developing companies to show their capability. Most of the well-developed contractors sometimes they opt to subcontract their projects to the developing contracts to allow them to develop their skills such as in the cases of internship and the industrially based learning for institutions.
  1. Issues of obtaining quotations from a new company or specialist traders.
  • The new company or the specialist trader is likely to come up with an exaggerated bill of quantities whereby the number of materials and labour which will be needed will be wrongly estimated. Thus the bill of quantities which will be obtained will not be able to fully and accurately represent the quantity of the material, labour, time and work which will be done.
  • The obtained quotation cannot be used in the administration of the project because most of the contents which are contained are wrongly calculated.
  • Similar projects which will be carried out cannot use this quotation to estimate the cost and duration of the project because most of the estimations which were carried out were exaggerated.
  • The new company or he specialised trader may be using the rates and standards which one is not used with and in that way it will make it very difficult to interpret the contents of the quotation thus making the quotation to be meaningless.
  • The possibility of the entire project failing is increased due to the poor project administration which may occur due to the poor quotation.
  1. On-costs which are associated with the directly employed labour.
  • Commissions
  • Piece rate wages.
  • Pension contributions
  • Direct labour salaries
  • Payroll tax.
  1. The Conditions of a contract which may have an impact the cost of the project and are included in the bill of quantities.
  • Price variations clauses
  • Validity considerations
  • Payment conditions
  • Penalties
  • Contract change conditions
  1. How to come up with the cost estimation of a project when you do not know the time involved to carry out the work.

In the situation where the cost estimator does not know of any of the techniques which are used to estimate the cost of a project. The best way is to use the analogous method whereby he/she will compare different aspects of the project with the same aspect of their past similar project. From there after comparing the different components of the project with the current project, it is easier to come up with an estimated cost of that project

Another way through which one can calculate the cost of the project is to use the individual judgment and in that case, one is expected to use the knowledge he/she has in the construction sector to come up with the estimation.

Computer programs are another option through which one can easily come up with an estimation of the project cost and duration. The tutorials which can guide one on how to use the programme can be downloaded then followed to enable one to come up with the estimated cost of the project.

References

Justin SweetMarc M. Schneier, Legal Aspects of Architecture, Engineering & the Construction Process (Cengage Learning, 8th Ed, 2015) 120-596.

Thomas E. Usher and Philip Davenport, Fundamentals of Building Contract Management,
UNSW Press, 3rd Ed, 2014) 67-312.

John Mullen and R Peter Davison, Evaluating Contract Claims,( John Wiley & Sons,2nd Ed,2014) 110-222.

Franklin and Andrews, Spoon’s Fabrication Norms for Offshore Structures: A handbook for the oil, gas and petrochemical industries,( CRC Press 1st Ed,2015) 45-294.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2020). Estimating The Cost Of A Front Fence Variation: A Builder's Essay For P10 Format.. Retrieved from https://myassignmenthelp.com/free-samples/cpccbc4004a-identify-and-produce-estimated-costs-for-building-and-construction-projects.

"Estimating The Cost Of A Front Fence Variation: A Builder's Essay For P10 Format.." My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/cpccbc4004a-identify-and-produce-estimated-costs-for-building-and-construction-projects.

My Assignment Help (2020) Estimating The Cost Of A Front Fence Variation: A Builder's Essay For P10 Format. [Online]. Available from: https://myassignmenthelp.com/free-samples/cpccbc4004a-identify-and-produce-estimated-costs-for-building-and-construction-projects
[Accessed 28 April 2024].

My Assignment Help. 'Estimating The Cost Of A Front Fence Variation: A Builder's Essay For P10 Format.' (My Assignment Help, 2020) <https://myassignmenthelp.com/free-samples/cpccbc4004a-identify-and-produce-estimated-costs-for-building-and-construction-projects> accessed 28 April 2024.

My Assignment Help. Estimating The Cost Of A Front Fence Variation: A Builder's Essay For P10 Format. [Internet]. My Assignment Help. 2020 [cited 28 April 2024]. Available from: https://myassignmenthelp.com/free-samples/cpccbc4004a-identify-and-produce-estimated-costs-for-building-and-construction-projects.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close