Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. Managing the project scope is primarily concerned with defining and controlling what is and is not included in the project.

The Project Scope Management processes are:

Plan Scope Management—The process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled.

Collect Requirements—The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.

Define Scope—The process of developing a detailed description of the project and product.

Create WBS—The process of subdividing project deliverables and project work into smaller, more manageable components.

Validate Scope—The process of formalizing acceptance of the completed project deliverables.

Control Scope—The process of monitoring the status of the project and product scope and managing changes to the scope baseline.

Project and Product Overview (Background)

It is a considerable fact to build new constructions in manner to be motivated towards economic growth and development however, proper and effective planning is the only strategy that could lead such projects towards success. This project is about the construction of a drive through super market that will allow the consumers to buy groceries and other products through riding vehicles. The project is one of the big project with vast budget estimation within a year. The proposed project will have 40 order stations under a single roof allowing the consumers with an effective approach for finding the necessary products. This report will be emphasizing on the project management aspects of the project including the necessary deliverables and constraints those could be considered for delivering the successful project.

Construction sites are more vulnerable to risks and issues and hence, proper planning is the only way through which the project can be executed successfully. The considered area for the project was 170000 square feet where the proposed project can be delivered allowing the consumers to buy product even after riding vehicles. The estimated budget without considering the contingency plan is estimated to be $12 million in manner to manage the warehouses, necessary deliverables, and project activities. The project will take one year in manner to complete the construction and allowing the organization to launch the project for public use.

The purpose of the project is to establish a drive through market successfully that can be accessed by the public for buying products and groceries without parking or coming out of the vehicles. It will provide all the products to the consumers via the proposed system on the vehicles itself. In present situation, every consumer want a fast service without altering personal comfort and the proposed project will allow them to get the same services. The development of the project will need the large area land for the development of the specific construction that can meet the demands and traffic of the consumers. The target customers are the individuals who are busy in their personal and professional lives and do not want to spend extra time in parking and ordering. This will provide the necessary products at every counter even in the rush situation and hence, the services can be delivered in an efficient and effective manner. Moreover, the land should be wide enough allowing the vehicles to enter from one side and reach to the entire stores and getout with proper billing system.

Project purpose or Business Need

Following are the objectives those are considerable for the effective and efficient delivery of the project:

  • To fulfil the needs and requirements of the consumers in an efficient and effective manner
  • To allow the consumers shopping to be easy and fast services that can allow them to buy necessary products
  • To develop a drive through supermarket that will allow the consumers to buy the product even through riding the vehicles
  • To propose a system that can allow the consumers to avail the services even in very rush situation
  • To allow consumers to save time from buying groceries after parking and entering the super market

WBS

Task Name

Duration

1

Drive Through Super Market

261 days

1.2

   Second Phase: Planning

7 days

1.2.11

      M1: Completing initial planning and starting work

0 days

1.3

   Third Phase: Execution

218 days

1.3.5

      M2: Land ready for instructions

0 days

1.3.7

      M3: warehouse facility completion

0 days

1.3.9

      M4: completing drive through

0 days

1.3.11

      M5: Retail store completion

0 days

1.3.12

      Electrical and construction activities

11 days

1.3.12.5

         M6: Delivering electrical and other works successfully

0 days

1.4

   Fourth Phase: Project Closure

32 days

1.4.5

      M7: Opening ceremony

0 days

WBS

Task Name

Duration

Start

Finish

1

Drive Through Super Market

261 days

Tue 1/1/19

Tue 12/31/19

1.1

   First phase: Initiation

9 days

Tue 1/1/19

Fri 1/11/19

1.1.1

      Business Analysis

3 days

Tue 1/1/19

Thu 1/3/19

1.1.2

      Market Analysis

3 days

Fri 1/4/19

Tue 1/8/19

1.1.3

      Land finding

2 days

Fri 1/4/19

Mon 1/7/19

1.1.4

      Negotiation on Land acquisition

3 days

Wed 1/9/19

Fri 1/11/19

1.1.5

      Analysing market target

3 days

Wed 1/9/19

Fri 1/11/19

1.1.6

      Scope Identification

2 days

Wed 1/9/19

Thu 1/10/19

1.2

   Second Phase: Planning

7 days

Fri 1/11/19

Mon 1/21/19

1.2.1

      Objectives

2 days

Mon 1/14/19

Tue 1/15/19

1.2.2

      Scope

2 days

Wed 1/16/19

Thu 1/17/19

1.2.3

      Resources

1 day

Fri 1/11/19

Fri 1/11/19

1.2.4

      Budget

2 days

Fri 1/11/19

Mon 1/14/19

1.2.5

      Timeline

1 day

Fri 1/18/19

Fri 1/18/19

1.2.6

      Contractors

2 days

Tue 1/15/19

Wed 1/16/19

1.2.7

      Donors

1 day

Tue 1/15/19

Tue 1/15/19

1.2.8

      contingency plan

1 day

Tue 1/15/19

Tue 1/15/19

1.2.9

      project draft

1 day

Mon 1/21/19

Mon 1/21/19

1.2.10

      draft approval

1 day

Thu 1/17/19

Thu 1/17/19

1.2.11

      M1: Completing initial planning and starting work

0 days

Tue 1/15/19

Tue 1/15/19

1.3

   Third Phase: Execution

218 days

Wed 1/16/19

Fri 11/15/19

1.3.1

      Land approvals

3 days

Wed 1/16/19

Fri 1/18/19

1.3.2

      Site planning

6 days

Mon 1/21/19

Mon 1/28/19

1.3.2.1

         Engineering designs

2 days

Mon 1/21/19

Tue 1/22/19

1.3.2.2

         Engineering resources

2 days

Mon 1/21/19

Tue 1/22/19

1.3.2.3

         Construction materials

3 days

Wed 1/23/19

Fri 1/25/19

1.3.2.4

         Resource transportations

2 days

Wed 1/23/19

Thu 1/24/19

1.3.2.5

         Safety measures

2 days

Fri 1/25/19

Mon 1/28/19

1.3.3

      Stakeholder assigning

2 days

Tue 1/29/19

Wed 1/30/19

1.3.4

      informing stakeholders to execute project

1 day

Thu 1/31/19

Thu 1/31/19

1.3.5

      M2: Land ready for instructions

0 days

Thu 1/31/19

Thu 1/31/19

1.3.6

      Warehouse management

63 days

Fri 2/1/19

Tue 4/30/19

1.3.6.1

         stock requirement analysis

16 days

Fri 2/1/19

Fri 2/22/19

1.3.6.2

         establishment of the pathways

14 days

Mon 2/25/19

Thu 3/14/19

1.3.6.3

         establishing conveyors

16 days

Fri 3/15/19

Fri 4/5/19

1.3.6.4

         Engineering modification

17 days

Mon 4/8/19

Tue 4/30/19

1.3.7

      M3: warehouse facility completion

0 days

Tue 4/30/19

Tue 4/30/19

1.3.8

      Drive through

66 days

Wed 5/1/19

Wed 7/31/19

1.3.8.1

         Designing pathways for vehicles

30 days

Wed 5/1/19

Tue 6/11/19

1.3.8.2

         Establishing conveyors platform

19 days

Wed 6/12/19

Mon 7/8/19

1.3.8.3

         Managing the warehouse and conveyors

17 days

Tue 7/9/19

Wed 7/31/19

1.3.9

      M4: completing drive through

0 days

Wed 7/31/19

Wed 7/31/19

1.3.10

      Retail stores functioning

66 days

Thu 8/1/19

Thu 10/31/19

1.3.10.1

         Storing stocks

15 days

Thu 8/1/19

Wed 8/21/19

1.3.10.2

         Preparation of stocks transfer from warehouse to conveyors

20 days

Thu 8/22/19

Wed 9/18/19

1.3.10.3

         Developing Order System

17 days

Thu 9/19/19

Fri 10/11/19

1.3.10.4

         Developing Billing System

14 days

Mon 10/14/19

Thu 10/31/19

1.3.11

      M5: Retail store completion

0 days

Thu 10/31/19

Thu 10/31/19

1.3.12

      Electrical and construction activities

11 days

Fri 11/1/19

Fri 11/15/19

1.3.12.1

         preparing power supply connections

2 days

Fri 11/1/19

Mon 11/4/19

1.3.12.2

         Establishing motors and electrical components

2 days

Tue 11/5/19

Wed 11/6/19

1.3.12.3

         Assigning separate team for functioning of the components

5 days

Thu 11/7/19

Wed 11/13/19

1.3.12.4

         Assigning technicians and human resources

2 days

Thu 11/14/19

Fri 11/15/19

1.3.12.5

         M6: Delivering electrical and other works successfully

0 days

Fri 11/15/19

Fri 11/15/19

1.4

   Fourth Phase: Project Closure

32 days

Mon 11/18/19

Tue 12/31/19

1.4.1

      Project Documentation

11 days

Mon 11/18/19

Mon 12/2/19

1.4.2

      Learnings gained

7 days

Tue 12/3/19

Wed 12/11/19

1.4.3

      stakeholder releasing

8 days

Thu 12/12/19

Mon 12/23/19

1.4.4

      resource releasing

6 days

Tue 12/24/19

Tue 12/31/19

1.4.5

      M7: Opening ceremony

0 days

Tue 12/31/19

Tue 12/31/19

WBS

Task Name

Duration

Start

Finish

Cost

1

Drive Through Super Market

261 days

Tue 1/1/19

Tue 12/31/19

$11,920,080.00

1.2

   Second Phase: Planning

7 days

Fri 1/11/19

Mon 1/21/19

$18,160.00

1.2.11

      M1: Completing initial planning and starting work

0 days

Tue 1/15/19

Tue 1/15/19

$0.00

1.3

   Third Phase: Execution

218 days

Wed 1/16/19

Fri 11/15/19

$11,831,720.00

1.3.5

      M2: Land ready for instructions

0 days

Thu 1/31/19

Thu 1/31/19

$0.00

1.3.7

      M3: warehouse facility completion

0 days

Tue 4/30/19

Tue 4/30/19

$0.00

1.3.9

      M4: completing drive through

0 days

Wed 7/31/19

Wed 7/31/19

$0.00

1.3.11

      M5: Retail store completion

0 days

Thu 10/31/19

Thu 10/31/19

$0.00

1.3.12

      Electrical and construction activities

11 days

Fri 11/1/19

Fri 11/15/19

$2,623,840.00

1.3.12.5

         M6: Delivering electrical and other works successfully

0 days

Fri 11/15/19

Fri 11/15/19

$0.00

1.4

   Fourth Phase: Project Closure

32 days

Mon 11/18/19

Tue 12/31/19

$57,040.00

1.4.5

      M7: Opening ceremony

0 days

Tue 12/31/19

Tue 12/31/19

$0.00

Deloitte is one of the leading industry around the world and proposing the project in front of them through demonstrating the positive figures could attract them for sponsoring the project being proposed and executed. Deloitte can be the biggest source of funding for this project.

Banks are the greatest source of financial help and so approach can be delivered for the loans in manner to deliver the entire project successfully. The banks should be the highest priority for the sponsorships and funding.

Government can also make an approach towards the development and growth of the Australian economy. Technology and innovation has been always the crucial for the growth and development of the economy and thus, the developed project will be a point of interest for the organization.

WBS

Task Name

Duration

Resource Names

Cost

1

Drive Through Super Market

261 days

$11,920,080.00

1.1

   First phase: Initiation

9 days

$13,160.00

1.1.1

      Business Analysis

3 days

Business Analyst

$840.00

1.1.2

      Market Analysis

3 days

Market Analyst

$960.00

1.1.3

      Land finding

2 days

Civil engineer, Project Manager

$1,760.00

1.1.4

      Negotiation on Land acquisition

3 days

Business Analyst, Civil engineer, Project Manager, Project heads

$3,480.00

1.1.5

      Analysing market target

3 days

Business Analyst, Civil engineer, Project Manager, Project heads

$3,480.00

1.1.6

      Scope Identification

2 days

Civil engineer, Electrical Engineer, Project heads, Project Manager

$2,640.00

1.2

   Second Phase: Planning

7 days

$18,160.00

1.2.1

      Objectives

2 days

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$3,280.00

1.2.2

      Scope

2 days

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$3,280.00

1.2.3

      Resources

1 day

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$1,640.00

1.2.4

      Budget

2 days

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$3,280.00

1.2.5

      Timeline

1 day

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$1,640.00

1.2.6

      Contractors

2 days

Civil engineer, Electrical Engineer, Market Analyst, Project heads, Project Manager

$3,280.00

1.2.7

      Donors

1 day

Project heads, Project Manager

$440.00

1.2.8

      contingency plan

1 day

Project heads, Project Manager

$440.00

1.2.9

      project draft

1 day

Project heads, Project Manager

$440.00

1.2.10

      draft approval

1 day

Project heads, Project Manager

$440.00

1.2.11

      M1: Completing initial planning and starting work

0 days

$0.00

1.3

   Third Phase: Execution

218 days

$11,831,720.00

1.3.1

      Land approvals

3 days

Business Analyst, Market Analyst, Project heads, Project Manager

$3,120.00

1.3.2

      Site planning

6 days

$1,824,520.00

1.3.2.1

         Engineering designs

2 days

Civil engineer, Electrical Engineer, Miscellaneous Materials[1], Project Manager

$302,640.00

1.3.2.2

         Engineering resources

2 days

Civil engineer, Electrical Engineer, Miscellaneous Materials[1], Project Manager

$302,640.00

1.3.2.3

         Construction materials

3 days

Civil engineer, Electrical Engineer, Miscellaneous Materials[1], Project Manager

$303,960.00

1.3.2.4

         Resource transportations

2 days

Civil engineer, Electrical Engineer, Miscellaneous Materials[1], Project Manager, Transportation[1]

$312,640.00

1.3.2.5

         Safety measures

2 days

Civil engineer, Construction resources[1], Electrical Engineer, Project heads, Project Manager

$602,640.00

1.3.3

      Stakeholder assigning

2 days

Civil engineer, Electrical Engineer, Project heads, Project Manager

$2,640.00

1.3.4

      informing stakeholders to execute project

1 day

Project heads, Project Manager

$440.00

1.3.5

      M2: Land ready for instructions

0 days

$0.00

1.3.6

      Warehouse management

63 days

$4,008,680.00

1.3.6.1

         stock requirement analysis

16 days

Business Analyst, Market Analyst, Project heads, Project Manager

$16,640.00

1.3.6.2

         establishment of the pathways

14 days

Civil engineer, Construction Materials[1], Construction resources[1], Electrical Engineer, Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,328,480.00

1.3.6.3

         establishing conveyors

16 days

Civil engineer, Construction Materials[1], Construction resources[1], Electrical Engineer, Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,331,120.00

1.3.6.4

         Engineering modification

17 days

Civil engineer, Construction Materials[1], Construction resources[1], Electrical Engineer, Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,332,440.00

1.3.7

      M3: warehouse facility completion

0 days

$0.00

1.3.8

      Drive through

66 days

$3,288,080.00

1.3.8.1

         Designing pathways for vehicles

30 days

Civil engineer, Construction resources[1], Project Manager, Transportation[1]

$636,400.00

1.3.8.2

         Establishing conveyors platform

19 days

Civil engineer, Construction Materials[1], Construction resources[1], Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,326,720.00

1.3.8.3

         Managing the warehouse and conveyors

17 days

Civil engineer, Construction Materials[1], Construction resources[1], Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,324,960.00

1.3.9

      M4: completing drive through

0 days

$0.00

1.3.10

      Retail stores functioning

66 days

$80,400.00

1.3.10.1

         Storing stocks

15 days

Business Analyst, Project heads, Project Manager

$10,800.00

1.3.10.2

         Preparation of stocks transfer from warehouse to conveyors

20 days

Human labours, Business Analyst, Market Analyst, Project heads, Project Manager, Transportation[1]

$32,400.00

1.3.10.3

         Developing Order System

17 days

Market Analyst, Project heads, Project Manager, Software Engineer

$20,400.00

1.3.10.4

         Developing Billing System

14 days

Market Analyst, Project heads, Project Manager, Software Engineer

$16,800.00

1.3.11

      M5: Retail store completion

0 days

$0.00

1.3.12

      Electrical and construction activities

11 days

$2,623,840.00

1.3.12.1

         preparing power supply connections

2 days

Construction Materials[1], Construction resources[1], Electrical Engineer, Miscellaneous Materials[1]

$1,300,880.00

1.3.12.2

         Establishing motors and electrical components

2 days

Construction Materials[1], Construction resources[1], Electrical Engineer, Miscellaneous Materials[1], Project Manager, Transportation[1]

$1,311,760.00

1.3.12.3

         Assigning separate team for functioning of the components

5 days

Business Analyst, Civil engineer, Electrical Engineer, Project heads, Project Manager

$8,000.00

1.3.12.4

         Assigning technicians and human resources

2 days

Business Analyst, Civil engineer, Electrical Engineer, Project heads, Project Manager

$3,200.00

1.3.12.5

         M6: Delivering electrical and other works successfully

0 days

$0.00

1.4

   Fourth Phase: Project Closure

32 days

$57,040.00

1.4.1

      Project Documentation

11 days

Business Analyst, Civil engineer, Electrical Engineer, Market Analyst, Project Manager, Software Engineer

$25,960.00

1.4.2

      Learnings gained

7 days

Business Analyst, Civil engineer, Electrical Engineer, Market Analyst, Project Manager, Software Engineer

$16,520.00

1.4.3

      stakeholder releasing

8 days

Business Analyst, Market Analyst, Project heads, Project Manager

$8,320.00

1.4.4

      resource releasing

6 days

Business Analyst, Market Analyst, Project heads, Project Manager

$6,240.00

1.4.5

      M7: Opening ceremony

0 days

$0.00

Following are the assumptions those could be considered while considered the proposed project plan for the delivery of the project:

  • The required land will be available for the delivery of the necessary project deliverables
  • The human resources and materials will be available throughout the entire project lifecycle
  • The contractors will be capable of fulfilling the necessary resources for the successful delivery of the project
  • The proposed timeline will be strictly followed in manner to accomplish every activity and sub-activity of the project
  • The contingency plan will be enough for tackling the uncertainties or unwanted events occurring during the project delivery.
  • The decision-making for the implementation and modification of the implemented strategies will be evaluated and delivered in an efficient and effective manner

Following are the constraints of the project based on which the monitoring and evaluation of the project will be proceeded:

  • The timeline for the delivery of entire project lifecycle would be one year starting from 1stJan 2019 to 31st December 2020
  • The estimated budget for the delivery of the project is $ 12 million excluding the contingency plan that can be saved of about 10% of the entire project budget
  • The milestones of the project has been stated in the above report
  • Total quality management strategy will be adopted in manner to make sure that the project delivery is meeting the necessary objectives and of high standard that can fulfil the needs and requirements of the consumers
  • Triple constraint strategy will be adopted in manner to make sure that the project is meeting the estimated constraints

Following risk register will be demonstrating the risks those could be considered in the prior of the project execution in manner to develop the strategies those could be delivered fort the successful delivery of the project:

Sl No.

Risk

Description

Impact

Probability

Mitigation strategies

1

Schedule Altering

There are the possibilities that scheduled get altered if the project is not managed properly

High

High

Proper project planning

2

Budget Altering

The alteration in the schedule will alternatively influence the project budget

Very High

High

Proper project planning

3

Deliverables not meeting

The project might be headed towards another direction and hence, the objectives might not be delivered effectively

High

Low

Continuous monitoring and quality assurance

4

Design issues

The construction project entirely depends on the design and little error can bring a drastic change in the project

Very High

Medium

Proper design after concerning the experienced players

5

Lack in resources

The resource manager might lack in supplying the necessary resources and hence, influencing the entire project

High

Low

Proper and effective resource management

6

Accidents

Construction sites are vulnerable to accidents due to certain human errors those could be an obstacle in running the project in schedule

Medium

Low

Proper and reliable safety measures

7

Transportation

Location of the project is the major factor in this scenario in manner to deliver the project resources efficiently

Low

Very Low

Proper and effective way of the transportation is highly recommended

8

Power supply

The power will the most crucial factor for the deployment of necessary electrical and software work, which should be available throughout the project

High

Very Low

Electrical supply should be available throughout the project along with the backup of power supply

9

Dust

New construction needs digging and building new buildings those would lead towards raising the dust that could possibly influence the pace of the project delivery

Medium

High

Proper safety measures and regular watering at the dusty areas

10

Communication gap

Since this is a big project, large number of stakeholders will be involved and so the communication gap could influence the entire project

Very high

Low

Development of an efficient and effective communication management plan

Following is the list of the team members who will be responsible for the successful delivery of the project in manner to make sure that the project is meeting the estimated objectives and goals:

Resource Name

Name

Max. Units

Std. Rate

Business Analyst

< Please Fill >

200%

$35.00/hr

Market Analyst

< Please Fill >

400%

$40.00/hr

Project Manager

< Please Fill >

400%

$55.00/hr

Civil engineer

< Please Fill >

400%

$55.00/hr

Electrical Engineer

< Please Fill >

400%

$55.00/hr

Human labours

< Please Fill >

100%

$10.00/hr

Project heads

< Please Fill >

400%

$0.00/hr

Software Engineer

< Please Fill >

100%

$55.00/hr

Resource Name

Roles

Responsibilities

Government

Allowance for land acquisition and outsourcing

Allow the better course of approvals

Resource Manager

Manage the resource for the delivery of the project

Provide high quality resources

Donors

Provide necessary funding for the project delivery

Manage the efficient financial help for the delivery of the project

Business Analyst

Analyse the business needs and requirements

Provide better strategies related to business

Market Analyst

Analyse the market needs and requirements

Provide better strategies related to market

Project Manager

Provide the strategies related to the project deliverables and activities

Assign proper and effective roles and responsibilities of every stakeholder involved in the project

Civil engineer

Manage the construction and design objectives

Effective and efficient construction deployment

Electrical Engineer

Manage the electrical related project activities

Make sure that the project is not lagging because of electrical works

Sl No

Stakeholder

Communication purpose

Frequency

Medium

Comments

1

Government

Approval on the necessary topics is necessary to

Four times throughout the project

Mail

-

2

Resource Manager

Resource management

Weekly

Face to face or mobile phone

-

3

Donors

Finance related requirements and objectives

Once in every three months

Mails and face to face

-

4

Business Analyst

Business needs and requirements

Monthly

Face to face

-

5

Market Analyst

Market needs and requirements

Monthly

Face to face

-

6

Project Manager

Manage the project deliverables and objectives

Twice a week

Face to face or video conference

-

7

Civil engineer

Manage the design and construction related objectives

Twice a week

Face to face

-

8

Electrical Engineer

Manage the power supply related objectives and constraints

Once a week

Face to face

-

9

Human labours

Manage the operational activities related to the project

Once a week

Face to face

-

10

Project heads

Considering vital decision-making

Quarterly project accomplishment

Mails or conference calls

-

11

Software Engineer

Manage the ordering, billing and entry systems

Once in two weeks

Face to face

-

Following are the processes those will be followed for the management of the team risk and make sure that the project being delivered is free of the risks and every objective is being delivered without any compromise:

Routine risk identification and analysis: it could be managed through periodic risk assessments those could be adapted for regular identification of the risks in every phase of the project those are considerable of influencing the entire project. It can also be deployed in efficient manner if the process of periodic risk reporting is being delivered from the perspective of the entire team in different ways and in a proper documentation. It will be helpful in tracking the records and the deployed strategies for mitigating the risks or minimizing the impact of the risk to the extent level.

Team Reviews: Nominal group technique can be applied for collecting and analysing the team reviews on certain risks and the implemented strategies for the elimination of the same risk. Comparison of risk ranking is another technique that can be deployed for reaching at a particular point if negotiation where the proposed strategies could be implemented throughout the project.

SCOPE

Action Planning: this is the third process that focuses on the consensus on responsibilities and the mutual understanding between the team members in manner to discuss and implement the necessary strategies those could change the present situation and develop a new environment with less influenced risks. Strategizing the processes and recommendation for the communication gap can be used as a tool for allowing this process to be delivered in efficient and effective manner.

Tracking: it is the next process that will again be helpful I mutual understanding between the team in manner to understand the situations and the mitigation of the strategies through using various tools such as triggers, metrics, and status indicators. It will allow to implement the better strategies those could be helpful in establish a bond and better communication for the accomplishment of the project constraints.

Control: It is the last process and very effective in manner to allow the team to communicate with each other and develop better mutual understanding to accomplish the necessary project deliverables. Risk action and risk correction are some of the tools k0r methods those could be deployed in manner to lead the successful and efficient delivery of the team risk management.

1. Project Summary

Start Date

01/01/2019

Finish Date

12/31/2020

Project Duration

One year

2. Project Goal

Were project goals met?

Yes

The developed project will meet all the objectives if the proposed project management plan is followed in strict manner.

3. Project Deliverables

Were project deliverables met?

Yes

The project deliverables are the milestones as stated in the above report and if the project manager follows the same plan, the deliverables will be provided in an efficient and effective manner.

4. Comments (If any)

Construction project need additional time for developing the strategies and planning that can be accomplished for meeting the objectives and goals set for the project delivery. Learnings gathered will be helpful I implementing the ideas and practices in the future projects.

5. Document Signatures

Name

Title

Description

Signature

Date

< Please fill >

Business Analyst

By signing this document, I acknowledge that the developed project will deliver the business needs

< Please fill >

-

< Please fill >

Market Analyst

By signing this document, I acknowledge that the developed project will deliver the market needs

< Please fill >

-

< Please fill >

Project Manager

By signing this document, I acknowledge that the developed project meets all the objectives and goals of the project

< Please fill >

-

< Please fill >

Civil engineer

By signing this document, I acknowledge that the developed project is feasible as per the construction

< Please fill >

-

< Please fill >

Electrical Engineer

By signing this document, I acknowledge that the developed project meets all the objectives and goals of the project

< Please fill >

-

< Please fill >

Project heads

By signing this document, I acknowledge that the developed project meets all the objectives and goals of the project

< Please fill >

-

< Please fill >

Software Engineer

By signing this document, I acknowledge that the developed project meets all the objectives and goals of the project

< Please fill >

-

References

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. Amacom.

Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E. W., & Gray, C. F. (2015). A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.

Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.

Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.

Leach, L. P. (2014). Critical chain project management. Artech House.

Lock, D. (2017). The essentials of project management. Routledge.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Meredith, J. R., Mantel, S. J., Shafer, S. M., & Sutton, M. M. (2014). Project management in practice. Wiley.

Meredith, J. R., Shafer, S. M., Mantel Jr, S. J., & Sutton, M. M. (2016). Project management in practice. Wiley Global Education.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.

Project Management Institute. (2018). A Guide to the Project Management Body of Knowledge (PMBOK® Guide)-(SIMPLIFIED CHINESE). Project Management Institute.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Steyn, H., Sparrius, A., Dekker, A. H., Kuschke, B., Van Eck, B. P. S., & Visser, K. (2016). Project management: A multi-disciplinary approach. FPM Publishing.

Turner, J. R. (2014). Handbook of project-based management(Vol. 92). New York, NY: McGraw-hill.

Turner, R. (2016). Gower handbook of project management. Routledge.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Walker, A. (2015). Project management in construction. John Wiley & Sons.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2021). Project Scope Management: Processes And Deliverables Essay.. Retrieved from https://myassignmenthelp.com/free-samples/sbm1101-project-management-fundamentals/critical-chain-project-management.html.

"Project Scope Management: Processes And Deliverables Essay.." My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/sbm1101-project-management-fundamentals/critical-chain-project-management.html.

My Assignment Help (2021) Project Scope Management: Processes And Deliverables Essay. [Online]. Available from: https://myassignmenthelp.com/free-samples/sbm1101-project-management-fundamentals/critical-chain-project-management.html
[Accessed 26 April 2024].

My Assignment Help. 'Project Scope Management: Processes And Deliverables Essay.' (My Assignment Help, 2021) <https://myassignmenthelp.com/free-samples/sbm1101-project-management-fundamentals/critical-chain-project-management.html> accessed 26 April 2024.

My Assignment Help. Project Scope Management: Processes And Deliverables Essay. [Internet]. My Assignment Help. 2021 [cited 26 April 2024]. Available from: https://myassignmenthelp.com/free-samples/sbm1101-project-management-fundamentals/critical-chain-project-management.html.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close